Title: The Interface of Foundation Construction with the Urban Environment
1The Interface of Foundation Construction with the
Urban Environment
- Marco D. Boscardin
- 48th Annual Conference of the Northeast
- States Geotechnical Engineers
- October 23-25, 2007
- Boston, MA
2Courtesy Dr. Sauer Corp.
3Typical Considerations for Underground
Construction in an Urban Setting
- Feasible Methods for Site Conditions.
- Costs vs. Budget.
- Schedule.
- Coordination with Other Work.
4Other Key Items to Consider
- Identification of Events that Pose Risk.
- Potential for Such Events to Occurs.
- How Will Occurrences Affect the Project.
- How to Manage/Control Each Risk.
- Who Owns or Can Best Control Each Risk.
5 Program Includes Methods and Techniques that are
Options to Address and Manage Risk
- Soil Nails
- Jet Grouting
- CFA Piles
- Instrumentation - Monitoring
- MSES/Geofoam Backfill
6Risk In Underground Construction
Nicholson and Architect of the Capitol
7What is Risk?
The combination of the chance of an event or
hazard and its consequence/ project vulnerability.
8Consequences of Risk
Increased Cost Delays Compromised
Safety Unsatisfactory Performance
9Some GeneralTypes of Risk
- Permitting risks
- Financing risks
- Environmental/Ecological risks
- Legal (government and third party) risks
- Market forces risks
- Labor risks
- Exploration risks
- Design risks
- Construction risks
- Operation and Maintenance risks
10Types of Underground Construction Risks
Physical Contract Design Construction
11Physical Risks
Water Obstructions Nature and Extent Environmental
Conditions Corrosion Material Properties
Magnitude and Consistency
12Contractual Risks
Procurement Type Third Party Impacts Third Party
Agreements Permits Contract Interfaces
Coordination
13Design Risks
Assumptions Third Party Input Parameter
Selection Discipline Interfaces Performance
14Construction Risks
Design vs Construction Design Labor, Materials,
Equipment Weather, Politics, Inflation Understandi
ng of Contract, Specification and Design Intent
15How Much Exploration is Enough?
For Permitting For Design For Budgeting and Cost
Estimating For Construction
16(No Transcript)
17Systematic Risk Managment
Deal with Uncertainties Identify Hazards
Early Assess Vulnerability of Various Project
Approaches Involve the Client ID Client Risk
Tolerance
18Risks should be identified in detail
- Name of each risk
- Type of each risk
- Description of each risk
- Estimate of probability of each risk developing.
- Estimate of the impact/consequences/ severity of
condition for each risk should it occur (estimate
cost /delay days).
19- Identify response actions needed to mitigate each
risk. - Identify who is in the best position to
manage/control each risk. - Identify who will be responsible for each
particular risk and that particular risks
management. - Identify what will trigger each risk and the need
for response. - How monitor for each risk and the mitigation of
each risk. - Tolerance to each risk.
- Status of each risk.
20Parties With Roles in Risk Management
Client/Owner Project Manager Designer Contractor
21(No Transcript)
22The Client ( with Project Manager)
Deep Dynamic Compaction
- Sets Objectives
- Risk Tolerance?
- Plays Active Role
- Starts the Risk Management Process
- Understands Can Not Eliminate All Risk
23The Designer
Design in Response to Risk ID Hazards ID
Vulnerability Associated with Each Risk Develop
Risk Register Update Risk Register Communicate
Risk Register
Boulders From Slurry Wall
BCEI
24The Contractor
- RM Starts During Bidding
- Owns a Share of the Risk - MM
- Implements RM in Construction
- Updates RR and Feedback to Des and Owner
Soil Nailed Wall
25The Risk Register
What is it? Who is Responsible for it? How is it
Communicated? How is it Updated?
26The Risk Register
- Data Organization
- Routine Procedure
- ID Potential Risks
- ID Pot. Construction Methods
- Match Risks with Methods
- Rank Risks
27Risk Register Cont.
