Title: Section 5 Ground System Readiness
1Section 5 Ground System Readiness
- ORR Summary
- Ground Stations
- Space Network
- Science Validation Facility
- Mission Operations Center
- Flight Software Maintenance Facility
- Simulations
- Documentation
- Remaining Work
. . . Dan Mandl EO-1 Ground System Manager
2Results of Operational Readiness Review (ORR)
- Conducted on 10/3/00
- Chaired by Bill Mack of Code 300 and attended by
same review board as was present for the Mission
Operations Review (MOR) and the Flight Operations
Review (FOR) - Attended by Ron Thomas and Ann Merwarth of Red
Team - Review board and attendees agreed with conclusion
that EO-1 Operations is prepared for launch - Actions
- 1. Check if official license to radiate with new
transponder frequency was completed - 2. Create a combined EO-1/SAC-C Launch Hold
criteria in time for the MRR - Question about whether SAC-C can make McMurdo a
launch critical ground station - 3. Follow-up installation of ground station PTP
upgrade to version 1.49
3Operational Launch Constraints
- EO-1
- One of the two Northern stations (I.e., Alaska or
Norway) is green for launch (includes voice and
data IFs) - TDRSS including voice and data lines via White
Sands - Mission Operations Control Center
- Voice and data lines to VAFB
- Flight Dynamics Facilities Support (Building 28
and MOC) - SAC-C
- Requirement of McMurdo as prime ground station
for launch being worked
4Ground Stations
- Successfully conducted final End-to-End Interface
(T5) Test between MOC and Wallops, Norway, Alaska
McMurdo on 9/14-15/00 - Playback recorded EO-1 data from CD through
system long loop - Tested S-Band interfaces with new (Triana)
frequency - PTP version 1.49 tested with Compatibility Test
Van (CTV) - In process of being installed at Wallops
- To be installed at Svalbard, Alaska and McMurdo
by 10/13/00 - Wallops Orbital Tracking Information System
(WOTIS) 8.4 operational since 05/99 - Tracking - SCC 3.1.1 for Automated Tracking
System (ATS) - Installed 9/18/00, tested, and is operational at
Wallops - Installed at Svalbard and Alaska -- testing in
process
5Ground Stations (continued)
- Standard Autonomous File Server (SAFS) 1.0
operational since 05/99 post-pass forwarding of
recorded engineering data - Successfully conducting monthly End-to-End
Science data flow Simulations (M4) which exercise
X-band interfaces - Ampex tape recorders at Norway, Alaska and
Wallops - Data Quality Monitors (DQM) at Alaska and Wallops
- RF Compatibility test successfully rerun with
Triana transponder and Compatibility Test Van
(CTV) on 9/16/00 - Not tested through actual stations, rather with
same equipment which resides on the CTV - Assured new frequency at Wallops via spectrum
analyzer on 9/26/00 - C-Band tracking ready for launch
- Service supplied by Air Force
6Ground Stations (continued)
- Coordination with SAC-C (co-launch with EO-1)
- EO-1 to get Svalbard and Alaska 11 meter antennas
for first 5 orbits - SAC-C to get Alaska 8 meter and McMurdo 10 meter
antennas first few orbits - Plan to conduct joint Ground Interface Test and
Joint Network Simulation between 10/19/00 and
10/25/00 - Ground Network loading study conducted and
reviewed by salient projects to verify that there
is adequate coverage for EO-1 for LEO and normal
operations
7Space Network
- Successfully conducted RF Compatibility test
through TDRSS with (Triana) new transponder
frequency and Compatibility Test Van (CTV) on
9/16/00 - Used actual Spacecraft and Triana transponder
- Tested and performance confirmed at the following
data rates - Telemetry- 2, 4, 6, 8 kbps
- Command- 2 kbps
- Successfully suported Launch Simulation on
9/24-26/00 through TDRSS
8Other SOMO Services Network
- NISN
- All interfaces to ground stations and White Sands
successfully tested via T5 End-to-End tests - Lines to Vandenberg successfully used in Launch
Simulations - Voice
- 5 required SCAMA lines installed and operational
- 3 additional SCAMA lines requested for launch, to
be installed by 10/16/00 - CSOC ORR to occur on 10/17/00
- No issues with SOMO
9Science Planning Processing Overview
- Instrument teams (MIT/LL, TRW, AC) will perform
detailed instrument on-orbit calibration and
performance verification during first 60 days on
orbit. - Detailed list of DCEs have been compiled and
simulated in mission planning exercises. - Major technologies are in the instruments and
will be validated via paired scene comparison
with Landsat 7 or special scene requests by
NRA-selected Science Validation Team (SVT). - SVT has provided first draft list of scenes to
MSO - Other technologies (except EFF and PPT) are
passive requiring only trending data periodically
to provide necessary validation data. - PPT will not be tested until end of mission
- EFF has detailed plan for moving from semi-auto
to autonomous mode. - XPAA will be utilized operationally, validated
every 60 days. - NRA proposal selection based on creation of a SVT
to ensure that instrument technologies are
completely validated and can eventually meet
future Landsat 8 science requirements - Metrics
- Instrument checkout reports by day 90
- NRA Validation plans completed by end of mission
(one year)
10Science Planning Processing Testing Summary
- Mission Planning Sims conducted numerous times.
