BASIC SERVICES FOR URBAN POOR APUSP, ANDHRA PRADESH EXPERIENCE - PowerPoint PPT Presentation

1 / 46
About This Presentation
Title:

BASIC SERVICES FOR URBAN POOR APUSP, ANDHRA PRADESH EXPERIENCE

Description:

BASIC SERVICES FOR URBAN POOR APUSP, ANDHRA PRADESH EXPERIENCE. B. ... Urbanization is a worldwide phenomenon and ... Rationalism in decision making. An ... – PowerPoint PPT presentation

Number of Views:1010
Avg rating:3.0/5.0
Slides: 47
Provided by: DEO69
Category:

less

Transcript and Presenter's Notes

Title: BASIC SERVICES FOR URBAN POOR APUSP, ANDHRA PRADESH EXPERIENCE


1
BASIC SERVICES FOR URBAN POOR APUSP, ANDHRA
PRADESH EXPERIENCE
  • B. JANARDHAN REDDY, IAS.,
  • Project Co-ordinator, APUSP
  • 07.06.2007

2
Urbanisation a global phenomenon
  • Urbanization is a worldwide phenomenon and India
    is no exception
  • In western countries industrialization
    necessitated urbanization
  • In India, urbanization is basically a result of
    migration arising out of non availability of
    livelihoods in rural areas
  • Indias low exports and underdeveloped
    manufacturing sector only 25 of its economy
    meant the demand for factory jobs in the cities
    far outstripped the supply.
  • Many migrants eked out work as street vendors,
    construction labourers, day labourers, etc.,

3
Urbanisation of Inida
  • of Urban Population to total population in
    India
  • 17.29 in 1951
  • 27.78 in 2001
  • of Urban Population to total population in
    A.P.
  • 17.42 in 1951 (5.4 Millions)
  • 27.08 in 2001 (20.50 Millions)

4
Pace of Urbanization (Percent of Urban
Population to Total Population)
Source Census of India, Series-29 Andhra Pradesh
Provisional Population Totals, Paper 2 of 2001
5
Challenges of urbanisation
  • Water Supply
  • Sanitation
  • Transportation, Pollution
  • Housing
  • Electricity
  • Land use, growth of slums
  • Health, Education, Social security
  • Unemployment

6
Relevance of APUSP
  • Cities are considered leading engines of Indias
    economic growth contributing up to 40 GDP.
  • However, crumbling infrastructure, deficient
    governance, appalling health and social
    indicators of the poor are chronic problems of
    urban administration
  • Lack of participatory process in urban management
    and acute resource constraint are the basic
    problems
  • The APUSP addressed these basic problems through
    innovative management tools

7
APUSP An Overview
  • Rs.747.22 Crore project
  • supported by DFID of Govt. of U.K on 100 grant
    basis
  • Implementation in Class-1 (1 lakh or more
    population) Municipal towns
  • Project coverage - 32 initially, now extended to
    42
  • Project period Sep., 2000 to March, 2008

8
Original Towns Additional Towns
  • Rs 747.22 crores Grant from DFID of Govt of UK
  • Municipal Reforms
  • (Rs. 121.13 cr)
  • Infrastructure Improvement
  • (Rs. 525.34 cr)
  • Social Development (Rs. 100.75 cr)

9
Project Goal and Coverage
  • The project aims to
  • Stimulate reforms in municipalities
  • Provide environmental infrastructure based on the
    demands of the poor
  • Strengthen the contributions of Civil Societies
    to poverty alleviation
  • Sustained reduction in vulnerability and poverty
    of urban poor.
  • Coverage of 2.88 million poor people in 42 towns

10
ANDHRA PRADESH URBAN SERVICES FOR THE POOR
11
C1 Municipal Reforms
  • Objective Initiation of reforms for Municipal
    Performance Improvement
  • Budget Rs.121.13 Crores
  • Approach
  • People participation
  • Revenue improvement
  • Institutional Development
  • Capacity Building
  • Improved Service Delivery

12
C2 Environmental Infrastructure
  • Objective Infrastructure improvement in urban
    slums
  • Budget Rs.525.34 Crores
  • Approach
  • Water supply improvements
  • Drainage facilities
  • Sanitation improvements
  • Roads footpaths
  • Solid Waste Management
  • Street Lighting

13
C3 Strengthening Civil Society
  • Objective Strengthening of Civil Society
    Organisations
  • Budget Rs.100.75Crores
  • Approach
  • Vulnerability
  • Strengthening of SHGs
  • Livelihoods
  • Health
  • Education

14
CMAPP Cycle
15
The APUSP approach Participatory process
  • Involvement of people at every stage of project
    planning and implementation
  • A programme of the people, for the people and by
    the people
  • A sense of belongingness in stakeholders
  • Common man, especially poor women have a direct
    stake in urban planning

