Title: Agenda
1Agenda
2Early Involvement and Visibility
- To my knowledge getting safety involved at this
stage is a Lab first. - The primary reason to start now, rather than
after more engineering, is to identify potential
problems at a stage where corrective action is
relatively inexpensive - The timing of this first series of presentations
is driven by the magnet procurement schedule,
thus the goals of this meeting are to - Familiarize the committees with MECO in general
and the magnets in particular - Obtain feedback from the committees that we can
incorporate into the Request For Proposals for a
commercial procurement
3Some Caveats
- A necessary feature of early involvement is that
many areas outside of the magnets have had little
engineering development for lack of funds. - It follows that
- In some cases we will present plans rather than
designs - We are not seeking a formal sign off at this
stage. We simply want to build safety
requirements into the RFP in parallel with the
physics, engineering, QA, and financial
requirements. - If this process of early involvement proves
fruitful, we will use it in other areas as they
reach an appropriate level of maturity (i.e. a
completed CDR in hand).
4MECO Overview
- Michael Hebert
- UC Irvine
- MECO Magnet Safety Meeting
- BNL, June 3, 2003
5 A Four Order of Magnitude Improvement
1
The Sensitivity of Charged Lepton Flavor
Violation Searches by Year
- Goal reach a single event sensitivity of 2 ?
10 17 - Effective mass reach is enormous, e.g. for
leptoquark exchange
10-4
10-8
Sensitivity to Lepton Flavor Violation
?-N ? e- N ? ? e ? ? ? e e e- K0??
? e- K?? ??e-
10-12
MECO Goal
10-16
1940 1950 1960 1970 1980 1990
2000 2010
Year
6MECO Collaboration
- Institute for Nuclear Research, Moscow
- V. M. Lobashev, V. Matushka
- New York University
- R. M. Djilkibaev, A. Mincer,
P. Nemethy, J. Sculli, A.N. Toropin - Osaka University
- M. Aoki, Y. Kuno, A. Sato
- University of Pennsylvania
- W. Wales
- Syracuse University
- R. Holmes, P. Souder
- College of William and Mary
- M. Eckhause, J. Kane, R. Welsh
- Boston University
- J. Miller, B. L. Roberts, O. Rind
- Brookhaven National Laboratory
- K. Brown, M. Brennan, L. Jia, W.
Marciano, W. Morse, Y.
Semertzidis, P. Yamin - University of California, Irvine
- M. Hebert, T. J. Liu, W. Molzon, J.
Popp, V. Tumakov - University of Houston
- E. V. Hungerford, K. A. Lan, L.
S. Pinsky, J. Wilson - University of Massachusetts, Amherst
- K. Kumar
7MECO Project Organization
National Science Foundation RSVP Program Manager
Institutional Board
BNL ALD T. Kirk
Spokesperson W. Molzon
BNL Oversight Committee
Executive Committee
Project Manager M. Hebert
Project Manager Spokesperson
Project Office
Technical Board
ES H Officer W. Meng
Chief Mechanical Engineer
1.1 AGS Mods M. Brennan
1.2 Proton Beam K. Brown
Cost Schedule Manager
Chief Electrical Engineer
1.3 Target Shield TBD
1.4 Solenoids B. Smith
Quality Assurance Officer
1.5 Muon Beam W. Morse
1.6 Tracker E. Hungerford
1.7 Calorimeter J. Sculli
1.8 C R Shield J. Kane
More information in the MECO Project Management
Plan available at http//meco.ps.uci.edu
1.9 DAQ K. Kumar
1.10 Infrastructure TBD
8Features of the Experiment
- 1000fold increase in m beam intensity over
existing facilities - High Z target for improved pion production
- Axially-graded 5 T solenoidal field to maximize
pion capture
Superconducting Solenoids
Muon Beam
1 T
1 T
Calorimeter
2 T
Straw Tracker
Stopping Target Foils
Proton Beam
- Curved transport selects low momentum m-
- Muon stopping target in a 2 T axially-graded
field to improve
conversion e- acceptance - High rate capability e- detectors in a constant 1
T field
2.5 T
5 T
Pion Production Target
9The MECO Magnets
The superconducting solenoids define the critical
path for MECO
- Very detailed CDR completed
- Complete 3D drawing package
- Technical Specification and SOW for commercial
procurement being prepared - Industrial manufacturability studies completed
- Interface engineering ongoing as funds allow
PS
TSu
TSd
DS
- 5 T maximum field
- 150 MJ stored energy
- Uses surplus SSC cable
- Within industry capabilities
- Draft RFP to be released at the end of this
summer
10Magnet Design Management Group
- MDMG advises the Solenoids Subsystem Manager
during oversight of final design, construction,
and installation of the magnets - Chaired by Solenoid Subsystem Manager and
Contracting Officers Technical Representative
B. Smith - A MECO physicist knowledgeable in the detailed
physics requirements of the solenoid system W.
Molzon - A BNL physicist or engineer able to address
interface, installation, and operational issues
for the system on the AGS floor M. Iarocci - MECO Project Manager (advisory) M. Hebert
- BNL AGS Liaison Engineer for MECO (advisory) D.
Phillips - BNL AGS Liaison Physicist and ESH Officer for
MECO (advisory) W. Meng
11The Primary Proton Beam
- Two bunches in the AGS at 180? (?
