PPP Project - PowerPoint PPT Presentation

1 / 31
About This Presentation
Title:

PPP Project

Description:

National Organization for Potable Water and Sanitary Drainage (same ... Responsible for potable water and wastewater treatment operation and maintenance ... – PowerPoint PPT presentation

Number of Views:118
Avg rating:3.0/5.0
Slides: 32
Provided by: sin142
Category:
Tags: ppp | potable | project

less

Transcript and Presenter's Notes

Title: PPP Project


1
PPP Project New Cairo Wastewater Treatment
Plant Investors Conference December 3, 2007
2
Tables of Contents
  • Project Overview
  • Project Description
  • Project Structure
  • Legal Basis for the Transaction
  • Tender Process and Tentative Timeline

3
I. Project Overview
  • Project Management
  • Water and Wastewater Institutions
  • Project Summary
  • Tentative Project Timeline

4
Project Management
Ministry of Investment (MoI)
Ministry of Housing (MHUUD)
Ministry of Finance (MoF)
PPP Unit
Off-taker (NUCA)
Consultants
IFC
Tender/Construction (CAPWO)
Investors
WWTP Project
Operation (The Holding Co.)
Lenders
Regulator (EWRA)
End-users
Planning (GoPP)
5
Water and Wastewater Institutions
6
Project Summary
  • Scope finance, design, construct, start-up,
    operate, maintain, repair, and renew the WWTP.
    Transfer the facility back to GoE at the end of
    the contract
  • Term 20-30 years
  • Capacity initial phase of 250,000 m3/day by end
    of 2010 and second phase (if applicable) of
    250,000 m3/day when justified by demand
  • Payment sewage treatment charge based on
    availability and treatment volumes
  • Grantor Ministry of Housing Utilities Urban
    Development
  • Off-taker New Urban Communities Authority, a
    Government entity.

7
Tentative Project Timeline
Months
Dec 07
Jul 08
2010
Mar 07
Dec 08
Apr 08
Jun 08
Contract Award
Invitation to Bid
Pre-Qualification
WWTP Construction
Data Room
Financial Closing
Bids
WWTP online
8
II. Project Description
  • Service Area
  • Wastewater Flows
  • Wastewater Plant Staging Plan
  • Design Parameters

9
Service Area
X
New Cairo City Extension Zone

3
S1
S-5
Expansionarea
S-3
10
Wastewater Flows
7.34
  • High growth

5.68
Population (millions)
3.27
  • Moderate growth
  • Low growth

11
Wastewater Plant Staging Plan
Scope of the PPP
12
Design Parameters
  • The following table summarizes the influent and
    effluent specifications for key design parameters
  • To be set when agricultural re-use is
    implemented

13
III. Project Structure
  • Scope, Term Site
  • Capacity Phasing
  • SP Operating Obligations
  • Grantor Operating Obligations
  • Monitoring
  • Sewage Treatment Charge
  • Contract Re-equilibrium
  • Force Majeure, Change in Law, Extr. Event
  • Step-in Rights Direct Agreement
  • Termination Clauses
  • Settlement of Disputes

14
Scope, Term Site
  • Financing, design, construction, start-up,
    operation, maintenance, repair and renewal of
    WWTP
  • Handover of facility upon termination
  • Accept Influent Water from Purchaser at Reception
    Point meeting pre-defined specifications
  • Treat and dispose of effluent in compliance with
    performance requirements for treated effluent
  • Treat and dispose of sludge
  • Term 20 to 30 years concession
  • Site Grantor responsible for making site
    available and obtaining authorizations/approvals.

15
Capacity Phasing
  • First stage capacity 250,000 m3/day built in two
    phases
  • 125,000 m3/day mid 2010
  • 125,000 m3/day end of 2010
  • Capacity might be expanded to 500,000 m3/day.

16
SP Operating Obligations
  • OM, repair, replacement and renewal of the WWTP
    to meet Performance Criteria and Good Industry
    Practice
  • Meet performance criteria for effluent water
    provided influent water is within specification
  • Treat and dispose of sludge in compliance with
    environmental norms and Sludge Strategy.

17
Grantor Operating Obligations
  • Ensure Influent Water meets Specifications
  • Operate and maintain Influent Water Pipeline
    System so to not Materially and Adversely
    affect the WWTP
  • Keep SP informed of proposed physical alterations
    to the Influent Water Pipeline System if
    Materially and Adversely affect the WWTP
  • Implement, monitor and enforce a pre-treatment
    program for industrial wastewater
  • Prior to consenting new industrial discharge,
    consult with SP if it can have Material and
    Adverse Effect on SPs treatment process.

18
Monitoring
  • Performance Monitoring Committee made up of
    representatives of Grantor, Service Provider,
    Independent Expert
  • Grantor has right to appoint
  • CAPWO as representative during construction
    phase
  • Holding company as representative during
    operating phase
  • Independent expert to prepare technical elements
    for decisions.

