Section 5 Ground System Readiness - PowerPoint PPT Presentation

1 / 34
About This Presentation
Title:

Section 5 Ground System Readiness

Description:

PTP version 1.49 tested with Compatibility Test Van (CTV) ... Successfully conducted RF Compatibility test through TDRSS with (Triana) new ... – PowerPoint PPT presentation

Number of Views:186
Avg rating:3.0/5.0
Slides: 35
Provided by: danm2
Category:

less

Transcript and Presenter's Notes

Title: Section 5 Ground System Readiness


1
Section 5 Ground System Readiness
  • ORR Summary
  • Ground Stations
  • Space Network
  • Science Validation Facility
  • Mission Operations Center
  • Flight Software Maintenance Facility
  • Simulations
  • Documentation
  • Remaining Work

. . . Dan Mandl EO-1 Ground System Manager
2
Results of Operational Readiness Review (ORR)
  • Conducted on 10/3/00
  • Chaired by Bill Mack of Code 300 and attended by
    same review board as was present for the Mission
    Operations Review (MOR) and the Flight Operations
    Review (FOR)
  • Attended by Ron Thomas and Ann Merwarth of Red
    Team
  • Review board and attendees agreed with conclusion
    that EO-1 Operations is prepared for launch
  • Actions
  • 1. Check if official license to radiate with new
    transponder frequency was completed
  • 2. Create a combined EO-1/SAC-C Launch Hold
    criteria in time for the MRR
  • Question about whether SAC-C can make McMurdo a
    launch critical ground station
  • 3. Follow-up installation of ground station PTP
    upgrade to version 1.49

3
Operational Launch Constraints
  • EO-1
  • One of the two Northern stations (I.e., Alaska or
    Norway) is green for launch (includes voice and
    data IFs)
  • TDRSS including voice and data lines via White
    Sands
  • Mission Operations Control Center
  • Voice and data lines to VAFB
  • Flight Dynamics Facilities Support (Building 28
    and MOC)
  • SAC-C
  • Requirement of McMurdo as prime ground station
    for launch being worked

4
Ground Stations
  • Successfully conducted final End-to-End Interface
    (T5) Test between MOC and Wallops, Norway, Alaska
    McMurdo on 9/14-15/00
  • Playback recorded EO-1 data from CD through
    system long loop
  • Tested S-Band interfaces with new (Triana)
    frequency
  • PTP version 1.49 tested with Compatibility Test
    Van (CTV)
  • In process of being installed at Wallops
  • To be installed at Svalbard, Alaska and McMurdo
    by 10/13/00
  • Wallops Orbital Tracking Information System
    (WOTIS) 8.4 operational since 05/99
  • Tracking - SCC 3.1.1 for Automated Tracking
    System (ATS)
  • Installed 9/18/00, tested, and is operational at
    Wallops
  • Installed at Svalbard and Alaska -- testing in
    process

5
Ground Stations (continued)
  • Standard Autonomous File Server (SAFS) 1.0
    operational since 05/99 post-pass forwarding of
    recorded engineering data
  • Successfully conducting monthly End-to-End
    Science data flow Simulations (M4) which exercise
    X-band interfaces
  • Ampex tape recorders at Norway, Alaska and
    Wallops
  • Data Quality Monitors (DQM) at Alaska and Wallops
  • RF Compatibility test successfully rerun with
    Triana transponder and Compatibility Test Van
    (CTV) on 9/16/00
  • Not tested through actual stations, rather with
    same equipment which resides on the CTV
  • Assured new frequency at Wallops via spectrum
    analyzer on 9/26/00
  • C-Band tracking ready for launch
  • Service supplied by Air Force

6
Ground Stations (continued)
  • Coordination with SAC-C (co-launch with EO-1)
  • EO-1 to get Svalbard and Alaska 11 meter antennas
    for first 5 orbits
  • SAC-C to get Alaska 8 meter and McMurdo 10 meter
    antennas first few orbits
  • Plan to conduct joint Ground Interface Test and
    Joint Network Simulation between 10/19/00 and
    10/25/00
  • Ground Network loading study conducted and
    reviewed by salient projects to verify that there
    is adequate coverage for EO-1 for LEO and normal
    operations

