INTERVENORS PRESENTATION - PowerPoint PPT Presentation

1 / 80
About This Presentation
Title:

INTERVENORS PRESENTATION

Description:

The Northwestern Ontario Municipal Association (NOMA) The Town of Atikokan ... Appreciate that the IPSP fails to comply with the Minister's directive on ... – PowerPoint PPT presentation

Number of Views:49
Avg rating:3.0/5.0
Slides: 81
Provided by: KLew8
Category:

less

Transcript and Presenter's Notes

Title: INTERVENORS PRESENTATION


1
INTERVENORS PRESENTATION
  • Ontario Energy Board Hearing on the Ontario Power
    Authoritys Integrated Power System Plan
  • Board File EB-2007-0707

2
Intervenors
  • The Northwestern Ontario Municipal Association
    (NOMA)
  • The Town of Atikokan
  • The City of Thunder Bay

3
Statement of Purpose
  • Understand and consider the unique nature of the
    electrical system in Northwestern Ontario
  • Appreciate that the IPSP fails to comply with the
    Ministers directive on several material points

4
Concerns
  • The concerns of the three Intervenors are
    threefold
  • The IPSP as it stands does not provide for
    transmission line upgrades that must be put in
    place the OPA fails to provide any justification
    for not selecting upgrades that in northwestern
    Ontario would significantly improve system
    efficiency in northwestern Ontario.
  • Secondly, the IPSP fails to provide for
    replacement generation for the two thermal
    generators it proposes to shut down in
    northwestern Ontario, contrary to the requirement
    in section 5 of the Ministers directive.
  • 3. The proposed replacement of the 517 megawatts
    (MW) of energy that would be lost in the shutdown
    of the two thermal generating stations does not
    provide for system reliability required in
    section 5 of the Ministers Directive.

5
Electricity Act, (Section 1(a))
to ensure the adequacy, safety, sustainability,
and reliability of electricity supply in Ontario
through responsible planning and management of
electricity resources, supply and demand
  • Obviously underpins the goals set out insection
    5 of the Ministers Directive for an IPSP that
  • ensures adequate generating capacity
  • Ensures electrical system reliability, and
  • Calls for replacement generation

6
Intervenors are requesting, pursuant to section
25.30(5) of the Electricity Actrefer all
portions of the IPSP affecting northwestern
Ontario back to the OntarioPower Authority for
reconsideration as to
  • How system efficiency and integration of new
    supply (section 6 of the Ministers directive)
    can be achieved by further upgrades to the
    transmission system in northwestern Ontario
  • How adequate generating capacity and system
    reliability are to be maintained through
    replacement generation in northwestern Ontario
    upon shutting down the two thermal generating
    plants
  • How levels of energy sufficient to meet base load
    capacity in northwestern Ontario can be
    maintained upon shutting down the two plants

7
The Issue
  • In the alternative to having the Board refer the
    portions of the IPSP back for reconsideration,
    the three Intervenors seek to have the following
    added to the list of issues to be considered by
    the Board in Phase II of this hearing
  • Does the IPSP plan for
  • Replacement generation
  • Adequate generating capacity
  • Strengthening of the transmission system
  • System efficiency, and
  • System reliability
  • in the substantively different circumstances of
    northwestern Ontario?
  • In deciding on either alternative, the Board will
    need to understand more about northwestern Ontario

8
Understanding Northwestern Ontario
9
(No Transcript)
10
Kenora
Wawa
Thunder Bay
Ottawa
Toronto
Windsor
11
Kenora
Wawa
Thunder Bay
Ottawa
Toronto
Windsor
12
Kenora
Wawa
Thunder Bay
Ottawa
Toronto
Windsor
13
Kenora
Wawa
Thunder Bay
Ottawa
Toronto
Windsor
14
Kenora
Wawa
Thunder Bay
Ottawa
Toronto
Windsor
15
Kenora
Wawa
Thunder Bay
Ottawa
Toronto
Windsor
16
Kenora
Wawa
Thunder Bay
Ottawa
788 km corridor Population 9.5 million
Toronto
Windsor
17
785 km corridor Population 250,000
Kenora
Wawa
Thunder Bay
Ottawa
788 km corridor Population 9.5 million
Toronto
Windsor
18
Generating Capacity
  • Northwestern Ontario
  • 1197 megawatts of installed generating capacity
  • Less than 5 of the 27,000 megawatt installed
    capacity for the entire province

19
Source of Generation
  • 680 megawatts of installed hydro-electric
    generating capacity
  • 517 megawatts of installed thermal generating
    capacity

