Title: Managing Risks in Major Construction Contracts
1Managing Risks in Major Construction Contracts
- Professor Rudi Klein, Barrister
- Chief Executive, SEC Group
- AUDE Conference
- 4th April 2007
2Meaning Of Risk
- Risk usually refers to circumstances outside the
direct control of the parties that could have a
positive/negative impact - usually negative - on
the performance of the parties and, therefore,
the project. - Such risks would include for example, acts of
terrorism, weather, collapse or subsidence,
ground conditions, industrial disputes and supply
problems.
3Meaning of Risk (2)
- However, many risks arise as a result of
actions/inactions by project participants (e.g.
insolvencies, delays and disruption, design
defects and non-payment). - Risks also arise from lack of clarity or
definition of roles and responsibilities (e.g.
extent of design responsibility). - Traditional fragmented delivery systems and
hierarchical appointments enhance risk profiles
more interfaces to co-ordinate
4Meaning of Risk (3)External or Macro Risk Factors
(unrelated to the project or its participants)
- Lack of availability of materials
- Capacity issues lack of skilled labour
- Massive increase in energy costs
5Treatment Of Risk In Contracts
- Generally contracts do not use the word risk
risk is transferred via express or implied
obligation - e.g. Section 113, Housing Grants, Construction
and Regeneration Act 1996 pay when paid
provisions passing on insolvency risk.
6Treatment of Risk in Contracts (2)
- There is a distinction between risk and the
consequences thereof this distinction is never
brought out in contracts. The liberal and
widespread use of indemnities ensures that a
party takes responsibility for all the
consequences. - The back to back approach to drafting supply
chain contracts reflects the traditional mindset
in respect of risk transfer.
7Risk and Procurement
- Procurement strategy tends to be overtaken by
considerations of contract will the contract
ensure effective risk transfer? - Decisions on the deployment of resources (i.e.
procurement decisions) most likely to achieve the
clients objectives have a second-place ranking.
8Risk Allocation
- The principle that risk should be allocated to
the party best able to manage it is an alien
concept in construction although broadly
accepted as an economically efficient aim (but a
few clients such as BAA prefer to absorb all
risks on the basis that certainty of where risk
lies is preferable).
9Risk Principle 1 Allocating Risk
Risk, both positive and negative, should be
allocated tan organisation in proportion to the
extent to which it can influence the likelihood
of that risk occurring.
Who can best prevent it?
General Rules
2. If risk can be removed then remove l it 3.
Removal reduction are legal health safety
obligations
1. Ability of organisation to prevent risk
occurring
High
The organisations stake in the consequences of
the risk to motivate the organisation to prevent
the risk happening
10Risk Principle 2 Controlling Risk
Negative risk should be allocated to an
organisation in proportion to the extent to which
the organisation can minimise the consequences if
that risk occurs, with all things being equal,
the second risk principle taking priority
Who can best minimise the consequences of it?
General Rules
2. If risk cannot be removed then control it 3.
For health and safety risks there is a
sequence of controls beginning with design
1. Organisations ability to minimise the
consequences
11Risk The Cost
- Can risks be priced? often an unreal
expectation since it assumes that risk and its
consequences are defined at the outset. - The waste associated with inappropriate or
unclear risk allocation and consequent disputes
is incalculable - contingencies probably run
into billions of pounds.
12Risk The Cost (2)
- Since each party along the supply chain is adding
a contingency the resultant cost to the ultimate
client is likely to be enormous. - Risks and/or their consequences often change
during a project but, traditionally, exploitation
of the opportunities for claims tends to override
effective risk management.
13Risk The Cost (3)
- It is an erroneous assumption that success in
transferring risk has no adverse implications for
the transferor he (and others) may have to deal
with the repercussions of inappropriate risk
transfer.