19
Sewage Treatment Charge (STC)
  • STC divided into three components
  • Capital Charge to compensate for the total costs
    of investments, made in designing, constructing
    and starting-up the project (including debt
    service and return on equity)
  • Fixed Operation charge to compensate for fixed
    OM costs, overhead, working capital and
    provisions for replacement or renewal of plant
    and equipment
  • Variable Operation Charge to compensate for
    variable unit OM costs such as chemicals and
    electricity consumption based on volume of
    wastewater treated.
  • Fixed and Variable Operation Charge adjusted for
    inflation (basket of relevant indexes)

20
Contract Re-equilibrium
  • SP may request Grantor to re-examine the STC and
    other terms if one of the following events has
    caused or results in an increase in costs or a
    reduction in revenue
  • Maximum Volumes have been exceeded for 3
    consecutive months
  • Influent Water does not meet Influent Water
    specifications and actual operating costs exceed
    by more than 5 agreed operating costs
  • Grantor initiates Capital Improvements that have
    an impact on SPs costs
  • Grantor imposes new requirements in addition to
    those foreseen in contract.

21
Force Majeure, Direct Change in Law,
Extraordinary Event
  • Force Majeure affecting ability of SP to perform
    its obligations under the contract. Grantor to
    pay only Capital Charge and Fixed Operation
    Charge. Ability to terminate in case of prolonged
    Force Majeure
  • Direct Change in Law that Materially and
    Adversely effects the SP. SP to be compensated
    for losses exceeding 5 of STC collected over a
    period of one quarter
  • Extraordinary Event which causes a Material
    Adverse Effect and whereby SPs performance
    obligations become unduly burdensome. Grantor to
    compensate for actual losses or minimize
    burdensome obligations.

22
Step-in Rights Direct Agreement
  • Lenders to the Project Company will have Step-in
    rights in case of early termination by Grantor
    for Service Provider default
  • Direct Agreement will be signed between the
    Grantor and the Lenders and co-signed by the
    Ministry of Finance
  • The Direct Agreement will include a trapping
    account / proceeds account mechanism. All sums
    payable by the Grantor to the SP will be paid
    through the trapping account.

23
Termination Clauses
  • SP Breach
  • Compensation 90 of senior debt (-) distributed
    dividends (-) cash available after payment of
    outstanding current liabilities (-) insurance
    proceeds
  • Grantor Breach
  • Compensation Senior debt () paid-in equity
    shareholder loans () termination costs () 75
    of expected profits (-) insurance proceeds (-)
    distributed dividends (-) net cash available
    after outstanding current liabilities (-)
    insurance proceeds for lenders
  • Prolonged Force Majeure
  • Compensation Senior Debt outstanding ()
    paid-in equity shareholder loans (-)
    distributed dividends (-) net cash available
    after payment of outstanding current liabilities
    (-) insurance proceeds

24
Settlement of Disputes
  • Notification in writing
  • Parties shall settle any disputes as soon as
    possible by way of negotiations
  • Should negotiations fail, any party can refer the
    dispute to a Technical Review Panel (TRP)
  • Three TRP members (one chosen by SP, another by
    Grantor and third selected by common agreement)
  • Required qualifications pre-defined in contract
  • Panel is to investigate the dispute, write a
    report of findings and submit to each party
  • In case the parties disagree they can submit the
    matter to arbitration under ICC rules (to take
    place in Cairo, Egypt)
  • Governing Law Egyptian Law with international
    provisions.

25
IV. Legal Basis for the Transaction
  • Water and Wastewater Sector Law
  • PPP Law

26
Water and Wastewater Sector Law
  • It is anticipated that a water and wastewater
    sector-specific law will be issued in time for
    the tender
  • MHUDD and MoF have prepared a draft
    sector-specific law for water and wastewater and
    the law will be presented to Parliament soon
  • Such a law would typically exclude the
    application of the Public Utilities Law (Law
    129 of 1947 and Law 61 of 1958) and set forth the
    legal basis for PPP projects in the water and
    wastewater sector.

27
PPP Law
  • Alternatively, a PPP law is being drafted and
    will likely be considered and presented to the
    Parliament during the current parliamentary
    session
  • The PPP Law is expected to provide a one-stop
    shop for PPPs with provisions that could cover
    among other areas
  • - clear list of sectors to be included by
    the Law
  • - identification of the granting
    authorities
  • - creation of clear tender rules for PPPs
    based on international best practice
  • - guidance on the form and content of the
    PPP Contract and
  • - dispute resolution including arbitration
    under International Chamber of Commerce rules.

28
V. Tender Process Tentative Timeline
  • Tender Process
  • Tentative Timeline

29
Tender Process
  • Expression of Interest published in October
    2007
  • Investors Conference organized by MHUUD, MoF
    and MoI on December 3, 2007
  • Invitation for Pre-Qualification to be
    published in December
  • Pre-Qualification to be evaluated on a
    pass/fail basis in January
  • Bidders Due Diligence access to data room,
    ability to ask questions in writing and orally
    during Bidders conferences
  • Tender (once the legal documents are finalized)
  • Technical proposal reviewed first
  • Financial proposal evaluated only if technical
    proposal meets required criteria.

30
Tentative Timeline
31
Thank you
  • Questions?
Write a Comment
User Comments (0)
About PowerShow.com