20
Base Load Generation
  • Hydro-electric generation
  • Very economical
  • Not reliable
  • Current three-year drought conditions actual
    generation, on occasion, been no greater than 30
    of the installed capacity
  • Hydro-electric generation is not a reliable
    component in base load capacity

21
Base Load Generation
  • Essential to understand 517 megawatts of thermal
    generation constitutes the base load capacity in
    northwestern Ontario
  • Southern Ontario relies on nuclear generation for
    its base load capacity

22
Transmission Map
23
Transmission Map
  • Northwestern Ontario has only 5 of its
    transmission lines looped. 95 of the
    northwestern Ontario Grid is in radial circuits.
  • Transmission map shows only 40 of the land mass
    of northwestern Ontario

24
Ratio of Industrial to Residential Demand
  • Southern Ontario70-80 residential
  • Northwestern Ontarioindustrial use constitutes
    the largest sector
  • 70 of electricity customers are Industrial

25
Scale of Industrial Users
  • Scale of the industrial users in northwestern
    Ontario is comparatively much larger than the
    typical industrial user in southern Ontario
  • One paper mill consumes between 100 and 210
    megawatts of power
  • The largest one of the paper mills is typically
    among the highest energy users in the province
  • There are five paper mills operating in
    northwestern Ontario today
  • Those five paper mills operating today consume
    the equivalent to something in the order of ten
    to fifteen automobile assembly plants

26
Inadequate Supply
ERCO Chemical Plant
27
Inadequate Supply
ERCO Plant
  • High Amperage
  • Supply had to be on a radial line that also
    served two paper mills which, conversely,
    required high voltage.
  • Decided that it would make more sense for them to
    consolidate their operations in Calgary
  • Ship their product over 2,000 km to the paper
    mill in Thunder Bay
  • IPSP as it is currently framed is inadequate for
    the demand needs of northwestern Ontario

28
Boreal Forest Map
Hudson Bay Lowlands
North of the Undertaking
Boreal Forest
Great LakesSt. Lawrence Forest
Deciduous Forest
29
Mining in Northwestern Ontario
Approximately 300 active exploration programs
4 producing gold mines 1 producing PGE mine
McFaulds Lake
Red Lake
Greenstone
Rainy River
30
Mining in Northwestern Ontario
44.6 of the active mining claims in Ontario
31
New Industrial Users
  • Supply for an electric smelting plant. Currently
    such a plant would be impossible without
    additional generation transmission supply over
    and above the proposed replacement supply 517
    megawatts of the two thermal generating stations

32
NWO as Electrical Island
33
Where Northwestern Ontario Stands in Compliance
with Ministers Directives
  • A) Conservation targets for northwestern Ontario

34
Where Northwestern Ontario Stands in Compliance
with Ministers Directives
  • Conservation and Demand Management
  • Ministers Directive targets 1,350 megawatts cut
    from peak demand for the entire province by 2010
    and 3,600 more megawatts by 2025
  • The problem has already been dealt with in
    northwest Ontario

35
Where Northwestern Ontario Stands in Compliance
with Ministers Directives
  • For their own economic necessity
  • Cooperated with both the former Ontario Hydro and
    local utilities to level off periods of peak
    demand in the northwestern Ontario grid
  • Some 200 megawatts in peak demand eliminated from
    the northwestern Ontario system some fifteen
    years ago
  • By production shifting
  • Industrial users cooperate in shifting key
    elements of their production to other time
    periods
  • Irony, because northwestern Ontario is an
    electrical island.
  • Surplus power saved in leveling peak demands in
    northwestern Ontario cannot be exported to
    Southern Ontario

36
Where Northwestern Ontario Stands in Compliance
with Ministers Directives
  • B) Residential Conservation
  • Southern Ontario
  • Much of the conservation targets set by the
    Ministry will likely be met through more
    effective residential use.
  • Residential use constitutes an estimated 70-80
    of the demand as in southern Ontario
  • Reduction in demand will undoubtedly be large

37
Where Northwestern Ontario Stands in Compliance
with Ministers Directives
  • B) Residential Conservation
  • Northwestern Ontario
  • The comparatively small residential use (some
    20-30 of demand) correspondingly, small
    reduction in a correspondingly small segment of
    Ontarios energy demand
  • Less than 5
  • There is no recognition in the IPSP of how these
    facts affect the achievability of the targets for
    northwestern Ontario