Exercises the following - Ingest and modification of LTAP, ground station
scheduling, daily scene targeting, constraint
resolution, command generation and daily load
generation processes. - Sims in Jan, April, May, June, July August and
Sept - One additional sim planned in Oct
- Continually refining and optimizing process to
provide greatest return in images over early
mission (Accelerated Minimal Mission concept) - Nine Monthly M4 Science Data Simulations have
been conducted to date. - Verified all Ground Station Interfaces
(WGS,AGS,SGS) - Verified data product output and performance of
L0 processing system - Verified SVF and instrument team interfaces for
real-time, trended, and playback data - M4 simulation planned monthly from now until
launch - One normal operations simulation held which
coupled together Mission planning and Processing
system and ran on S/C (during T/V II)
11MOC (ASIST / FEDS)
- ASIST 8.1g Operational (includes FEDS) this is
the launch release - Command, telemetry, user interface (includes MOC
front end) - Completed installation and regression testing
9/20/00 - Added capabilities from ASIST 8.0
- Improved load, dump capability
- Improved playback capability
- Linux version of ASIST
- Fix for DR 230 Dual CMS Usage
- Testing
- Detailed regression tested by ASIST developers
- Functional regression testing plus fixes tested
by FOT - Successfully conducted Launch sim 9/24-26/00 (58
hrs. with S/C) - Another launch sim scheduled for 10/00 (58 hours
with S/C) - By launch, total aggregate hours on system will
exceed 300 hours
12MOC (Database)
- DB 2.1 Operational this is the launch release
- Completed installation and regression testing on
9/21/00 - Total number of DBCRs incorporated was 42
- Incorporate limit changes from T/V II testing
- Incorporated a few polynomial coefficient
changes - Commented out a few hazardous commands
- Testing
- Tested fixes with playback data to trigger
specific limits - Conducted launch simulation 9/24-26/00 (58 hours
with S/C) - Another launch simulation on 10/00 (58 hours with
S/C) - By launch total aggregate hours on DB 2.1 will
exceed 300 hours
13MOC (Database)
- Building procedure that modifies some limits in
database via STOL procedure - Database Change Requests (DBCRs)137, 140, 142,
143, 151, 152, 155, 156, 163 - Will be tested by playback data
- Decided that this would be strategy that we would
use to incorporate lessons learned from Launch
Sims and due to the fact that we do not have
conditional limit capability
14MOC (MOPSS)
- MOPSS 6.2 operational this is the launch release
- Mission Operations Planning and Scheduling System
(MOPSS) - MOPSS 6.1 delivered and installed 8/7/00
- Found problem and needed to patch to MOPSS 6.2
- Delivered and installed 9/4/00 tested 9/8/00
- Testing
- Benchmark input and output data used and compared
with previous release for Delta V maneuver, ALI
AC Solar Cal and Ground Station pass - Conducted actual test against S/C for Hyperion
Solar Cal, Combined Lunar Cal and Combined
Imaging - MOPSS derives database from the MOC database
- Validated MOPSS translation of MOC database 2.1
by analysis and usage - MOPSS database only builds mnemonic, not binary
15MOC (MOPSS)
- MOPSS 6.2 (continued)
- Testing (continued)
- Has been used since 8/7/00 for 320 hours for
6.1/6.2 and since 9/4/00 for 160 hours for 6.2
only - Successfully used for Launch Sim in 9/24-26/00
- Will be used for 10/00 Launch Sim
- Total expected hours on MOPSS 6.2 system by
launch will exceed 300 hours
16MOC (DPS)
- DPS 3.0 operational and is launch release
- Data Processing System (DPS) built with a FEDS
- Tested during T/V II in End-to-End Science data
flow - End-to-End Science simulation run monthly
- Total hours on DPS 3.0 will exceed 200 hours by
launch - Benchmark data set available for future
post-launch release regression testing if needed
17MOC (FDSS)
18MOC (FDSS)
19FDF Readiness
20S/C to MOC Testingas of 9/28/00(1 of 2)
21S/C to MOC Testing(2 of 2)
P - Planned
22MOC Procedure Readiness Status
23MOC Procedure Readiness
- Philosophy set forth was that if S/C test time
available and CCB determines that there is a
decrease in mission if procedure mod implemented
then CCB approved changes - 11 Procedures (one command procedure) still to be
tested on 10/11/00 (per DBCR) - Discovered in contingency review as needed