14(No Transcript)
15Risk The Macro Cost
- Risk/reward dynamics in procurement are of major
importance to the industrys capacity. Any
actions that override the principles of best
practice or attempts to shift unacceptable risks
onto suppliers could be counterproductive and
reduce the ability of the client to procure in
the construction market. - Construction Demand/Capacity Study for OGC
2005-2015, Deloitte June 2006
16NAO REPORT Improving Public Services Through
Better Construction, March 2005
- Departments should have a well developed
capability to identify and manage construction
project risks. Departments need to be more adept
at identifying and considering the potential
strategic impact of risks to the success of a
construction project at its outset and how the
risks should best be managed.
17- Through our workshops we identified that many
clients viewed risk management as an enforced
burdensome process, rather than an essential way
of working, with the emphasis on allocating risks
to suppliers rather than on genuine mitigation. - Source NAO Report
18Design Risks
Design consists of a range of activities
- Achieving functionability and form.
- Producing design drawings/details for approval
and ensuring compatibility. - Selecting materials.
- Complying with performance specifications.
- Ensuring buildability.
19Design Risks (2)
- The major cause of defects lies in design
shortcomings due, primarily, to original design
not working. - This usually means that the out-turn costs are
substantially higher than the original price
(usually 50 higher) - Available research suggests that over 50 of
accidents could have been avoided by a change in
design.
20(No Transcript)
21Design Risks (3)
- Design risks particularly the scope of design
responsibility and the uncertainty about
workability of inherited design is usually
borne by the supply chain. - This is accentuated by lump sum/GMP bids in
response to design information which is usually
incomplete, inaccurate and misleading.
22Example of a GMP Clause
- The GMP shall be the maximum price paid to the
Sub-Contractor for the execution of the Works
howsoever the costs of the Sub-Contractor may
fluctuate or the timing of the Sub-Contract may
vary subject only to a fair and reasonable
proportion (as determined by the Main Contractor
acting reasonably) of additional monies paid or
time granted under the Main Contract. -
23Design Risks (4)
- The case of Nottingham Cooperative Society v.
Henry Boot reinforces the risks associated with
inherited design.
24- Ultimately, in my view, someone who undertakes,
on terms such as those of the Contract., an
obligation to complete a design (emphasis added)
begun by someone else agrees that the result,
however much of the design work was done before
the process of completion commenced (emphasis
added), would have been prepared with reasonable
skill and care. The concept of completion of
design, of necessity, in my judgment, involves a
need to understand the principles underlying the
work done thus far and to form a view as to its
sufficiency. - His Honour Judge Seymour in Co-operative
Insurance Society -v- Henry Boot, TCC, 1July 2002
25Design Risks (5)
- Novation of consultants design to design and
build contractor design footprint set before
supply chain appointed often a recipe for
disaster. - An ME contractor, for example, is unlikely to
have seen the assumptions underlying the
calculations used by the design team.
26Design Risks (6)
- Moreover the design process is not seen as a risk
management process.
27Performance/Completion Risks
- Supply chain is usually allocated the risks
associated with unrealistic completion dates,
programmes and revisions thereto. - The specified performance is still required even
though unrealistic (or virtually non-existent)
time is allocated for testing and commissioning.
28Performance/Completion Risks (2)
- Responsibility for managing and coordinating
interfaces is usually imposed upon members of the
supply chain but they do not have the necessary
authority to discharge such responsibility. - Unrealistic programmes mean that the potential
impact of delays cannot be assessed
realistically.
29Payment Risk
30Payment Risks (2)
- Payment provisions in contacts are usually
structured so that the supply chain assumes the
risk of poor payment performance upstream.e.g.
EPR provisions in PFI Midland Expressway v.
Carillion. - Lack of certainty of entitlement and timing of
payment (e.g. pay what/when certified)
facilitates flexible management (i.e.
manipulation) of the payment process.
31Payment Risks (3)
- Risk of upstream insolvencies is normally borne
by firms lower down the supply chain (s.113.,
Construction Act). - Supply chain retentions are always at risk from
third party default (e.g. architect/engineer,
other sub-contractors and main contractor
default.)
