Title: Bidding Strategies
1Bidding Strategies
2Outline of Presentation
- Markup
- Expected Profit
- Cost of Construction
- Maximizing Expected Profit
- Case 1 Single Known Competitor
- Case 2 Multiple Known Competitors
- Case 3 The Average Competitors
- The Use of Bidding Strategies
- Examples of Bidding Strategies
3Markup
- Final action before bidding is adding markup.
- Markup is usually a percentage of the cost.
- All items of job expense, including contingency
and general overhead are already in the
contractors estimate. - Contractor tries to select a markup that will
enable him to bid the largest amount possible and
still be the lowest bidder.
4Markup
- Deciding a good markup is very subjective.
- From past experience various bidding variables
are analyzed competition, type of work,
geographical area, A/E, terms of contract etc. - These variables can give a fair idea of high or
low markup for a particular project.
5Expected Profit
- When contractor bids a lump-sum job, potential
profit of (b-c) is anticipated, where b amount
of bid and c actual cost of work - Probability of successful bid- p is related to
the amount of bid b - Probability of being the lowest bidder (p) is
also related to the expected profit. - Expected/potential profit p(b-c)
6Expected Profit
- Example consider a project with actual cost c
50,000. Suppose the contractor knows that the
probability of 56,000 bid has a probability of
0.3 and that a bid of 53,000 has a probability
of 0.8. - When b56,000
- Expected profit0.3(56000-50000) 1,800
- When b53,000
- Expected profit0.8(53000-50000)2,400
7Expected Profit
- The bid of 53,000 is better because the expected
profit is greater. - The probability of 0.3 and 0.8 is instrumental in
deciding the bid. - Expected profit represents the average return per
bid if the bidding is repeated a large number of
times.
8Cost of Construction
- The cost-c is the actual cost of construction but
unfortunately it cannot be exactly known till the
construction is done. - Cost is an important element of bidding strategy.
- Assumption is made that c is same as the
estimated cost. - Validity of this assumption depends on
contractors past record of bidding accuracy.
9Cost of Construction
10Cost of Construction
- Figure G.1studies the bidding performance of the
contractor. - Vactual construction expenses/estimated cost
- Fig G.1 shows the number of occurrences of V in
each interval of 0.05 - These data is plotted to obtain a histogram as
shown in Fig G.2 and a frequency polygon is drawn
utilizing the midpoints of the horizontal bars of
histogram.
11Cost of Construction
12Cost of Construction
- Smoothed frequency polygon of past bidding
resembles normal distribution of small variance
with mode close to the value V of 1.0 as in curve
A of Fig G.3 then the bidding accuracy is good. - Curve B also has mode close to V1, large
dispersion of values indicate loose estimating - Curve C shows estimating errors leading to
consistent over estimating or under estimating
13Cost of Construction
14Maximizing Expected Profit
- Consider the estimated cost is 200,000
- Assume the probability of success for different
bids as shown in Fig G.4 - Fig G.4 shows that a markup of 5 which gives a
bid of 210,000 yields the maximum expected
profit and thus is the best bid.
15Maximizing Expected Profit
16Case 1 Single Known Competitor
- Before bidding strategy is developed the values
of probability of bidding success must be
determined from historical data. - In this case the contractor knows the competitor
and has experience bidding with this competitor. - Since the bids are opened in public and read
aloud, the past bids of competitors is also
known.
17Case 1 Single Known Competitor
- Suppose using the past data of the competitor A
and the contractor compiles the information as
shown in Fig G.5. - The data is for 62 times the contractor and
competitor A has bid in the same projects in the
last 5-6 years. - RbA/c where bA is the competitor As bid and c
is contractors estimate.
18Case 1 Single Known Competitor
19Case 1 Single Known Competitor
- Probability PA can be computed from data of G.5
- If the contractor bids a ratio b/c 0.98, the
probability that it will underbid competitor A is
1.0 because at no time has A ever bid this low. - If contractor bids at cost (b/c1) there is 1
chance in 62 of being lowest bidder. - Expected profit is obtained from these values
20Case 1 Single Known Competitor
21Case 1 Single Known Competitor
22Case 2 Multiple Known Competitors
- Two known competitors A and B
- Past bidding record of B is analyzed in the same
way as that of A in previous section - Both probabilities of A and B are independent of
each other. We can find the probability of
beating both A and B by multiplying their
probabilities as shown in Fig G.8 - Fig G.9 shows the expected profit when bidding
again both A and B
23Case 2 Multiple Known Competitors
24Case 2 Multiple Known Competitors
25Case 3 The Average Competitor
- Average bidder is hypothetical competitor whose
bidding behavior is a statistical composite of
the behaviors of all competitors. - Collective bidding pattern of competitors can be
obtained by combining all competitors into one
probability distribution. - In Fig G.10, Pav is the probability that the
contractor will submit a bid lower than a single
unknown competitor.
26Case 3 The Average Competitor
27Case 3 The Average Competitor
- If there are 3 unknown competitors than the
probability will be 3 times the probability of
one unknown contractor as they are independent
variables. - Fig G.11 shows that if the markup is 8 then the
probability it will be underbid all three unknown
competitors is (0.51)(0.51)(0.51) which is 0.13. - Fig G.11 also shows expected profit.
28Case 3 The Average Competitor
29The Use of Bidding Strategies
- Bidding involves trying to outguess and outsmart
the competition. - Systematic analysis of past bidding experience is
not common in industry. - Probabilities can be computed for different
categories of projects. - Greater weight could be given to recent bidding
information as compared to old information.
30Examples of Bidding Strategies
- Choose types of projects in which the bidders
company has demonstrated competency. - Advantages of this are
- Owners approval in case of being 2nd lowest
bidder. - Experience reduces construction cost thus reduce
bid. - Competitive prices from sub contractors and
suppliers based on their knowledge of bidders
competency.
31Examples of Bidding Strategies
- Improve and use effectively knowledge of
competitors strengths and weaknesses. - This information can be used as guide for
- Choice of projects to bid
- How competitively to bid
- How much markup to apply to the bare cost.
- How much risk to take.
32Examples of Bidding Strategies
- Favor projects with the least number of bidders.
- This strategy increases the probability of the
contractor to win the bid. - There may be exceptions for example it may be
better to bid for a project with 8 relaxed
competitors as compared to a project with 3
extremely competitive competitors.
33Examples of Bidding Strategies
- Choose those projects that have the highest
profit margin as compared to completion time - This may not increase the probability of low bid
but it may increase the potential of total profit
within an year. - Y creates faster ROI
- Reduces overhead
- Personnel available sooner
34Examples of Bidding Strategies
- Bid as many well selected projects as possible.
- Bidding on increased number of projects increases
the probability of winning more low bids.