Title: Kampulan ACTS
1(No Transcript)
2Introduction
- Context and objectives of the training
- Some definitions
- The Project Cycle at-a-glance
- Phase 1 Assessment Planning
3Context of the PCM training
- Field staff mostly inexperienced and new to the
NGO sector. - Field staff has primary responsibility for
quality aid delivery towards beneficiaries - Save the Chidren is increasingly accountable
towards donors - Opportunity for strenghtening the internal
coordination of project activities
4Objective of the PCM training
- PCM training provides basic understanding of
project-based activities - PCM training provide means and tools for
increased quality of projects - PCM training provides means enabling for stronger
accountability - PCM training underlines the importance of
coordinated actions during all phases of the
project-cycle
5in short
6Scope of the PCM Training
- Provide the general knowledge about project
management - Familiarize with key concepts related to project
management - Familiarize with specific vocabulary related to
project management - Not a Master in project management
7The Laws of Project Management
- When things are going well, something will go
wrong. - When things cant get any worse, they will.
- When things appear to be going better you have
overlooked something. - A carelessly planned project will take 3 times
longer to complete than expected. A carefully
planned project will only take twice as long. - Murphy was an optimist !
8Murphys Law ?
I never had a slice of bread,Particularly large
and wide,That did not fall upon the floor,And
always on the buttered side.
910 Reasons why Projects Fail
- Unclear objectives
- Over-ambitious project goals
- No stakeholder consultation
- Not linked to programme or policy framework
- Rigid targets and processes (inflexible)
- False expectations (optimistic goals to attract
finance) -
- End abruptly and usually too short term
- Driven by aid professionals, not locally
owned - Many projects are not relevant to beneficiaries
- Risks are insufficiently taken into account
10Definition of Project
- An undertaking encompassing a set of tasks or
activities having a definable starting point and
well defined objectives. Each task has a planned
due date and assigned resources - A structure to complete a specific set of
deliverables. A project has a specific begin date
and end date, specific objectives and specific
resources assigned to perform the work -
- A time-bound set of tasks directed to an
overall goal
11Key components of the Project
- Goal identifed objectives
- Activities geared towards completion of goal
- Resources assigned to implementation of
activities - Time-bound defined begining and end-date
12Definition of Program
- A collection of projects that are directed
toward a common goal - A broad framework of goals to be achieved,
serving as a basis to define and plan specific
projects - Umbrella structure established to manage a
series of related projects. The program does not
produce any project deliverables
13Definition of Cycle
- a periodically repeated sequence of events or
phases
14Example
15Example
16Example
17The Laws of Project Management
- When things are going well, something will go
wrong. - When things cant get any worse, they will.
- When things appear to be going better you have
overlooked something. - A carelessly planned project will take 3 times
longer to complete than expected. A carefully
planned project will only take twice as long. - Murphy was an optimist !
18Murphys Law ?
I never had a slice of bread,Particularly large
and wide,That did not fall upon the floor,And
always on the buttered side.
1910 Reasons why Projects Fail
- Unclear objectives
- Over-ambitious project goals
- No stakeholder consultation
- Not linked to programme or policy framework
- Rigid targets and processes (inflexible)
- False expectations (optimistic goals to attract
finance) -
- End abruptly and usually too short term
- Driven by aid professionals, not locally
owned - Many projects are not relevant to beneficiaries
- Risks are insufficiently taken into account
20The phases of the project-cycle
21Phase 1 Assessment Planning
- Assessment
- Project identification
- Planning
- Process of setting objectives/goals, strategies,
procedures and means to meet them
22Phase 2 Implementation Monitoring
- Implementation Actual running of the project
- Monitoring Control of the progressive changes
brought about by the project.
23Phase 3 Evaluation
- Evaluation
- Assessment of an ongoing or completed project,
its design, implementation and results.
24Phase 4 Adaptation
- Adaptation
- Refining of the project according to the results
of the evaluation. May lead discontinuation of
the project.
25Phases of the P-C on a time-line
T
P
Planning
Assessment
Evaluation
Adaptation
Implementation Monitoring
26Break ! 15
27The Assessment stage
28- Assessment
-
- Project
- identification
29Assessment
- Assessment as Need identification ???
