2Facts Figures
- 38 square miles
- 44,000 population (2005 est.)
- 255 km of paved road
- 12 bridges
- 321 km of water mains
- 22 reservoirs
- 363 km sewer pipe
- 58 sanitary lift stations
- 1 Citrus Wynd Wastewater Treatment Plant
3How were organized
4Engineering Transportation
5Personnel Resources
- 65 full time staff (Engineering)
- 90 full time staff (Blue Bus)
- 7 Professional Engineers
- 5 in Engineering
- Land Development Engineer
- Manager, Permits Licences
6Engineering Transportation
Expenditures and Revenues
2006 Budget 2007 Request
Total Expenses 16,322,745
17,969,239 Total Revenue 13,490,284
15,080,316
Net 2,832,461 2,888,923
FTEs 126 (West Van Transit 90)
7Water Sewer Utilities
Expenditures and Revenues
Water Utility 2006 Budget 2007 Budget
Total Expenses 15,215,900
21,583,600 Water Utility Revenue 15,215,
900 21,583,600 Net 0 0
Sewer Utility 2006 Budget 2007 Budget
Total Expenses 6,616,708
6,961,577 Sewer Utility Revenue
6,616,708 6,961,577 Net 0
0
FTEs 29
8Capital ProjectsUpcoming and Underway
9(No Transcript)
10(No Transcript)
11Almondel Bridge
12Almondel Bridge
13Eagle Lake Membrane Filtration
- Low head membrane filtration technology
- 22 ML/d capacity
- LEED
- 16 Million
- Zenon Environmental
- Dayton Knight Ltd.
14Civic Site Community Centre
- Under construction
- 80,000 sq. ft.
- Partnership VCHA, West Van Youth Band
- 40 million budget
- 25 million District share
- Hughes Condon Marler Architects
- Scott Construction
152007 Consulting Assignments
- Marine Drive Gateway Project Design (ND Lea)
- Transportation Plan (Unawarded)
- Cycling Network/Greenway Plan (Urban Systems)
- Bridge Management Program (EarthTech)
- Pavement Management Program (StanTech)
- Dundarave Traffic Calming and Parking Plan
(Binnie) - Almondel Bridge Demolition Design (Unawarded)
- Traffic Signal/Street LightProgram (Cobra
Electric) - Spirit Trail (Unawarded)
16- Eagle Lake Membrane Filtration Facility (Dayton
Knight) - SCADA Upgrades (Dayton Knight)
- Water Supply System Simulation Model (Dayton
Knight) - Montizambert Creek Water Treatment Pre-Design
Piloting (Dayton and Knight) - Water Reservoir Structural Assessments (Dayton
Knight) - SWIFT Implementation (Land Info Technologies)
- Sewer Rate Study (FCS Group)
- Sewer Condition Assessment Reporting (UMA Group)
- II Pilot Study Update (Dayton Knight)
- Rodgers/Marr Creeks ISMPs (Associated Eng.)
- Rodgers Creek 07 Reconnaissance (Associated Eng.)
- 2007 Rainfall Monitoring Program (Kerr Wood
Leidal) - Sanitary/Storm/Water National Benchmarking
(EarthTech)
17Contacts
- Emil Barth, Director, Engineering
Transportation - (604)-925-7158
- ebarth_at_westvancouver.ca
- Phil Bates, Business Technical Services Manager
- (604)-925-7039
- pbates_at_westvancouver.ca
- Brent Dozzi, Manager, Roads Transportation
- (604)-925-7157
- badozzi_at_westvancouver.ca
- Ray Fung, Manager, Utilities
- (604)-925-7159
- rfung_at_westvancouver.ca