Title: Beam Delivery System Risk Issues
1Beam Delivery System Risk Issues
- American Linear Collider Physics Meeting
- SLAC
- January 8th, 2004
2Introduction
- Analyze risks to the LC project completion
- Considered four categories
- Type beam physics engineering production
- Impact impact on luminosity or energy reach
- Time when the problem would be uncovered
- Consequence impact of fixing the problem
- Rankings in each category were then multiplied
together - Risk is evaluated against the design parameters
E Lum. - Risks is based on present evaluation
- Many risks will change as RD progresses
- Only considered a subset of relevant items
broad scope - A total of 40 items for each of US warm and US
cold are listed
3Example 1 SLED-II
- SLED-II Demonstration
- Technology State of the art 4
- Effect linear impact on energy 3
- Time RD Stage 1
- Consequence Back to RD 4
- Total 48
- SLED-II Production
- Engineering Feasible but untested 3
- Effect linear impact on energy 3
- Time PED Stage 2
- Consequence Major rework 3
- Total 54
- SLED-II Operations Example (not actually
included) - Total 36
4Example 2 Active Vibration Suppression
- Demonstration Example (not actually included)
- Technology RD prototypes but extrapolation
remains 3 - Effect impact on luminosity is quadratic or
steeper 4 - Time RD Stage 1
- Consequence Back to RD 4
- Total 48
- Operations
- Engineering Feasible but untested 3
- Effect impact on luminosity is quadratic or
steeper 4 - Time Pre-ops Stage 3
- Consequence Major rework 2
- Total 72
- Many items identified in BDS were high risk
because uncovered late in the project cycle
5Risk Evaluation
- High risks are attached to issues that are not
understood or have not been demonstrated - Risks are high when issues are demonstrated late
in the project cycle - One problem all of us understand the warm better
than cold - Much of cold design is based on the TESLA TDR but
this has lots of known errors (and possibly a few
unknown errors) - I think we overcompensated in an attempt to be
unbiased
- E source target damage
- E source operations impact
- Ions and e-cloud in DR
- DR impedance
- Collimation system efficiency
- Single tunnel LC design
- E source yield
- DR dynamic aperture
- DR tolerances
- Emittance growth in LET
- Head-on collision extraction
- IP feedback
6BDS Risks
- Compiled by Mike Harrison and myself
- Much of the BDS is conventional
- Elements which are more novel include the
superconducting final focusing magnets, the beam
collimators, the vibration suppression systems,
and the fast feedback systems - Beam dynamics issues which is novel are related
to the short bunches, the higher energy, and the
small beam emittances - Operation of the BDS depends on the input beams
- Emittances are designed to be the same
- One significant difference between warm and cold
is the incoming beam jitter - Another difference is the pulse structure
7Table of LC BDS Parameters
8Emittance and Jitter Budgets
- LET simulation codes benchmarked against each
other - Schulte and Walker, PAC 2003 and PT get similar
results for the linacs - 40 growth through the linacs ? round up to 50
- Some BDS tolerances tighter for cold and some
looser - Warm BC more complicated but lower DE/E
- Estimate for De/e larger in cold BC than in warm
but
9LC Environment
Simulation of beam-beam interactiondebris in NLC
IR (e- from left)
Not quite as clean as people might like!
BPM measurements on PEP-IIIR BPMs during abort
gap
10BDS Risks (1)
- Backgrounds 81
- Beam physics Poor or ambiguous data indicates a
problem 3 - Effect linear impact on luminosity 3
- Time Pre-Ops Stage 3
- Consequence Major redesign 3
- Why is there a risk?
- We can model and design extensively now, but,
turn the machine on and ! - This is the experience of most colliding beam
facilities - Hard to fully model all parts of the problem
- The LC is probably in better shape because we are
so concerned - Calculated beam tails are similar in warm and
cold designs at 10-6 of the beam calculations
are incomplete
11BDS Risks (2)
- Final Magnet Stabilization 72 (warm) 0 (cold)
- Engineering/Design Feasible but untested 3
- Effect Quadratic or steeper impact on luminosity
4 - Time Pre-Ops Stage 3
- Consequence Minor redesign 2
- Why is there a risk?