- Presentation field rapid assessment method
- Exercise on assessment
30The concept of NEED
- The Maslow Pyramid
- Definitions of NEED
- Interpretation of NEED
31The Maslow Pyramid
32Definitions of NEED
- Describe a basic human need (Maslow pyramid)
- Describe the LACK of a basic human need
- Describe the need for relief assistance or some
other humanitarian intervention
33Interpretation of NEED
- Common mistake Intellectual shortcut leading to
confusion - Needs assessment tend to be combined with the
formulation of the responses - The concept of need as a deficit (lack of) often
leads to define need in terms of goods and
services to offer
34The crux of the matter
- Need based assessment requires a clear
distinction between - - definition of the problem
- - formulation of solutions to it
35Solutions to avoid confusion
- Risk-based assessment
- Need identified as the result (the product) of
actual or imminent threats and vulnerabilities
(threats to life, health, subsistence and
security) - Demand-based assessment
- Need identified as the demand from the
customers regardless of the type of supply that
can be provided by the assessor.
36In short..
- Risk-based assessment
- supplier perspective
- Demand-based assessment customer perspective
37Rights and Needs
- Need-based and right-based approaches are often
in opposition - Statement about rights and needs are different in
kind and incompatibles (Speaking different
languages, comparing apples and pears) - - Need refers to what for programming
- - Right involves a moral and legal claim about
entitlements and helps to identify
responsibilities -
38Assessment - Field Assessment
39Assessment - Exercise
- Split into 3 workgroups 5
- Read Case Study 15
- Produce Assessment report following case study
30 - Present results 30
40Problem Assessment
- The Problem Tree
- Helps to establish the cause/effect relation
between problems
41Problem Assessment Problem Tree
Effect
CORE PROBLEM
Causes
42Exercise -gt Build a Problem Tree
- Split into 3 workgroups 5
-
- Read Case Study 5
- Produce Problem Tree following case study 30
- Present results 30
43Objective Assessment
- The objective Tree
- Convert the problems into positive achievements
through means/ends relationships
44Linking Problems Objectives
Negative
Positive
45Linking Problems Objectives
- Just to kick opened doors
Solutions
Changes
46Objective Assessment The Objective Tree
End
CORE OBJECTIVE
Means
47Exercise - gt Build a Objective Tree
- Split into 2 workgroups 5
-
- Read Case Study 5
- Produce Objective Tree following case study 30
- Present results 30
48Taking Strategic options
Choices
49(No Transcript)
50Assessment Planning The Planning Stage
51(No Transcript)
52The logical framework is
- A blue-print for project planning
- A framework to articulate logically the content
of the project - A tool and just a tool but
- the synthesis of the project proposal
- a requirement from most institutional donors
53Introducing the Logical Framework
Indicators
Evidences
Objectives
Assumptions
Overall objective
Project purpose
Results
Activities
Pre-conditions
54Column OBJECTIVE
Objectives
Indicators
Evidences
Assumptions
The broader why for the project.
Overall objective
The desired change that this project will bring
about.
Project purpose
The project deliverables. What the project will
achieve and leave behind
Results
The things that those involved actually do during
the life of the project to produce the outputs
above.
Activities
means
costs
Pre-conditions
55Objective is
- GOAL
- GOAL is identified specifically according to the
LEVEL of planning
56Example of Objectives
Objectives
The broader why for the project.
Overall objective
The change that this project will bring about
Project purpose
The project deliverables. What the project will
achieve and leave behind
Results
The things that those involved actually do during
the life of the project to produce the outputs
above.
Activities
57Column INDICATORS
Indicators
Evidences
Objectives
Assumptions
what is acceptable performance at each level of
the project objectives.
Overall objective
define the expected Project impact which is what
we evaluate.
Project purpose
information we use to monitor the projects
progress.
Results
Activities
activity level indicators
costs
Pre-conditions
QQT - SMART
58Indicator is
- BENCHMARK
- Standard measuring change in a specific
situation - Standard measuring performance of specific
activities and project - Can be
- Qualitative (based on FACTS)
- Quantitative (based on FIGURES)
- Must be SMART
- S pecific
- M easurable
- A ttainable
- R ealistic
- T ime-bound
59Example of Indicators
Indicators
what is acceptable performance at each level of
the project objectives.
define the expected Project impact which is what
we evaluate.
information we use to monitor the projects
progress.
Information we need to monitor the project at
activity level - workplan
QQT - SMART
60Column EVIDENCES
Indicators
Objectives
Evidences
Assumptions
Where do we go to find the information for
measuring Indicators ??
Overall objective
idem
Project purpose
idem
Results
Activity level Evidences
Activities
means
Pre-conditions
61Evidence is
- PROOF
- Record
- Tangible or intangible
62Example of Evidences
Evidences
Where do we go to find the information for
measuring Indicators ??