1.35 ?s) with 20 Tp each (40 Tp
total) to match m lifetime
in stopping target - Slow extraction over 0.5 s in lt 50 ns wide
bunches at g 8 (p 7.5 GeV/c) - 1.0 s cycle time
- Inter-bunch extinction better than 1109
- Hardware addition inside the AGS
- External RF Modulated Magnet
12AGS Inter-Bunch Cleanup Hardware
- Principle Excite coherent vertical betatron
resonance for beam outside the two bunches - Hardware
- Strong AC dipole at 80 kHz
- Fast (100 ns) kickers cancel AC dipole at the
bunches
13Proton Transport Upstream
- RF Modulated Dipole
- Improves extinction diverting inter-bunch beam to
separate beamline - Parameters
- 10 cm gap
- 5 meter magnetic length (6 m total)
-
- Vacuum of order 10-6
- Thick Septum and Thin Septum Lambertson Magnets
- Primary beam passes undeflected
- Empty buckets further bent into extinction beam
line - This is the original B line layout, new A line
layout later today
Pitching Magnet
Lambertsons
External Kicker
14Proton Transport Downstream
- Equipment Protection
- PLC system interlocks beam for flexibility
- Beam loss monitors near PS
- Steering magnet monitors
- Collimator / thick beampipe
- Pitching Magnets
- Extinction Beamline
- Counters sum out of time beam as an extinction
monitor - Originally horizontal, considering vertical
deflection with counters above or below final
dipole
Proton Beam Dump
Production Target
Pitching Magnet
Quads
15Production Region
- Primary beam strikes production target in the
warm bore of the PS - Cu and W heat and radiation shield protects
superconducting PS coils
2.5 T
Proton Beam
5 T
Production Target
Heat Radiation Shield
16Production Target Options
- Radiation-cooled
- Minimal material to absorb pions and reduce MECO
sensitivity - Significant engineering difficulties to overcome
- Water-cooled
- Modest engineering difficulties associated with
handling coolant - Physics concerns due to water jacket material
absorbing pions - Not a critical path system we can study the
water-cooled option now and fall back if
insurmountable difficulties are encountered - Funding limits current effort to physicist
studies in the lab - Once we have engineering at the conceptual design
level another briefing like this on the details
of the target will be appropriate
17Water-cooled Target
- Simulations indicate that 0.5 mm water layer
thickness, 0.5 mm Ti containment wall thickness,
and a 3.0 mm radius target rod cost only 5 of
stopped muons - Supply return pipes double as supports
Water Channel
Au or Pt Target
Ti Shell
Proton Beam
18Target Hydrodynamic Simulations Test
- Hydrodynamic simulations (Masters ME thesis)
demonstrate feasibility of the cooling scheme - Flow rates verified in prototypes
- Induction heating tests have begun to verify
temperatures
Target Center
Target Surface
Water
19Target Installation Concept
- Keystoning in inner W ring captures supply
return pipes - Quick disconnect and flexible supply return
connections - Requires only two axes of translation easing
automation for remote handling
Installation Close-up
Installed Position
Installed Detail
20Transport Region
- Curved solenoid eliminates line-of-sight
transport of photons and
reduces neutron flux - Curvature drift and four collimators sign and
momentum select beam - Thin (replaceable) window separates production
and detector region vacua, conceptual design
completed by AGS engineers
Thin anti-proton stopping window between center
collimators
2.1 T
Collimator
2.5 T
21Detector Region
- Axially-graded field near stopping target to
increase acceptance and reduce cosmic ray
background - Uniform field in spectrometer region to simplify
momentum analysis - Electron detectors downstream of target to reduce
rates from g and neutrons
Muon Beam Stop
Electron Calorimeter
Straw Tracking Detector
Stopping Target Foils
1 T
1 T
2 T
22Fringe Field Contours
- Result of OPERA calculations at UCI
- Field contours calculated without PS and DS pole
pieces - Overlaid here on original B Line layout
600 gauss contour
5 gauss contour
23MECO Status Schedule
- Scientific, Technical, and Management Approval
- Approved by BNL and by the NSF through level of
the Director - Approved by the NSB as an MREFC Project
- Endorsed by the HEPAP Subpanel on long-range
planning - Numerous positive reviews of project structure,
technical progress and readiness - Funding
- Currently operating on RD funds from the NSF
- RSVP is not in the Presidents FY04 budget
- The NSF FY04 Budget Request states that RSVP
construction will begin in FY06 with increasing
RD support in the interim - Efforts are ongoing in Congress to obtain
additional Pre-Project Development money and/or
move up the project start - Schedule
- NSF funding profile shows a five-year
construction plan completing in FY10 and a magnet
design completed in FY05 on PPD funds
24Items from the Pre-Meetings
- NSF requirements are basically that the local
institutional requirements are met, i.e. if we
meet BNL/DOE requirements they will be content - QA Plans Vendor will be required to provide one
for the magnet design, construction,
installation, test. Similarly we will develop
plans for other MECO systems along the lines of
the BNL QA plan ala US ATLAS, although that
effort awaits a QA Officer hire to gain momentum. - NEPA and external structures? No new
information there that I know of - Lift requirements see Peter Titus talk
- Personnel exposure estimates have not been
performed yet - Beam loss monitoring system see Kevin Browns
talk - Rad waste mass and activation calculations have
not been performed yet.
25Administrative Epilogue
- MECO Information
- Copies of the talks will be posted on the MECO
web site - The MIT CDR for the solenoids and a small, but
growing, list of Reference Design Documents are
also publicly available on the site providing
some additional parameter and requirements
details. - Feedback from Safety Committees
- We would like to get guidance on specific
sections of the BNL safety docs that should be
included in the RFP package - We need your notes, suggestions, and concerns in
written form for massaging into the RFP package - Given the RFP schedule and the short decay
constant of detailed memory, it would be best to
get this by the end of this week - The RFP package will be sent to committee chairs
for review of the safety information in its final
form