38
Renewable Energy
  • Biomass
  • Economic necessity industrial users in
    northwestern Ontario have and continue to develop
    biomass generation
  • For example, one of northwestern Ontarios paper
    mills produces as much as 50 megawatts of its own
    210 megawatts electrical energy needs
  • Difficult, therefore, for the OPA to propose
    anything not already being implemented out of
    economic necessity
  • Mandate of every mill manager appointed in the
    last fifteen years to cut production costs
  • Especially given Ontarios uncompetitive
    electricity costs

39
Renewable Energy
  • Wind Power Generation
  • Planned Wind Generation
  • IPSP proposes wind power installation
  • One for example is on the shores of Lake Nipigon
    in northwest Ontario
  • Other wind power developments elsewhere in
    northwestern Ontario
  • Useful only as additional energy
  • Unpredictability of wind means that its energy
    generation cannot be considered part of the base
    load capacity
  • Industrial users need to be able to rely upon
    secure and adequate base load supply
  • Lack of suitable Inertial Reserve in Wind Farms

40
Renewable Energy
  • Related to dynamic behaviour and stability
  • Due to the fact that wind generators will replace
    conventional generators, possible problems in the
    considered zones may arise related to
  • Reduced short circuit level, which could have an
    impact on line protection.
  • Risk of local voltage collapse or risk of
    prolonged voltage sags during grid faults
  • Reduced system inertia could impact stability in
    island operation, if relevant
  • Small signal stability could be affected

Exhibit C-11-2 Attachment 29.9 page 28click here
for citation
41
Renewable Energy
  • In the NE and NW zones lack of sustained short
    circuit power can become a problem. This would
    have an impact in situations, when most of the
    demand can be covered by the wind generation in
    the zone. If in this case the majority of
    synchronous generators are stopped due to the
    limited export capacity and a line fault occurs
    in the transmission system, the fault
    contribution from one side may decay, so that
    line distance protections cannot detect faults.
  • In the NE and NW zones, the behaviour of wind
    turbines during grid faults can have significant
    impact with risk of local voltage collapse in the
    worst case or prolonged voltage dips due to
    delayed voltage recovery in the best case.

42
Renewable Energy
  • Solar Generation
  • Solar generation will be welcome as additional
    energy
  • Cannot be considered part of the capacity

43
Renewable Energy
  • Hydro-electric Generation
  • Many potential sites for new hydro-electric
    generation within the northwestern Ontario
    watersheds have been identified
  • The largest would produce 20 to 25 megawatts of
    electricity
  • Exception is Little Jackfish 132 megawatts
  • Considered peak power only, as water reserve is
    exhausted in 4 hours

44
Renewable Energy
  • Hydro-electric Generation
  • Desirable for local small-scale use
  • Contributing very economically to the overall
    supply of energy
  • None would be suitable for the base load capacity
    industrial users must be able to rely upon
  • Caution
  • Drought conditions that can and have reduced
    production to around 30 of installed capacity

45
Demand Management Uniquely Different
  • Generally Demand Management will refer to the
    efficient management of existing demand
  • For example, northwestern Ontario has succeeded
    in leveling peak demands
  • Essential to realize that Demand Management in a
    region that develops natural resources is
    entirely different
  • The Demand to be planned for in northwestern
    Ontario
  • Is beyond existing users
  • Is beyond demographic projections
  • Demand Management to be planned for northwestern
    Ontario means planning to encourage development

46
Issues for Phase IIRadial Circuits
  • Radial circuitry that constitutes 95 needs to be
    substantially upgraded
  • Looping the circuits in order to ensure more
    stable and secure supply to industrial users
  • The IPSP as it is presently drafted has no
    provision for looping any of the remote radial
    transmission lines

47
Northern Ontario Transmission System
48
Red Lake Loop
  • Loop of the Red Lake line with the Musselwhite
    tap of the Ear Falls by Pickle Lake 115 kv
    circuit could be installed
  • Such a loop would significantly increase the
    stability and security of supply for
  • Existing Mines
  • Municipal ties
  • Proposed manufacturing of value added wood
    products

49
Longlac \ Geralton Loop
  • Loop of the Longlac line with the Terrace Bay
    line could be installed
  • Such a loop would make the same improvements for
    similar customers in that part of northwestern
    Ontario

50
Without Such Loops
  • Without such loops, at present, existing radial
    transmission supply means
  • That downtime maintenance must be conducted only
    on statutory holidays
  • In the event of any fault in the radial
    transmission lines there is no alternate source
    of supply
  • Inevitable result is unanticipated downtime
  • Havoc with production schedules of the industrial
    customer
  • Prolonged disruption to the residential customers