Idem at purpose level
Idem at result level
Idem at activity level
63Column ASSUMPTIONS
Indicators
Evidences
Objectives
Assumptions
Overall objective
What assumptions must hold true for the project
purpose being produced
Project purpose
What external risks might prevent project Outputs
resulting in the planned Purpose
Results
What external risks might prevent project
Activities resulting in the planned Outputs ?
Activities
means
costs
Pre-conditions Anything that the host
organization must do/have in place before project
activities can start
64Assumption is
- Proposition or statement accepted as true until
proven otherwise - Help identifying RISKS at an early stage of the
project - Helps managing RISKS under uncertainty
- Often based on IGW
- KILLERs assumptions
65Example of assumptions
Assumptions
What assumptions must hold true for the project
purpose being produced
What external risks might prevent project outputs
resulting in the planned Purpose
What external risks might prevent project
activities resulting in the planned Outputs ?
Pre-conditions Anything that the host
organization must do/have in place before project
activities can start
66Break ! 15
67(No Transcript)
68- Your Logical Framework exercise should yield
something like this
69(No Transcript)
70(No Transcript)
71Planning Preparing the logframe
72Build a Logical Framework - Exercise
- Split into workgroups 5
-
- Produce Logical Framework following case study
90 - Present results 30
73Wrap-up session
- Highlights of the day
- Definition of project cycle management
- 4 phases
- Assessment and planning
- Assessment method
- Problem tree, objective tree, Logical framework
- Participants feed-back and evaluation
74(No Transcript)
75- Assessment Planning
- Implementation Monitoring
- Evaluation
- Adaptation
76Implementation and Monitoring
77Implementation
- In managing the implementation of a project,
objectives play a key role. - Management based on objectives means that
performance is measured only against achieving
the objectives. - If this is done strictly, it will help to show
flaws in the project design (impossible
objectives) or implementation (practical
constraints) at an early stage, when it is still
possible to make adjustments.
78Workplan
- Workplan based on the logical framework
- Workplan is divided according to each objective
- For each objective a responsible person is
assigned -
- List the activities in chronological order, and
give more detail than when preparing the logical
framework. -
- For each objective, list the resources and staff
required.
79Workplan
80Workplan and rollout planning
- Part of the workplan should be a detailed time
plan or rollout planning - List all the activities from the sheets, and add
columns for days, weeks or months.
81Weekly rollout planning
82Workplan and rollout planning Exercise for a 3
months project
- Split into 2 workgroups 5
- Draw a workplan based on the logframe per
objective, breakdown each activity, the
resources, the person responsible and the
deadline 30 - Do the same with weekly rollout planning. 30
- Present results 15
83Implementation and Monitoring
84Definition
- A continuous and systematic processof
recording, collecting, measuring, analysing and
communicating - Monitoring is about one thing
- information
85Why information ?
86Principles for project monitoring
- Focuses on minimal information required for each
level of responsibility - Includes all forms of communication
verbal,written, formal, informal - Uses participatory methods
- Creates an obligation to act on operational and
strategic implications of information received
87Project monitoring tools
- Platforms of exchange
- Flash meeting
- Team/Staff meeting
- Coordination/ Management team meeting
- Board meeting
- Reporting
- Ad hoc report
- Situation report
- Monthly, Quarterly, Annual Report
88Reporting
- Ad hoc Report
- Situation Report
- Monthly Report
- Quarterly Report
- Annual Report
89Phase 3 Evaluation
90Phases of the P-C on a time-line
T
P
Planning
Assessment
Evaluation
Adaptation
Implementation Monitoring
91Definition of Project Evaluation
- An assessment, as systematic and objective as
possible, of an ongoing or completed project,
programme or policy, its design, implementation
and results. -
- The aim is to determine the relevance and
fulfilment of objectives, efficiency,
effectiveness, impact and sustainability.
92Guiding Principles for Project Evaluation
- The main purposes of evaluations are learning and
accountability. - Often referred to as an action oriented
management tool - ethical implications. We need to be aware that
our understandings and beliefs towards what is
right and what constitutes good quality are the
evaluation framework itself reflects the ethical
values the organization holds.
