Title: Senior User Group
1Senior User Group
2Introduction Previous Actions
3Previous Actions
- 1 MCIS team to prepare Data Dictionary/XML
Guidance Notes - 2 Finalise YF UAT Sign Off
- 3 SWRDA to raise Project Variance reporting
with Ginny Walker - 4 Implementation dates with YF, AWM and EMDA
to be finalised - 5 Approach to PIRs to be developed
- 6 Dates for NWDA interface to be agreed
- 7 AA to issue guidance on evidence to satisfy
Annex XII - 8 AA to clarify which RDAs to have more
detailed follow up inspection - 9 MA to provide clarity on what additional
info maybe needed in Annex XII - 10 MCIS team to issue approach to Implementation
and User testing - 11 Change Control process to be issued
4R1 Development Progress Test Status
5R1 Development Progress Test Status, Topics
- Overall status, key achievements
- V1.8 contents
- Interface developments
- Full user update
- Core system testing
- Progress with YF
- Issues found, lessons learned
- Guidance notes
- Current actions
6Key Achievements Since Last SUG
- Training of trainers for full system users
completed - EEDA passed UAT, now ready for live
- Release 1.8 deployed, for core system go live
- Help texts User Guides available
- Financial interface with LDAs Open Accounts
systems test complete - Core system testing with YF continues but some
issues to resolve - Core user integration test planning meetings now
all held - Deployed first version of Release 2 into systems
test - Progress with YF (see later slides)
- Priority axis problem
- Lessons learned documented
- Guidance notes prepared and first drafts issued
- Current actions recommence next week
7Release 1.8.0 Key Features
- Primarily a release to fix some important
defects - User set up adding users to projects works,
obsolete user records / projects now not in list - XML upload claim resubmission allowed, priority
axis and claim type codes corrected, indicator
amounts now not doubling, forecasts with decimals
now allowed - Aggregation clawback step problem resolved,
Paid status works - Projects systems errors removed, step ticking
works, CLG, PMO literals added - Claims grant payable screen now visible on all
claim statuses - Assignment of new projects to applicant user
records now automatic - Help texts included
8Interface Developments
- MCIS financial interface with LDA
- MCIS developer, working with LDA IT, ran
end-to-end tests to prove the two sides of the
interface work correctly together - Only 1 error was found that was not fixed and
re-tested on the day - Interface was demonstrated to LDA finance
representatives - they were content - Other financial interfaces
- With OneNE, SEEDA, EEDA in the pipeline, but
not critical to sign-off - Web service interfaces for NWDA
- Generic version delivered 09/09/08
- Working version for Model Office, delivered
15/09/08 - Data to be updated today
9Core Planning Meetings
- EMDA 02/09/08, next 24/09/08 to start
integration testing - AWM 04/09/08, next 25/09/08 -------ditto
- SWRDA 16/09/08, next tba -----------ditto
- More about plans later.