commands - Philosophy became that all operations in MOC are
via STOL procedure therefore had to transform
extra commands in procedures into one command
STOL procedures - Modify and test additional procedures on 10/11/00
with S/C due to lessons learned in Launch Sim and
Contingency Review per 13 approved DBCRs
24FSW Maintenance Facility Readiness
- Tools to create patches frozen
- M5 diff-s3R
- Conv_s3R
- RSN-ftf.jar
- Facility and equipment are ready
- Facility provides capability to simulate and test
patches before uploads - Facility provides capability to test procedure
changes prior to operational use - Items to be completed
- ACE Safe Hold Mode (SHM) Open Loop
Testing 10/06/00 - ACS / ACE SHM Closed Loop Testing 10/18/00
- SHM Test Review Meeting 10/20/00
- FSW patch simulation of all processors conducted
on 9/23/00
25FSW Maintenance Facility Readiness
26Simulations
- 872 hours of simulation hours expected by launch
- Types
- Eight launch simulations
- Four normal operations simulations
- Nine End-to-End Science processing simulations
- Three exclusively contingency simulations,
although almost all of the launch simulations had
contingencies - one All ground anomalies sim
- One FSW patch simulation
- One Tumbling simulations
- Six Science Planning simulations
27Simulations
28Subsystems Exercised with ContingenciesDuring
Launch Simulations as of 9-28-00
Note All simulations specified above were
launch simulations. Sim1 was done with no
contingencies and therefore not listed. Sim 10
still to be conducted. Table illustrates number
of contingencies exercised against a subsystem.
29Documentation Readiness
- Key documents to fly EO-1 are the Mission
Procedure Document (MPD) and the S/C Users Guide
(SCUG) - Both are on the EO-1 web site
- MPD includes
- Launch script
- Contingency Procedure document which includes
escalation procedure - Link to the Constraints database
- Pertinent S/C information and procedures
- Both documents will reside in hardcopy on console
during operations and have been used during
launch simulations
30Work Remaining
- Install PTP SW 1.49 at all stations and test
- ACE Safehold Mode (SHM) Open Loop Testing --
10/6/00 - ACS/ACE SHM Closed Loop testing -- 10/18/00
- Test 11 (1 command ea) STOL procedures derived
from contingency procedure review by 10/11/00 - Test procedure that adjusts limits per 11
approved DBCRs - Test procedures per 12 approved DBCRs against
S/C by 10/11/00 - Conduct Launch Simulation on 10/12/00
- Conduct joint Ground Station test and simulation
with SAC-C by end of Oct 2000 - Install 3 additional SCAMA lines for launch
- Conduct part 2 of SADA training by end of Oct
2000 - Install extra disks on DPS
- Conduct M4 simulations to test 8 DCE/day scenario
- Update Contingency Book to version 6 based on
lessons learned from launch simulations - Create cross reference index for contingency book
post launch - Finalize DTAS configuration
31EO-1 CSOC Requirements
- Ground Network
- Alaska, Svalbard and Wallops stations provide
S-band and X-band telemetry, command and tracking
services. - McMurdo station provide S-band telemetry and
command services. - Space Network
- TDRSS provide S-band and telemetry, command and
tracking services.
32EO-1 CSOC Requirements(continued)
- Flight Dynamics Facility (FDF)
- Provide acquisition data and orbit determination
during Launch and early orbit (approximately L8
hours). - NASA Integrated System Network (NISN)
- Provide voice and data lines connectivity to EO-1
mission ground systems.
33EO-1 CSOC Status
- CSOC Resources Status
- All GN and SN requirements verified through
End-to-End Interface (T5), Compatibility testing
and Launch Simulations with the spacecraft and
MOC. - FDF and NISN requirements demonstrated throughout
testing and simulations. - 3 additional voice circuits requested for launch,
to be installed by 10/16/00. - CSOC Readiness
- CSOC is ready to support EO-1 mission pending
last GN and SN Network Simulation scheduled
10/24/00 and 10/25/00 and successful installation
and checkout of additional voice circuits.
34EO-1 CSOC Work Remaining
- GN and SN Network Simulation
- Conduct simultaneous testing of EO-1 and SAC-C
spacecraft with Alaska and Svalbard stations
10/19 and 10/20. - Conduct simultaneous Launch and Early Orbit
simulation of EO-1 and SAC-C spacecraft with GN
and SN facilities on 10/24 and 10/25.