- Decide Action to Deal with each Risk
- ID Phase Risk Affects
- ID How and By Whom each Risk is to be Managed
- Record Actions to Manage Risk
Tiedback Soldier Pile and Lagging Wall
28Risk Register Cont.
- Reassess Each Risk after Action Taken.
- Update Register Regularly
- Communicate Register with Design Team, Owner,
Contractor, 3rd Party?
Braced Cut for Building
29Risk Analsysis
- ID Risks
- Rank Risks on Prob. Occur/Impact on Project
- Eval. Cost of Risks
- ID how to Reduce Avoid, Manage, Share Risk
- ID Accept. Level of Risk
- ID who acts on and is resp. for each Risk
Mine Subsidence
30Example Occurrence Rating
Probability of Occurrence Rating
Description Improbable 1 Very Rare Not
Likely to Occur Even Once Remote 2 Not
Expected to Occur Even Once Probable 3 Likely
to Occur Once Likely 4 Expected to Occur
More Than Once Frequent 5 Expected to Occur
Often
31Example Vulnerability Rating
Impact Rating Description Very Slight
1 No Delay or Damage Slight
2 Delay up to 2 Days Very
Minor Damage Moderate 3 Up
to1 Week Delay Easily Repairable
Severe 4 1 to 2 Weeks
Delay Significant Repairable
Damage Catastrophic 5 Delays gt 2
Weeks Damage Not Repairable
32Example Risk Tolerance Rating
33Example Risk Register
34Example Risk Register
35Example Risk Register
36Risk Data Sheet
37- A risk register should be developed early in the
conceptualization of a project and be a living
document that is updated throughout the life of
the project as better information is developed
and risks can be better evaluated or eliminated.
38Managing Risks
- Obtain Sufficient Data
- Select Appropriate Technology
- Assess Technology Sensitivity to Uncertainty
- Monitor Performance
- Have Action Levels
- Have Pre-Planned Response Actions
39Relief Holes Along Post-Tensioned Panels
- Control of ground freeze pressures unique
application in U.S.
40(No Transcript)
41Appropriate Technology
- Geologic Conditions
- Hydraulic Conditions
- Environmental Conditions
- Site Constraints
- Condition of Adjacent Structures
- Presence of Sensitive Receptors
42(No Transcript)
43(No Transcript)
4410 St. James
Braced Cut for Building
45(No Transcript)
46(No Transcript)
47(No Transcript)
48Vibratory Roller Compactor
49(No Transcript)
50Vibroflotation Ground Modification
51Deep Dynamic Compaction
52Slurry Wall System
53(No Transcript)
54(No Transcript)
55(No Transcript)
56Sensitivity to Uncertainty
- Obstructions
- Natural
- Human-Derived
- Variations in Ground Conditions
- Contamination
- Conditions at Adjacent Structures
57(No Transcript)
58Soil Nailed Wall
59Monitoring Performance
- ID Appropriate Metrics/Observations
- Automated Data Acquistion and Processing
- Quantity of Data
- Correlating Site Status with Measurements
- Setting Action Levels
- Who Collects? (Owner, CM, Designer, Contractor,
Independent) - Who Evaluates? (Owner, CM, Designer, Contractor,
Independent) - Who Takes Action?
60(No Transcript)
61CLASSIFICATION OF VISIBLE DAMAGE
62(No Transcript)
63Pre-Planned Response
- A form of the Pecks Observational Method.
- Most Probable vs. Most Unfavorable Conditions
Compatible with Data. - Identify in Advance, a Course of Action or Design
Modification for All Foreseeable Significant
Deviation of the Observations or Measurements
from Those Predicted on the Basis of the Working
Hypothesis.
64Building Reinforcement
65Compaction Grouting
66(No Transcript)
67Tiedback Soldier Pile and Lagging Wall
68Underpinning on New Concrete Block
69Wall Underpinning
70Ground Loss During Tunneling Beneath a Road
71(No Transcript)
72QUESTIONS?