93Type of Evaluation
- Project Management Cycle Evaluations
- Routine evaluations integrated into the project
management cycle. It makes use of the accumulated
monitoring information at the project management
level. -
- Country Program Evaluations
- There is no fixed interval or period after which
such evaluations should take place but there is
usually a specific reason to initiate this type
of evaluation. This could be, for example, to
identify whether or not the organization is
achieving the objectives as stated in the
organizational policy. -
- Thematic Evaluations
- Usually not part of a particular planning cycle,
contrary to the previous types. In principle they
can focus on any topic - Evaluations of the organisational processes
94Evaluation Criterion
- Appropriateness (Relevance)
- Connectedness
- Effectiveness
- Impact
- Coherence
- Coverage
- Efficiency
- Cost-effectiveness
95Appropriateness (Relevant)
- Whether the intervention was appropriate
according to - organization policies
- perception and/or demands of the target
population - national policies
- - timeliness of the response
962. Connectedness
-
- Whether activities of a short-term nature were
carried out in a context which takes longer-term
problems into account. - Also called LRRD in donor jargon for Links
between Relief, Rehabilitation and Development.
973. Effectiveness
-
- Measures the extent to which the project purpose
was achieved and whether this happened on the
basis of the activities and inputs of goods and
services.
984. Impact
-
- Looks at the wider effects on the target
population or the country in general, intended or
unintended, positive and negative, both in the
short and long term.
995. Coherence
- Whether the activities were carried out with an
effective division of labour among the actors,
maximising the comparative advantage of each. - Avoiding gaps and overlap, acknowledging the
responsibilities of all involved -
- The co-ordination of the response(s) is sometimes
indicated as a separate criterion.
1006. Coverage
- The extent to which project activities reached
the specific target population and/or - to what extent the beneficiaries had access to
the services provided by the project.
1017. Efficiency
- Looks at the relation between the verifiable
outputs -qualitative and quantitative- and the
inputs (human, material and financial resources) - It is mainly used to place a value on the
implementation process - The term managerial efficiency is sometimes used
to look at for instance the decision making
process, human resource management, logistics,
financial management, etc.
1028. Cost-effectiveness
- Looks at the relation between costs and effects
or impact - Ex for health projects the intervention in
terms of costs per patient cured, costs per life
saved -
- But, it is seldom feasible to do this type
cost-effectiveness analyses as they are limited
by the same constraints as described under
impact. - Other methods include describing costs per
output, like cost per child immunised.
103Steps for the evaluation process
- Initiating the evaluation
- Defining the purpose
- Defining the scope
- Defining the key-questions
- Choosing the methodology
- Selecting the evaluators
- Planning the evaluation
- Defining the budget
- Follow-up
104Terms of Reference (ToR) for Project Evaluation
- 1. Title for the evaluation
- 2. Responsibilities and lines of communication
- 3. Context and history
- 4. Purpose
- 5. Scope
- 6. Key questions
- 7. Methodology
- 8. Profile of the evaluator(s)
- 9. Planning
- 10. Reporting and debriefing
105Format end of project cycle evaluation report
- Country X Project (name and cost
centre) - By
- EoP evaluation report From Till
-
- 1. SUMMARY (3 pages max.)
- Short description of the project
(purpose, target group, project period, budget,
etc.) - Purpose and approach of the evaluation
- Conclusions and recommendations
-
- 2. CONTEXT, NEEDS AND RESPONSE
- Short description of the project environment
(based on description of the pre-conditions and
assumptions) and changes over time. -
- 3. RESULTS/OUTCOME
- Project Purpose (PP) describe the main objective
of the project . - PP indicator (Planned result) planned target
group, quantity, quality, time and place - Current Value of PP indicator Achieved
results - Constraints/opportunities (Observations PC)
Incl. lessons learned -
106Monitoring - Reviewing - Evaluation
- MONITORING is done continuously to make sure the
project is on track - REVIEWING is done occasionally to see whether
each level of objectives leads to the next one
and whether any changes need to be made to the
project plans - EVALUATION is usually done at the end of the
project to assess its impact.
107Monitoring - Reviewing - Evaluation
Balance input/output managerial efficiency
Measure extend of achievement of PP
108- Monitoring,
- Reviewing and
- Evaluation
-
- each assess indicators at different levels in the
hierarchy of objectives in the logical framework
109Change
What
What
why
Change
What
110(No Transcript)
111(No Transcript)
112(No Transcript)
113Budget monitoring
- Description column insert the labels from the
project budget (opearation, administration costs
and transport costs) - Budget column insert the budget allocated to
the project - Actual Spending column insert how much money
has actually been spent - The variance difference between the Budget and
Actual Spending, expressed as a percentage. - The variance can be positive or negative. If the
variance is high for example, above plus or
minus 10 explain why. If the variance is
positive, say We have not spent the budget
because If the variance is negative, say We
have overspent because
114New Practice in Monitoring and Evaluation
- Video ME
- Video Intro
- Video Example
115Phase 4 Adaptation
116Phase 4 Adapation