7
Space Network
  • Successfully conducted RF Compatibility test
    through TDRSS with (Triana) new transponder
    frequency and Compatibility Test Van (CTV) on
    9/16/00
  • Used actual Spacecraft and Triana transponder
  • Tested and performance confirmed at the following
    data rates
  • Telemetry- 2, 4, 6, 8 kbps
  • Command- 2 kbps
  • Successfully suported Launch Simulation on
    9/24-26/00 through TDRSS

8
Other SOMO Services Network
  • NISN
  • All interfaces to ground stations and White Sands
    successfully tested via T5 End-to-End tests
  • Lines to Vandenberg successfully used in Launch
    Simulations
  • Voice
  • 5 required SCAMA lines installed and operational
  • 3 additional SCAMA lines requested for launch, to
    be installed by 10/16/00
  • CSOC ORR to occur on 10/17/00
  • No issues with SOMO

9
Science Planning Processing Overview
  • Instrument teams (MIT/LL, TRW, AC) will perform
    detailed instrument on-orbit calibration and
    performance verification during first 60 days on
    orbit.
  • Detailed list of DCEs have been compiled and
    simulated in mission planning exercises.
  • Major technologies are in the instruments and
    will be validated via paired scene comparison
    with Landsat 7 or special scene requests by
    NRA-selected Science Validation Team (SVT).
  • SVT has provided first draft list of scenes to
    MSO
  • Other technologies (except EFF and PPT) are
    passive requiring only trending data periodically
    to provide necessary validation data.
  • PPT will not be tested until end of mission
  • EFF has detailed plan for moving from semi-auto
    to autonomous mode.
  • XPAA will be utilized operationally, validated
    every 60 days.
  • NRA proposal selection based on creation of a SVT
    to ensure that instrument technologies are
    completely validated and can eventually meet
    future Landsat 8 science requirements
  • Metrics
  • Instrument checkout reports by day 90
  • NRA Validation plans completed by end of mission
    (one year)

10
Science Planning Processing Testing Summary
  • Mission Planning Sims conducted numerous times.
    Exercises the following
  • Ingest and modification of LTAP, ground station
    scheduling, daily scene targeting, constraint
    resolution, command generation and daily load
    generation processes.
  • Sims in Jan, April, May, June, July August and
    Sept
  • One additional sim planned in Oct
  • Continually refining and optimizing process to
    provide greatest return in images over early
    mission (Accelerated Minimal Mission concept)
  • Nine Monthly M4 Science Data Simulations have
    been conducted to date.
  • Verified all Ground Station Interfaces
    (WGS,AGS,SGS)
  • Verified data product output and performance of
    L0 processing system
  • Verified SVF and instrument team interfaces for
    real-time, trended, and playback data
  • M4 simulation planned monthly from now until
    launch
  • One normal operations simulation held which
    coupled together Mission planning and Processing
    system and ran on S/C (during T/V II)

11
MOC (ASIST / FEDS)
  • ASIST 8.1g Operational (includes FEDS) this is
    the launch release
  • Command, telemetry, user interface (includes MOC
    front end)
  • Completed installation and regression testing
    9/20/00
  • Added capabilities from ASIST 8.0
  • Improved load, dump capability
  • Improved playback capability
  • Linux version of ASIST
  • Fix for DR 230 Dual CMS Usage
  • Testing
  • Detailed regression tested by ASIST developers
  • Functional regression testing plus fixes tested
    by FOT
  • Successfully conducted Launch sim 9/24-26/00 (58
    hrs. with S/C)
  • Another launch sim scheduled for 10/00 (58 hours
    with S/C)
  • By launch, total aggregate hours on system will
    exceed 300 hours

