Title: FPL Group External


1
Impact of the 2004 Hurricanes
Data as of 11/04/04
2
A 56-day Storm Schedule(For illustrative
purposes)
3
Characteristics of Charley
  • Category 4 winds 140 mph
  • Hurricane force winds - 60 miles wide
  • Tropical storm force winds - 210 miles wide
  • Bicoastal event with severe damage in portions of
    west coast area
  • Moved quickly across state hours of impact 20
  • Exited state as a Category 1

4
Characteristics of Frances
  • Category 2 winds 105 mph
  • Hurricane force winds 145 miles wide
  • Tropical storm force winds 345 miles wide
  • Affected whole FPL service territory
  • Widespread but not severe damage
  • Very slow moving - hours of impact 60

Hurricane force winds
Tropical storm force winds
5
Characteristics of Jeanne
  • Category 3 winds 120 mph
  • Hurricane force winds - 125 miles wide
  • Tropical storm force winds 315 miles wide
  • Medium damage to central area and east coast
  • Pockets of severe damage
  • Moved up the state - hours of impact 45

6
Customers Interrupted
7
Approximate Damage to Infrastructure
1 Represents power unit impact, forced offline 2
Plant taken offline, represents damage to overall
facility
8
(No Transcript)
9
Progress during Restoration
Jeanne
Frances
Charley
90 of customers affected by Charley restored by
the 5th day
92 of customers affected by Frances restored by
the 7th day
93 of customers affected by Jeanne restored by
the 5th day
10
  • Peak Energy Use, System wide
  • Summer July 14, 2004 20,545 MW
  • Winter Jan 24, 2003 20,190 MW

FPL Service Area
11
Scherer
(SOU)
St. Johns
Putnam
  • Generating Units 37
  • Nuclear 4 units
    2,939 MW
  • Fossil 33 units 14,183
    MW
  • Peaking Units 1,934
    MW
  • Purchased Power
    3,141 MW
  • Total Generating Capability1
    22,197 MW

Sanford
Cape
Canaveral
Manatee
St
Lucie
Martin
Rivera
Ft
Myers
FPL Generators
Port
Everglades
Cutler
T. Point
1 as of 12/31/03
12
FPL Power Supply1
  • Number of Substations 529
  • Miles of Transmission Lines
  • 500kV 1,105
  • 230kV 2,350
  • 138kV 1,456
  • 115kV 671
  • 69kV 164
  • Total Transmission Miles 5,746 miles

Everglades
1 as of 12/31/03
13
FPL CONTROL CENTERS
DAYTONA DISPATCH OFFICE (DISTRIBUTION)
SARASOTA DISPATCH OFFICE (DISTRIBUTION)
WEST PALM DISPATCH OFFICE (DISTRIBUTION)
SOUTH FLA DISPATCH OFFICE (DISTRIBUTION)
SYSTEM CONTROL CENTER
GOCC
14
(No Transcript)