32Actions to Improve Risk Management
33Action 1 Everything starts with getting the
Procurement Strategy right
34Wembley
They cant quite believe that the keys have
been handed over
35Construction Industry v The Rest
5 minutes into the Game it is 0 - 50
36Construction Industry v The Rest
4 more players are brought on. Rate of scoring
slows down. 30 minutes into game score is 0 - 90
37Construction Industry v The Rest
Two more players are brought on before Half Time.
38Construction Industry v The Rest
After half time the whole team is on the pitch
but its too late. Score at full time is 0 - 300
39Procuring the latest Aircraft Carriers (Queen
Elizabeth II Prince of Wales)
40Aircraft Carrier Procurement (A Comparison)
Key User Requirements (or value criteria) Defined
At Outset
- Flexibility (e.g. able to operate different
aircraft) - Deployable anywhere
- Able to Sustain Operations
- Available at all times for operations
- Self-Sufficient (able to maintain aircraft in air
without support from a host nation) - Interoperability (able to communicate effectively
within combined operations)
41Appointment of Delivery Team
- Team selected on basis of evidence of ability to
deliver against user requirements - Team resolves design outcomes to deliver
cost-effective whole life solutions - Team manages risk through the design process and
own decisions on risk allocation - Open-book approach is adopted to drive out
unnecessary costs - Team has pain/gain share arrangements to keep
costs under budget - Manufacture commences once design solutions, risk
decisions and costs all agreed and, therefore,
owned.
42Bring the Team on at the Outset!
- Learning Points
- bring all parties together including end users
and subcontractors, early on in the process, so
they integrate and work to the same ethos.
Relationships are important and there needs to be
the environment of trust where people are talking
and information is flowing. - University of Reading Estates Dept. Windsor
Halls of Residence reported in Building Success
- Constructing Excellence
43Action 2 Use Selection Process to Determine
Attitude to Risk
- Selection of members of delivery team should seek
to identify attitudes to risk - Process of selection should weed out those who
have not given proper consideration to risk issues
44Attitude to Risk Problem
- XYZ University Estates Department is seeking
partners to carry out work on an existing
building where disruption to occupants has to be
avoided.
45Attitude to Risk The Responses
- Disruption is inevitable.
- Operations in existing buildings are fraught but
we can only do our best. - Innovative working methods materials may help
to deal with the problem but client must take on
extra risk. - Additional resources in design and planning from
earliest stage should minimise disruption. - It may be necessary to allow funds for liaising
with occupants to minimise disruption. - Which do you prefer?
46Action 3 Integrated Design Teams
- The key premise behind the integrated project
process is that teams of designers, constructors
and suppliers work together through a series of
projects, continuously developing the product and
the supply chain, eliminating waste in the
delivery process, innovating and learning from
experience. - Sir John Egan, 1998
47Integrated Design Teams
- Where suppliers are involved at an early stage
the quality of designs is better leading to
efficient and higher quality construction.
Departments should involve construction
suppliers early on in the design process, where
appropriate paying for their time on a fee
basis. - (NAO Report, Improving Public Services through
better construction, 15 March 2005)
48Integrated Design Teams
- The Environment Agency considers it obtained a
better engineering solution through early
involvement of specialist engineering
contractors that will last up to 20 years longer
than the initial design, which also has
significant environmental benefits at a saving of
1,120,000 (12) cost of the original solution.
The contractors and consultants considered that
without the early joint working approach the
solution and saving would otherwise not have been
identified. - Page 22, NAO Report, (Case example 17)
49Key Engineering Inputs are not Integrated
Number of projects on which the firm was
appointed at an early stage to engage in the
design process.
Source SEC Group Survey of Specialist
Engineering Contractors Satisfaction on
Government Projects, October 2005
50Integrated Design Teams
- Key suppliers to be appointed as members of the
design team to bring production experience into
risk dialogue. - Clarity of scope of design responsibility
Specialist Engineering Alliance publication - A Design Framework for Building Services
- BSRIA, 2006
- Team to OWN the design.