16
The APUSP approach Participatory instruments
  • Introductory Workshops
  • Launch Workshops
  • Strategy Formulation Workshops
  • Micro Planning for prioritisation of
    infrastructure needs
  • Direct participation of over 1 lakh people

17
The APUSP model Indirect approach to poverty
reduction
  • Creation of an enabling environment for
  • The poor to seek more appropriate civic services
  • The ULBs to deliver basic civic services more
    efficiently

18
The APUSP way Integrated development approach
  • Emphasis on linking slums with main towns, rather
    than developing slums on standalone approach
  • A progress on earlier slum improvement projects
    in India which worked in individual slums
  • Linkage with main-town ensured through 6535
    ration between on-site and off-site works

19
The APUSP approach Policy initiatives to
benefit truly deserved
  • Notification of eligible non-notified slums to
    give them equal footing in provision of civic
    services and benefits from other government
    initiatives
  • A difficult process revived after 3 decades with
    objectivity in guidelines
  • Over 500 NNS recommended for notification in 42
    towns

20
The APUSP approach Objectivity in investment
decisions
  • Prioritization of slums on poverty and
    infrastructure deficiency matrix
  • Results
  • Rationalism in decision making
  • An end to discretion
  • Objectivity in allocation of funds to different
    wards, obviating the need for political lobbying
    thereby reducing political frictions
  • Wholehearted support from communities

21
The APUSP approach functionary capacity building
  • Regular trainings to functionaries at all levels
  • Nearly 270 structural trainings organised
  • Over 4.30 lakh SHG women trained
  • Training Needs Analysis in all ULBs
  • Exposure visits
  • Intrastate visits nearing completion
  • Interstate visits being planned

22
The APUSP approach Process Engineering
  • Change Management concept
  • Simplification and standardisation of procedures
  • Kapra model Citizen service centre transparent,
    responsible and timely service delivery
  • Personality Development and motivation trainings
    to functionaries

23
The APUSP approach Institutional capacity
building
  • Computerisation of services
  • systems and networking facilities for
    computerisation of primary data
  • 116 E-seva centers for integrated services
  • Automation
  • Modernisation of office buildings, Record rooms
  • Municipal Knowledge Cells
  • Improved tools is Engg., Town Planning Sanitary
    divisions
  • Internal and external communication systems
  • Comprehensive studies
  • In key engineering areas for strategic planning
    for next 30 years.

24
The APUSP approach Financial stability to ULBs
  • Revenue improvement measures
  • Application of GIS
  • 104 Municipal Accounting years updated
  • 38 years of Audit cleared
  • Revenue Improvement
  • Rs 311 Cr to Rs.852.78 Cr i.e an increase of 265

25
The APUSP approach adoption of emerging
technologies
  • Municipal Base maps
  • GIS application for municipal revenue
    improvements
  • General Town Plan (GTP) for towns

26
The APUSP approach Energy Savings
  • Savings in energy consumption through
  • Optimisation of CMD
  • Avoiding surcharges on low PF
  • Light and Fan (LF) load segregation
  • Avoiding late payment charges
  • Sun-synchronization of street lighting
  • A saving of Rs.11.79 Crores from November, 2005.
    Anticipated savings are Rs.13.03 crore.

27
(No Transcript)
28
The APUSP approach Sensitive support mechanisms
  • Provision of Local Technical Assistance
  • ULBs could hire any professional services from
    open market for a limit period
  • Provision of new professional services on long
    term basis
  • MIPOs/MAFAs/TPRPs/LPAs/DRPs, etc.,
  • Filling of existing gaps
  • Provision of additional COs
  • MHOs, where there are no sanctioned posts
  • D.D. Consultants for Engineering Deptt.

29
The APUSP approach facelift to poor settlements
  • Massive creation of infrastructure in slums
  • Assets created
  • Roads - 749.12 K.Ms
  • Drains - 755.46 K.Ms
  • Street lighting - 112.38 K. Ms
  • Water Supply installations - 642.90 K.Ms
  • UGD - 32.52 K.Ms
  • People benefited
  • 18.93 lakh people in 1487 poor settlements

30
The APUSP approach Empowerment of Women
  • Organisation of poor women into SHGs
  • 49,366 groups with a membership of 6.30 lakhs
  • 90 of 6.96 BPL Households covered
  • Capacity Building of SHG women
  • 4.30 lakh SHG members trained on SHG concepts
  • Financial inclusion of SHG women
  • 41,468 SHGs (84) have been linked with Banks
  • Credit flow of Rs.182.00 Crores
  • Percapita availability of credit Rs.4400/-

31
The APUSP approach a value difference through
micro credit
  • Per capita credit available is Rs.4,400
  • Interest burden _at_3 from the money lenders
    Rs.1512 p.a
  • Interest burden _at_0.25 from the banks
    Rs125/p.a
  • Additional income generated per month Rs125 per
    family.

