Title: Chapter 10 Manufacturing Planning and Control Systems
1Chapter 10Manufacturing Planning and Control
Systems
2Agenda
- A Basic Framework for A Manufacturing Planning
and Control System - Demand Management
- Aggregate Production Planning
- Master Production Schedule
- Rough-cut Capacity Planning
- Material Requirements Planning
- MRP Lot-sizing Problem
- Capacity Planning
- Order Release
- Shop-floor Control
3A Basic Framework for a MPCS
- Objective ensure that the desired products are
manufactured at the in the ,
meeting specifications, and at . - Benefits
- Reduced inventories
- Reduced capacity
- Reduced labor and overtime costs
- Shorter manufacturing lead times
- Faster responsiveness to internal and external
changes such as machine and other equipment
failures, product mix and demand changes, etc.
4(No Transcript)
5Demand Management
- Activities demand forecasting, order
transactions entry, customer contact-related
activities, physical distribution management - Forecasting approaches
- The qualitative approach rely on opinions of
experts - The explanatory approach base on causal
relationship - The descriptive approach statistics
- Moving average xt a0 ?t
- The forecast for any future period based on N
recent observations - Exponential smoothing the forecast for ? future
periods for the constant model
6Examples 1
7Example 2
8Aggregate Production Planning
- Production planning is concerned primarily with
determining , , and to meet demand
fluctuations - APP obtain solutions by aggregating information
(production hours) for a large variety of
products, time-varying demand, a long planning
horizon, fixed available resources - Strategies to manage to absorb the demand
fluctuations - Maintain uniform and accumulate
- Maintain uniform by vary by permitting
planned overtime, subcontracting, etc. - Change production rate by changing the size of
the workforce - Explore the possibility of planned backlogs if
customers are willing to accept delays in filling
their orders - ? combination of strategies ?develop an optimal
APP
9A Mathematical Programming Model
- Where dt aggregate demand in period t Xt
production units scheduled in period t cx
variable cost of production excluding labor per
hour Ot overtime scheduled in period tco
over time labor cost per hour Ut undertime
allowed in period t cu opportunity cost of not
using the equipment Wt regular time workforce
in period tcw cost of regular time labor per
hour Ht new labor force added in hours in
period tch cost of hiring regular time labor
per hour Ft layoffs in hours in period tcf
cost of layoffs per hour ci cost of unit
inventory holding per hour cs cost of a
shortage per hour K labor hours required to
produce a unit T number of periods in the
planning horizon It inventory in stock at the
end of period t I-t shortages at the end of
period t
10Master Production Schedule
- Master Production Schedule output of a
process of the aggregated production plan for
- Executable manufacturing plan master production
schedule, capacity planning, material
requirements planning
11Rough-cut Capacity Planning
- Objective to ensure that the master production
schedule is feasible - Calculate the needed on work centers
per unit for each product family based on BOMs
and routings - The resource profile (the amount of work by
resource/ unit of output) is developed - Compare the available resources with the resource
requirements profile obtained for all the work
centers considering all product families - Example Resource profile for two product
families - Work center Family I Family II Total
required - (h/200units) (h/200units) resources
- 1100 14 7 21
- 2100 7 20 27
12Material Requirements Planning
- An information system consisting of logical
procedures for managing of components,
subassemblies, parts, and raw materials - Objective How many? When? (determine net
requirement for periods)
13Example 3
The manufacturing/assembly lead times for E1, S2,
and C4, ordering lead time for M4, information on
on-hand inventory, and scheduled receipts are
given in able 10.9 ( the solution table). Carry
out the material requirements planning procedure
for raw material M4 required to manufacture
component C4
14MRP Lot-sizing Problem
- Where
- T number of periods in the planning horizon
- aj 1 if xjgt0 0, otherwise
- dj demand in period j
- xj production quantity in period j (decision
variable) - Ij inventory level in period j (decision
variable) - hj holding cost/unit in period j
- cj variable production cost/unit in period j
- Sj setup cost in period j
15Solution Algorithm (W-W Algorithm)
- The optimal solution for periods 1,2..,k given Ik
0
16Example 4
- Consider a 4-period problem having no initial
inventory. The data are given in the following
Table
17Example 4
18Capacity Planning
- Capacity planning is concerned with such as
labor, equipment to ensure the feasibility of
production plans
19Order Release
- When the production plans obtained from MRP
system are executable, the orders are released to
the shop floor - Documents
- Order
- Material inventories allocated to the order
- Routing sheets operation sequences, machines,
etc. - Appropriate shop records (job cards, move cards,
parts lists) for assembly jobs - The order release triggers the shop-floor control
activities - Scheduling of job orders on the work centers
- Sequencing of jobs on a work center
- Allocation of jigs and fixtures
- Loading of work centers considering optimal
loading conditions - Coordination of material handling, storage,
warehousing, and machine tools
20Shop-Floor Control
- Functions of a shop-floor control system
job orders on the work centers, to on a work
center, to provide accurate and timely
information - Order status information
- batch sizes
- job completions
- remaining jobs and operations
- time for all remaining jobs and operations
- Use for
- To monitor the progress of manufacturing
activities - To determine priorities for scheduling jobs in
the shop in response to changes in job order
status - To maintain and control WIP
- To provide output data for capacity control
purpose
21Shop-Floor Control
- Two main functions of a shop-floor control system
- Machine loading allocation jobs to work centers
- Job sequencing sequence jobs at each work center
- Scheduling objectives
- Meeting due dates
- Minimizing manufacturing throughput time
- Minimizing WIP
- Maximizing work center utilization
22Shop-Floor Control
- Sequencing and Priority Rules
- First-come, first-served (FCFS)
- Shortest processing time (SPT)
- Earliest due date (EDD)
- Least slack (LS) slack time remaining until
due date processing time remaining - Least slack per operation (LSPO)
- Critical ratio (CR) CR time remaining until
due date/lead time remaining - Comparison of various scheduling rules using
common performance
23Example 5
24Example 5
25Shop-Floor Control
- Bar Code Systems for Shop-Floor Control
- Bar coding technology is being used in industry
for and . - Types of data in bar codes
- Item identification
- WIP tracking
- Distribution tracking
- Other manufacturing control functions process
steps, inspection results, equipment settings,
failure mode - Elements of a bar code system symbology, media,
printer, operator, scanner, decoder - Symbology process computer information ? bar
code symbol - Step 1 establish to be represented and the
in the message - Step 2 translate the human-readable information
into a - Step 3 create a representing for binary word
- Step 4 format the individual bar code characters
into a that represents the complete message
26Symbol encode-decode sequence
27A framework for shop-floor control using bar codes