- Legislative developments new CDM Regs/Part L of
the - Building Regs
51Action 4 Design Out Risks
- The design process should be managed so that risk
is minimised or even designed out. - This means we must focus on design management
skills. - Risk management need not stifle design flair it
can be a stimulus to design innovation.
52Action 5 Genuine Partnering To Encourage Open
Risk Dialogue
Number of projects on which the firm was invited
to enter into a partnering arrangement.
Source SEC Group Survey of Specialist
Engineering Contractors Satisfaction on
Government Projects, October 2005
53Genuine Partnering To Encourage Open Risk Dialogue
- Supply chain to be involved in partnering
arrangements. - Partnering arrangements to be based on trust
partnering bank accounts can generate trust. - With trust risk becomes an issue for the whole
team both in avoiding it and in addressing
consequences should risk materialise.
54Action 6 Improve Risk Management Skills
- Treat risk management as an on-going exercise.
- Have an audit trail to promote active risk
management. - Learn from each project.
- Opportunities for long-term relationships help
improve risk management processes. - Place focus not only on risk but on opportunities
put in place supporting management processes
that shrink risk. - Carry out regular and realistic risk assessments
place actions with parties best able to
mitigate risk.
55Action 7 Use Collaborative Contracts
- There is growing acceptance in the UK that
traditional contractual arrangements are no
longer the best basis for managing today's
high-risk projects. - Engineering construction risks by PA Thompson
JG Perry, SERC research project report, 1992.
56Use Collaborative Contracts That Address Risk
Management (eg. NEC)
- Contractor and PM to give early warning of
matters affecting costs, completion, key dates,
performance of the works in use. - The PM or Contractor may instruct the other to
attend a risk reduction meeting to consider
progress on managing the risk in the Risk
Register. - The Risk Register is regularly updated.
57JCT Constructing Excellence ContractRisk
Allocation Schedule
58Action 8 Project Insurance to Engender Team
Solidity
- Integrated teams enable risk management issues
to be fully addressed by the whole team in an
open and transparent manner. Insurance is an
aspect of risk management. Project insurance
products should be made available to underwrite
the whole team to facilitate integrated working. - Para. 5.18 Accelerating Change, the industrys
improvement agenda launched by Sir John Egan, - Sept. 2002
59Project Insurance
- Pursue the case for project-wide insurance, not
only to reduce costs but also to align behaviours
with principles of integrated team working. - (Improving Public Services through better
construction NAO, March 2005)
60Project Insurance
- Project insurance is an integrated approach to
insuring risk - It is financial loss insurance rather then
liability insurance widely used in Belgium and
increasing in use across Central Europe. - At the outset technical control team assesses the
teams processes for addressing risk. - Projects are now being piloted to test policies.
61Action 9 Project Bank Accounts to Deal with
Payment Risks
- Treasury/OGC/PSCCF support progressive
introduction of project bank accounts. - Payments made from safe receptable direct to
each member of delivery team. - Savings of 2.5 to client on project cost.
62Action 10 Be Innovative in Procurement to Reduce
Risks
- e.g. cradle to grave procurement
- so that design/construction or installation/FM/dis
posals becomes seamless
63Action 11 Select Firms that have Objectively
Demonstrated their Competence to Deliver Can
Deliver against Value Criteria
64A lesson from Wembley
- The overriding conclusion from the research is
that clients and all parties involved in
construction projects and contracts benefit
greatly from reduction in uncertainty prior to
their financial commitment. Money spent early
buys more than money spent late. Willingness to
invest in anticipating risk is a test of a
clients wish for a successful project. - Engineering construction risks. PA Thompson
JG Perry, 1992
65- If you do first what is necessary, then what
is possible, suddenly you will find you are
achieving the impossible. - St. Francis of Assisi