Title: LONGTERM RESOURCE ADEQUACY: DEMANDRESPONSE OPTIONS
1LONG-TERM RESOURCE ADEQUACYDEMAND-RESPONSE
OPTIONS
- ERIC HIRST
- Consultant in Electric-Industry Restructuring
- Bellingham, WA
- Eric_at_EHirst.com www.EHirst.com
- March 2003
2TWO PRIMARY WAYS TO MANAGE GENERATION ADEQUACY
- Investors, through market prices, decide on
generation retirement, repowering, and new
construction (e.g., pre-2001 California) - RTO or regulator uses LOLP calculations to set
minimum planning reserve requirements RTO may
run market for installed capacity (e.g., PJM, New
York, New England) - ______________
- Market prices include real-time and day-ahead
markets plus bilateral contracts.
3CAN SPOT PRICES DO THE JOB?
- Will demand and supply respond?
- Will prices accurately reflect system conditions
and economics?
4SCARCITY PRICING ESSENTIAL TO MOTIVATE INVESTMENTS
5TWO APPROACHES PRODUCE DIFFERENT OUTCOMES
- Mandated minimum reserve margins will yield
- higher average energy prices
- lower prices during peak-demand periods
- less price volatility
- lower customer load factors
- more peaking capacity
- than would sole reliance on markets to
- make capacity-expansion decisions
6NEW APPROACH vs TRIED AND TRUE
- MARKETS
- Lets market make both capital and operating
decisions (Isnt this why we are restructuring?) - Encourages demand-side participation in
reliability - Lowers costs to consumers
- Price volatility provides important information
- MANDATES
- Reliability in part a public good (Can we trust
market participants to provide enough capacity?) - Demand elasticity low and uncertain
- Major outages very costly
- Customers hate volatility
7PROBLEMS WITH FERCS SMD PROPOSAL
- Concept of long-term resource requirement is
antithetical to competitive markets - What other products are purchased so far ahead of
use with such ambiguous product definition? - For what other products does government mandate
purchase? - FERCs proposed long-term resource adequacy
(LTRA) requirements vague and at odds with other
parts of SMD - FERCs opposition to northeastern ISO ICAP
programs unclear
8UNCERTAINTY OVER RESOURCES INCREASES WITH
FORECAST TIME
Plans
??
Physical resources
9STRAIGHTFORWARD TO INCLUDE DEMAND RESPONSE
- Demand-response resources/programs developed for
shorter term should qualify as long-term
resources - No need to develop new programs for LTRA
- Challenge is to treat demand resources comparably
(not necessarily identically) to supply resources - ISO operating and market rules accommodate supply
idiosyncrasies, need to do same for demand
resources - Reliability requirements need to reflect system
needs, not just generator characteristics
10ISSUES TO CONSIDER ...
- Forecast horizon
- Certification requirements
- Qualifying resources
- Interruptible loads and direct-load control
- Dynamic pricing
- Load participation in contingency-reserve markets
- Energy efficiency
- Seasonal v annual requirements
- RTO role in markets
- End-use infrastructure requirements
- Metering and communications
11 ISSUES TO CONSIDER
- RTO resource rights
- Retail customer/LSE obligations
- Minimum resource size
- Customer baseline level
- Payments
- Capacity
- Energy
- Penalties
- Other ??
12KEY RESOURCE COULD BEDEMAND CURVE FOR RESERVES
13WHICH DEMAND RESOURCES CAN QUALIFY?
- YES
- Interruptible loads and direct-load control
(participants in existing programs) - Bids into contingency-reserve markets
- NO
- Dynamic pricing ? Probably not
- Energy efficiency, passive nature prohibits
system operator dispatch of resource - These resources show up in load forecast
14DEMAND RESPONSE MORE VALUABLE AS LOAD REDUCTION
- Consider LSE with 100 MW peak demand, 15 reserve
requirement, and 10 MW of contracted load
reduction - If the 10 MW qualify as LTRs, then LSE needs
another 105 MW of qualifying resources - If the 10 MW reduce peak demand, then LSE needs
only 103.5 MW of qualifying resources
15METERING AND COMMUNICATIONS DEPENDS ON TYPE OF
RESOURCEWho pays for this equipment?
- Interruptible Load
- Meters hourly
- Communications Receive, confirm, and act upon
RTO instructions (pager, telephone, email, fax) - Does RTO need to know load response in real time?
- Contingency Reserves
- Meters 1-minute
- Communications Receive and act upon RTO dispatch
instructions - Does RTO need to know load response in real time?
16RTO RIGHTS
- Number of times per year (or season)
- Maximum duration of each interruption
- Minimum advance notice
- These limits generally do not apply to generators
and reduce the value of demand resources - Point in emergency sequence (e.g., ISO New
England OP-4) that resource is called
17PAYMENTS AND PENALTIES
- LTRs (both supply and demand) receive
reservation/capacity payments, /MW-month - When dispatched, supply paid for energy at spot
energy price and load does not pay for unconsumed
energy at same price - (Ruff argument, no double payment)
- Noncompliance vs. underperformance penalties
- Stiff noncompliance penalty is quid pro quo for
capacity payments - Underperformance penalty should be cost based
18MY BOTTOM LINE
- LTRA is a political necessity because of aversion
to price spikes, lack of demand response, and
deficiencies in current market designs - LTRA not compatible with competitive wholesale
energy markets - Demand resources can and should qualify as LTRs
and participate in such markets - Build on experience with existing ISO and utility
programs - Ensure comparability with treatment of generation