12
MOC (Database)
  • DB 2.1 Operational this is the launch release
  • Completed installation and regression testing on
    9/21/00
  • Total number of DBCRs incorporated was 42
  • Incorporate limit changes from T/V II testing
  • Incorporated a few polynomial coefficient
    changes
  • Commented out a few hazardous commands
  • Testing
  • Tested fixes with playback data to trigger
    specific limits
  • Conducted launch simulation 9/24-26/00 (58 hours
    with S/C)
  • Another launch simulation on 10/00 (58 hours with
    S/C)
  • By launch total aggregate hours on DB 2.1 will
    exceed 300 hours

13
MOC (Database)
  • Building procedure that modifies some limits in
    database via STOL procedure
  • Database Change Requests (DBCRs)137, 140, 142,
    143, 151, 152, 155, 156, 163
  • Will be tested by playback data
  • Decided that this would be strategy that we would
    use to incorporate lessons learned from Launch
    Sims and due to the fact that we do not have
    conditional limit capability

14
MOC (MOPSS)
  • MOPSS 6.2 operational this is the launch release
  • Mission Operations Planning and Scheduling System
    (MOPSS)
  • MOPSS 6.1 delivered and installed 8/7/00
  • Found problem and needed to patch to MOPSS 6.2
  • Delivered and installed 9/4/00 tested 9/8/00
  • Testing
  • Benchmark input and output data used and compared
    with previous release for Delta V maneuver, ALI
    AC Solar Cal and Ground Station pass
  • Conducted actual test against S/C for Hyperion
    Solar Cal, Combined Lunar Cal and Combined
    Imaging
  • MOPSS derives database from the MOC database
  • Validated MOPSS translation of MOC database 2.1
    by analysis and usage
  • MOPSS database only builds mnemonic, not binary

15
MOC (MOPSS)
  • MOPSS 6.2 (continued)
  • Testing (continued)
  • Has been used since 8/7/00 for 320 hours for
    6.1/6.2 and since 9/4/00 for 160 hours for 6.2
    only
  • Successfully used for Launch Sim in 9/24-26/00
  • Will be used for 10/00 Launch Sim
  • Total expected hours on MOPSS 6.2 system by
    launch will exceed 300 hours

16
MOC (DPS)
  • DPS 3.0 operational and is launch release
  • Data Processing System (DPS) built with a FEDS
  • Tested during T/V II in End-to-End Science data
    flow
  • End-to-End Science simulation run monthly
  • Total hours on DPS 3.0 will exceed 200 hours by
    launch
  • Benchmark data set available for future
    post-launch release regression testing if needed

17
MOC (FDSS)
18
MOC (FDSS)
19
FDF Readiness
20
S/C to MOC Testingas of 9/28/00(1 of 2)
21
S/C to MOC Testing(2 of 2)
P - Planned
22
MOC Procedure Readiness Status
23
MOC Procedure Readiness
  • Philosophy set forth was that if S/C test time
    available and CCB determines that there is a
    decrease in mission if procedure mod implemented
    then CCB approved changes
  • 11 Procedures (one command procedure) still to be
    tested on 10/11/00 (per DBCR)
  • Discovered in contingency review as needed
    commands
  • Philosophy became that all operations in MOC are
    via STOL procedure therefore had to transform
    extra commands in procedures into one command
    STOL procedures
  • Modify and test additional procedures on 10/11/00
    with S/C due to lessons learned in Launch Sim and
    Contingency Review per 13 approved DBCRs

24
FSW Maintenance Facility Readiness
  • Tools to create patches frozen
  • M5 diff-s3R
  • Conv_s3R
  • RSN-ftf.jar
  • Facility and equipment are ready
  • Facility provides capability to simulate and test
    patches before uploads
  • Facility provides capability to test procedure
    changes prior to operational use
  • Items to be completed
  • ACE Safe Hold Mode (SHM) Open Loop
    Testing 10/06/00
  • ACS / ACE SHM Closed Loop Testing 10/18/00
  • SHM Test Review Meeting 10/20/00
  • FSW patch simulation of all processors conducted
    on 9/23/00