10Progress with YF Issues Found, Lessons Learned
- 01/08/08
- Project Claim XML files
- Sample of XML data of 6 projects successfully
passed validation after a few corrections - Project File
- Programme reference reset to 090, not 90
- Header record format corrected
- Programme Priority Axis code wrong in MCIS
software (mismatch with data dictionary) - Data validations rules on dates reapplied
- Claim schedule misunderstandings resolved
- Claim type code wrong in MCIS software (mismatch
with data dictionary)
11Progress with YF Issues Found, Lessons Learned
- 05/08/08, some problems
- Project File
- Load of 6 projects failed, so one project at a
time used - Worries about zero values causing performance
problems, so zeros suppressed - Data loaded successfully once validation rules
had passed, in particular claim schedule
complete, costs, funding, indicators present for
all quarters - Claims File
- Successfully generated after claim period changed
12Progress with YF Issues Found, Lesson Learned
- 14/08/08, lots of successes, but also some
problems - 6 projects and 7 claims loaded successfully, one
project had multiple PAs - Chris Lamb (as Aggregate Claim Editor) worked
with the system - Costs and funding profile incomplete for one
project - One project had a claim for a future claim period
- YF expenditure category code incorrect
reference data catalogue change needed - Expenditure data and grant calculations correct
- Layout of target screens needs improvement
- Workflow testing exposed some errors, raised in
SharePoint - Cognos MI reporting demonstrated, reconciliation
reports now available generally regarded as
good more needed / amendments requested
13Progress with YF Issues Found, Lesson Learned
- 28/08/08, some problems and successes
- 20 projects but with zero values failed to load
file size problems (40 Mbytes) due to a zero
entry for every O/P expenditure category, every
O/P indicator, every claim period - Indicator and expenditure forecasts failed the
validation rules - Quarterly progress reports successfully loaded
- 11/09/08, some problems
- Duplicate priority axes, due to phasing in
funding and other funding and have to paid at
different intervention rates - Policy directives on this subject e.g. separate
projects - Solution to increase PAs from 5 to 9
- Other options considered 2 programmes, 2
aggregate projects note - MCIS can cope with all
of these solutions, but revision of data
configuration in O/P spreadsheets is needed
14Implementation Status Plan
- Nigel Williams, Mark Swan
15Implementation Status Plan, Topics
- Go live approach document, including involvement
of AA finalising compliance statements - Overview of timescales
- EEDA implementation user testing and Model
Office - Project situation report
- Security review
16Overview of Timescales
17Go Live Approach User Testing
- Document Issued covering
- The go live and implementation approach
- Difference between User Testing Model Office
- The end to end User Test
- The witnessed test by the MA, CA, AA
- Generic Acceptance Criteria
- Standard end to end test script
- Additional information required by the AA to
demonstrate compliance - before we sign off the opinion provided in
respect of the compliance assessment review
(anticipated during September 2008) we will need
to review the results of the MCIS and local
computerised testing. - Attend user test events, review outcomes
- Further in depth review of 2 RDAs, 1 x core 1 x
full - Model Office evidence
18Go Live Approach User Testing
- RDA/MCIS Interface evidence required by AA in
Management Control - Are ERDF funds accounted for separately, and
against correct budget headings? - RDA MI systems that identifies
- each operation
- the final beneficiary
- the date of approval of the grant
- the amounts committed and paid
- the period of expenditure
- the total expenditure by measure and by sub-total
- Procedures to ensure that the data flow can be
followed from first entry to output and the
transfer of data between the systems - Reconciliations between systems
- Responsibility for system maintenance
monitoring - Access security controls, including backup
arrangements
19Go Live Approach User Testing
- Additionally, the AA also require evidence of
- RDAs internal approval and governance of
interface arrangements and documentation - MCIS and local system interfaces - effectiveness
of workflows and accuracy and consistency of
financial and other information - Interface descriptions, flow charts,
configuration plans, desk instructions and other
documentation - Operating personnel, including job descriptions
and training - Systems ownership and accountability, maintenance
and change control. - Continuity planning, back up procedure and
disaster recovery - Chinese walls and other special procedures
where RDA is the beneficiary are being observed,
separation of duties - Audit trails and version control
- Confirm the reliability and completeness of
statements made in the RDA system description in
Annex XII
20EEDA Model Office User Test
- Approach
- Model Office 4th to 9th Sept
- Scenarios included, and went beyond, the standard
set for User Test - 8 projects, taken from real life, and covering a
range of types - 24 financial claims, including restricted and
final. 6 progress report claims - Real users, not generic (single-role) logins
- Some processing was demonstrated (1 project
set-up, 1 claim, aggregation) - The rest was done beforehand, and EEDAs
observations recorded - Scope was EEDAs overall ERDF operation, not just
use of MCIS - Off-line processes, forms and other documentation
were also shown
21EEDA Model Office User Test
- Outcome
- No time to give Witnesses a tour of the projects,
claims processed before the day - User Test sign-off was achieved on the day
- For Model Office, the CA and AA identified some
follow-up actions in process
22Project Situation Report
- Need to change implementation approach
- Decouple core and full implementations
- System is ready to make 1st core system live
- Allow full users to progress implementations
- Address any defects found in core user testing
in later release - Views of RDAs?