32
Credit sources of the poor usage pattern
An independent Study in Guntakal
33
The APUSP approach Institutional mechanisms to
empower women
  • Town Level Bankers Committee
  • Closer interface between SHGs and Bankers
  • SHG women on equal footing with credit provider
  • Federation of SHGs
  • At slum level / town level / district level /
    state level
  • Family Budget preparation for SHG women
  • To assess the realistic credit needs and
    affordability of each member
  • To give appropriate credit rating for each group
  • Micro Credit Plan completed for 26,000 SHGs so
    far

34
The APUSP approach Placement linked skill
trainings
  • Objective selection of candidates
  • Analysis of market trends
  • Partnerships with market leaders
  • Demand driven, not supply driven areas
  • Emphasis on placement support
  • Skill trainings for
  • Semi educated in ITES, Hospitality, AC Mechanism,
    BPA, etc.,
  • Construction workers in barbending, masonry,
    heavy machinery operation, plumbing, etc.,
  • Adda coolies in skill improvement
  • About 23,500 trained with placement support

35
The APUSP approach Innovative ways of
addressing vulnerability
  • Physical vulnerability
  • Collectivisation of disabled formation of SHGs
  • Disability assessment linkages with service
    providers
  • Surgical corrections, wherever possible
  • Funding for barrier free access to public
    buildings
  • Social vulnerability
  • Capacity building / trainings
  • Health and Personal Hygiene awareness camps
  • Janasree Arogya Bheema
  • Family Conseling Centres (FCCs)
  • Economic vulnerability
  • Financial inclusion plan / micro credit plan
  • Food Security for SHGs

36
The APUSP approach Creation of baseline data
  • Comprehensive pictorial survey format for
    capturing all socio-economic indices
  • Participatory Poverty Assessments
  • Preparation of Social Development Action Plans
  • Objective prioritization of poor settlements
    become possible

37
The APUSP approach Wealth generation/ Rich
harvest from little investment
  • Skill trainings Expenditure incurred by APUSP
    is around Rs.6.00 Crores, where as benefits
    accrued to individuals is around Rs.35.00 Crores
  • Food security A saving of Rs.200 300/- per
    family per month
  • Disabled welfare 100 surgical corrections worth
    Rs.12.00 lakhs 2.4 Crores
  • Community insurance no capital cost
  • Revenue improvement Rs.30.00 lakhs Rs.6.00
    Cr.
  • Energy savings Rs.45.00 lakhs Rs.9.63 Cr.

38
The APUSP approach Emphasis on cross-learnings
  • APUSP Website www.apusp.org
  • Nagaradeepika monthly newsletter in Telugu and
    English versions
  • Workshops policy orientation with actual
    involvement of stakeholders MAPP workshops
    Visioning workshops
  • Exposure visits intra state and inter state
  • Regular, standardised monthly review meetings

39
The APUSP approach Effective incentive /
disincentive system
  • Challenge fund concept
  • Budgetary constraints for each MAPP and MPC for
    next cycle
  • Incentive to good repayment behaviour Pavala
    vaddi to SHGs
  • Identification of roll models honoring them
    with mementoes

40
The APUSP approach Convergence with other
departments
  • Environmental improvement in schools through SSA
  • Convergence with SERP MEPMA
  • Community health convergence with Health
    Department

41
The APUSP approach Citizen grievance redressal
system
  • District Call Centre for each district
  • Spandana boxes in poor settlements

42
The APUSP approach Improved service delivery
  • Municipal OMs linked to Annual Budgets
  • Municipal Management Modules in 11 areas
  • Internal quality control labs
  • Third Party Quality Assurance
  • Third Party audit of Citizen Charter
    implementation as a parameter of MPC

43
The APUSP approach - Sustainability
  • Mission for Elimination of Extreme Poverty in
    Municipal Areas (MEPMA)
  • Revitalisation of UPA Cells in ULBs
  • Federations of SHGs, Disabled groups, etc.,
  • Continuity of
  • institutions E-sevas, CRCs
  • initiatives MATRIX, MAPP, UPADHI, NNS, etc.,
  • individuals COs and other LTA

44
APUSP What made the difference?
  • Municipal Action Plans broad based decisions
    through Committees and WGs
  • SWOT Analysis leading to problem identification
    and organisational reforms
  • MATRIX of slums facilitating objective decision
    making for infrastructure investment
  • PMLP for identification of non-infrastructure/
    socio-economic needs of poor leading to SDAP
  • MoU to get ownership commitment from ULBs

45
Impact of the project..
  • Pro-poor initiatives of State Govt.
  • Extension of MAPP process to all ULBs
  • Extension of notification process for
    non-notified slums in all ULBs
  • Compulsory earmarking of 40 of Municipal Budget
    for exclusive benefit of slums
  • Adoption of UPADHI programme in all ULBs
  • Extension of water supply distribution network up
    to the doorsteps of urban poor

46
(No Transcript)