- Natural motion should be less than 20 nm based
on SLD measurements - Want to stabilize at the 0.5 nm level
- Done in other cases but not in the IR environment
- Important for operation (FONT may provide some
backup) - Possible to develop in the lab and build a full
mock-up during the PED phase (there is some risk
associated with the lab development) - However, impossible to fully duplicate actual
installation
12Scenario 1 No stabilization, no FONT, quiet
detector. Scenario 2 No stabilization, need
FONT, noisy detector. Scenario 3 Stabilization,
no FONT, noisy detector.
13BDS Risks (3)
- IP Feedback Implementation 48 (warm) 72
(cold) - Engineering/Design RD prototype 2 (warm)
- Engineering/Design Feasible but untested 3
(cold) - Effect Quadratic or steeper impact on luminosity
4 - Time Pre-Ops Stage 3
- Consequence Minor redesign 2
- Note categories need to be interpreted broadly
- Why is there a risk?
- Absolutely essential for luminosity after a few
seconds - Unprecedented requirements sub-nm accuracy
- Why is cold harder than warm?
- Higher resolution required for the same DL/L
- More complex system multiple interacting
feedbacks
14Beam-Beam Deflection Resolution
- Required resolution is determined by the outgoing
angles - Tolerances are 1.5 2x tighter in cold LC
15Outgoing Distribution
- High disruption makes the outgoing distribution
highly nonlinear - May be difficult to determine centroid
- RF bpms may not work
- It appears that close to maximal luminosity is
attained when the beam-beam deflection centroid
is minimized
16Solenoid and Crossing Angle
- Strong solenoid with the crossing angle will
cause variation of the vertical trajectory with
the horizontal position and with the energy loss - These may degrade theeffective resolution
- Outgoing spectrum hasa large fraction of
beamparticles at less than 50 energy - Low energy particleswill get large
deflectionsand may cause backgrounds
17More Complex Feedback System (1)
- The higher disruption and the larger incoming
beam jitter of the cold LC requires two linked
feedback systems - TDR design has angle feedback 850 meters
upstream of IP - Both angle and position setting change from
pulse-to-pulse - Beam trajectory changes from pulse-to-pulse by
sigma - Impact of BDS wakefields has not been considered
- Trajectory changeswill generate varyingbeam
tails - TDR design has 5 DN/N ? trajectory changes
from bunch-to-bunch
Figure 7.18 from TRC
18More Complex Feedback System (2)
- Changing IP angle through BDS will confuse BDS
drift feedbacks - Drifts feedbacks are required to stabilize the
trajectory at the BDS sextupoles at the sub-um
level - 1-sigma angle change corresponds to 100 um
trajectory change - Cold LC may need intra-train luminosity feedback
as well as position and angle feedback - Require fast luminosity monitor that will not be
impacted by changes in backgrounds - Beamstrahlung spectrum, energy loss, and
deflections are very sensitive to collision
parameters and tails - Higher bandwidth not a fundamental limitation but
complicates implementation - 3 MHz feedback requires significant faster
processing ? much faster BPMs and kickers
19Simulation Results
- Early TDR simulations were incomplete
- Glen White has performed full simulations of
TESLA system - still work in progress - Results published at PAC03 by Schulte, Walker,
White showed an average luminosity of 2.2e34
result below presented at SLAC - Each case depends on trajectory jitter see
Figure 7.18 from TRC - No wakefieldsand no correlationsbetween
backgroundsand trajectory
Nominal L 3.4e34
20Summary
- Many other risk issues identified in BDS
- Collective effects
- Magnet jitter in BDS
- Heating of SC IR magnets
- Collimator performance and MPS limitations
- Aberration tuning procedures
- Crab cavity
- The upper 3.5 items are also issues that can only
really be determined late in the project cycle - Risks in the BDS are high because, although
unlikely, there is significant luminosity impact
and little time for remediation - Given present knowledge, the risks in warm and
cold BDS are very similar