23Security Review
- MCIS Security Assessment only covers MCIS
Hosting - As MCIS is reliant on information held outside of
the system, assurances are needed that ensure its
integrity, trust and reliability - Latest National Security Standard requires that
- Departments are responsible for ensuring a
coherent approach to information risk management
across affiliated agencies and Non-Departmental
Public Bodies. They should lead efforts to engage
these stakeholders to satisfy themselves that the
appropriate levels of information risk management
are maintained in these wider organisations - IS1 requires an Information Risk Assessment
across the process - This will be achieved by a survey of the RDAs
security arrangements put in place against the
latest standards proposal is to use the MCIS
CLAS consultant to gather the information - Results will be presented back to the SUG at a
later date
24Security Review
- The Survey will cover
- Security Policy
- Organisation of Information Security
- Human Resources Security
- Phyisical Environmental Security
- Media handling Security
- IT Communications Operations Management
- Monitoring
- Access Control
- User Responsibilities
- Mobile Working
- Business Continuity Management
- Compliance
25End of Morning Agenda Items Any Other Business?
26Lunch
27MCIS Post Contract Governance
28Governance, Key Principles
- Focus on contract management as a distinct
function - Build on what works use existing structures
- Following IT infrastructure Library (ITIL)
principles - Align the IT service with the current and future
needs of the business and customers - Improve the quality of the IT service
- Reduce the long term cost of the service provision
29Business Environment
DG Regional Policy
MANAGING AUTHORITY
INTERMEDIARY BODIES (2007 2013)
EPP
mcis
GOVERNMENT OFFICES (2000-2006)
30What are we trying to achieve?
- Arrangements to manage the contractual
relationship with the MCIS supplier - A clear role for key stakeholders
- Allow all stakeholders to participate in defining
the direction and prioritisation of any system
enhancements - A one customer focus for engagement with the
service provider - Role clarity between the various levels of
governance - Put in place escalation and change control
mechanisms - Allow for SLA reporting and feedback of the
support service - Ensure contractual management mechanisms are
established - Clear interface with other ERDF delivery functions
31Governance links with programme management
- ERDF Management Control
- Ensure arrangements in place for effective
management control of the programmes - Facilitate regional practitioners to share and
learn from experiences and help the network
achieve compliance and N2 - Make sure the right group resolve the issues that
they are best placed to understand - Define the responsibilities and authorities of
the various groups
32Some core governance functions
33Proposed Organisation
Programme Implementation Group (PIG) Service
Management Board (SMB)
Chair EPP head of division Attendees All RDAs,
MA, CA, AA, BERR
- Responsibilities
- Overall direction management
- Authorise contract variations
- Arbitrate on business issues
MCIS Change Approval Board
MCIS Service Manager
Chair EPP Service Manager Attendees 1 x core,
1 x full RDAs, MA, CA, Supplier rep
Senior User Group (SUG) Service Delivery Board
- Responsibilities
- Reviewing change requests
- Impact assessments
- Monitoring SLA compliance
Chair EPP Service Manager Attendees All RDAs,
MA, CA, AA
- Responsibilities
- Ensuring operation compliance
- Resolving business technical issues
- Recommend way forward to PIG SMB
- Arbitrate on business issues
34Issues / Questions for Discussion Nigel Williams
35Issues / Questions for Discussion, Topics
- What information does the CA require in aggregate
progress reports - Article 55 COCOF paper issued what next?
- Others??
36Release 2
- Alex McIntosh / Alex Hazell
37Release 2, Topics
- Functional Specification walkthroughs
- R2 schedule
- Current status
- Design reviews
38Release 2, Progress
- Functional specification walkthroughs completed
- SEEDA
- EEDA
- ONE
- Release 2 Design Completed
- Project Categorisations
- Design document
- Screen design
- Funding Agreement
- Report specification
- First cut of report
- Release 2 Functionality Currently in Design
- Visits
- Irregularities
- Clawbacks
39Development Plan
40Risks / Issues Nigel Williams
41Risks / Issues, Topics
- Risk log review
- New risks / issues
42End of Afternoons BusinessAny Other Points?