25
FSW Maintenance Facility Readiness
26
Simulations
  • 872 hours of simulation hours expected by launch
  • Types
  • Eight launch simulations
  • Four normal operations simulations
  • Nine End-to-End Science processing simulations
  • Three exclusively contingency simulations,
    although almost all of the launch simulations had
    contingencies
  • one All ground anomalies sim
  • One FSW patch simulation
  • One Tumbling simulations
  • Six Science Planning simulations

27
Simulations
28
Subsystems Exercised with ContingenciesDuring
Launch Simulations as of 9-28-00
Note All simulations specified above were
launch simulations. Sim1 was done with no
contingencies and therefore not listed. Sim 10
still to be conducted. Table illustrates number
of contingencies exercised against a subsystem.
29
Documentation Readiness
  • Key documents to fly EO-1 are the Mission
    Procedure Document (MPD) and the S/C Users Guide
    (SCUG)
  • Both are on the EO-1 web site
  • MPD includes
  • Launch script
  • Contingency Procedure document which includes
    escalation procedure
  • Link to the Constraints database
  • Pertinent S/C information and procedures
  • Both documents will reside in hardcopy on console
    during operations and have been used during
    launch simulations

30
Work Remaining
  • Install PTP SW 1.49 at all stations and test
  • ACE Safehold Mode (SHM) Open Loop Testing --
    10/6/00
  • ACS/ACE SHM Closed Loop testing -- 10/18/00
  • Test 11 (1 command ea) STOL procedures derived
    from contingency procedure review by 10/11/00
  • Test procedure that adjusts limits per 11
    approved DBCRs
  • Test procedures per 12 approved DBCRs against
    S/C by 10/11/00
  • Conduct Launch Simulation on 10/12/00
  • Conduct joint Ground Station test and simulation
    with SAC-C by end of Oct 2000
  • Install 3 additional SCAMA lines for launch
  • Conduct part 2 of SADA training by end of Oct
    2000
  • Install extra disks on DPS
  • Conduct M4 simulations to test 8 DCE/day scenario
  • Update Contingency Book to version 6 based on
    lessons learned from launch simulations
  • Create cross reference index for contingency book
    post launch
  • Finalize DTAS configuration

31
EO-1 CSOC Requirements
  • Ground Network
  • Alaska, Svalbard and Wallops stations provide
    S-band and X-band telemetry, command and tracking
    services.
  • McMurdo station provide S-band telemetry and
    command services.
  • Space Network
  • TDRSS provide S-band and telemetry, command and
    tracking services.

32
EO-1 CSOC Requirements(continued)
  • Flight Dynamics Facility (FDF)
  • Provide acquisition data and orbit determination
    during Launch and early orbit (approximately L8
    hours).
  • NASA Integrated System Network (NISN)
  • Provide voice and data lines connectivity to EO-1
    mission ground systems.

33
EO-1 CSOC Status
  • CSOC Resources Status
  • All GN and SN requirements verified through
    End-to-End Interface (T5), Compatibility testing
    and Launch Simulations with the spacecraft and
    MOC.
  • FDF and NISN requirements demonstrated throughout
    testing and simulations.
  • 3 additional voice circuits requested for launch,
    to be installed by 10/16/00.
  • CSOC Readiness
  • CSOC is ready to support EO-1 mission pending
    last GN and SN Network Simulation scheduled
    10/24/00 and 10/25/00 and successful installation
    and checkout of additional voice circuits.

34
EO-1 CSOC Work Remaining
  • GN and SN Network Simulation
  • Conduct simultaneous testing of EO-1 and SAC-C
    spacecraft with Alaska and Svalbard stations
    10/19 and 10/20.
  • Conduct simultaneous Launch and Early Orbit
    simulation of EO-1 and SAC-C spacecraft with GN
    and SN facilities on 10/24 and 10/25.
Write a Comment
User Comments (0)
About PowerShow.com