51
  • Enhancing the security and stability of the
    electricity, a Red Lake looped and Longlac
    looped, also enhance the possibility of radial
    transmission from that loop
  • First Nation communities allowing them to replace
    the diesel plants
  • To increase their capacity to develop local
    industries
  • To assist in development of renewable generation,
    such as small hydro-electric generation sites

52
Inertia
53
Inertia
  • Southern Ontario
  • Large number of looped transmission lines
  • Many generating sources (especially large nuclear
    generator turbines)
  • Transformers
  • Other equipment
  • Widely distributed industrial customers
  • Create a very large inherent inertia in the
    southern Ontario grid itself
  • Northern Ontario
  • By Contrast
  • General absence of looped transmission lines
  • Many small hydro-electric generating stations
  • Even if wind turbine generation with their
    relatively small turbines are included
  • All of these add little to inertia in the grid
  • It is the two thermal generating plants that give
    meaningful stability to the grid

54
Energy Production Plus Inertia
  • Section 5 of the Ministers Directive speaks of
    replacement generation and adequate generating
    capacity
  • Fundamental importance to appreciate the two
    thermal generating stations contribute BOTH
  • 517 MW, and
  • provide an estimated 40 inertia in the
    northwestern Ontario grid
  • The Minister does NOT speak of replacement of
    energy only but of generation (that is energy
    PLUS inertia)
  • The IPSP provides only for energy replacement

55
Remember the problems a few minutes ago related
to dynamic behaviour and stability in wind
generation?
56
Energy Production Plus Inertia
  • Due to the fact that wind generators will replace
    conventional generators, possible problems in the
    considered zones may arise related to
  • Reduced short circuit level, which could have an
    impact on line protection
  • Risk of local voltage collapse or risk of
    prolonged voltage sags during grid faults
  • Reduced system inertia could impact stability in
    island operation, if relevant
  • Small signal stability could be affected

Exhibit C-11-2 Attachment 29.9 page 28click here
for citation
57
LACK of RELIABILITY in Transmission Supply with
the IPSP
  • Lack of system reliability Transmission supply
    is not stable
  • The IPSP as it is currently drafted proposes
    replacement of base load generation currently had
    in the thermal generating stations with a
    transmission supply that, in effect, is
    purporting to be the base load supply

58
LACK of RELIABILITY in Transmission Supply with
the IPSP
  • In addition to the inertia taken out of the
    northwestern Ontario grid, and not replaced, the
    supply of energy through transmission supply has
    the following problems
  • Transmission lines are vulnerable
  • The 230 kv line from Manitoba to Marathon would
    be the transmission source
  • Like all such transmission lines
  • Vulnerable to transient and permanent faults
  • Standard practice in electrical storms to reduce
    transmission in the area of the storm to zero in
    order to protect the lines and related equipment

59
Electrical Storms
  • In northwestern Ontario it is important
  • That transmission of electricity in the 230 kv
    line would be typically from west to east
  • That also is typically the course of an
    electrical storm
  • As a result there is
  • No reason to think that a transmission feed can
    be considered a reliable source of base load
    supply for northwestern Ontario even of energy
    alone (forgetting inertia for the moment)

60
Instability Over Length
  • A maximum 350 megawatt load placed on the 230 kv
    transmission line will by its nature cause the
    supply of energy to be subject to voltage drops
  • That must be compensated for by using capacitors
  • This will create instability and insecurity for
    industrial users

61
Likely Source of Energy
  • Unlikely that the transmission feed will ever
    come up from southern Ontario
  • Southern Ontario, obviously, needs everything it
    can generate
  • The transmission feed on the 230 kv transmission
    line will, in effect, come east from Manitoba
  • Impractical to theorize that the nuclear base
    load supply in southern Ontario can be considered
    to constitute a base load supply in northwestern
    Ontario
  • The 300 megawatt load limit of the tie lines at
    Marathon prevents that

62
Manitoba Energy
  • Manitobas hydro-electric generation is
    susceptible to a drought as is northwestern
    Ontarios
  • Typically Manitoba experiences drought before
    northwestern Ontario
  • Most of Manitobas current hydro-electric
    generation is largely pre-sold on long-term
    supply contracts to the USA
  • When Manitobas own needs exceed available
    hydro-electric demand, those deficiencies are
    covered by calling on Manitobas alternate
    supply, North Dakota

63
Manitoba Energy
  • Unless this OPA can demonstrate otherwise, it
    must be assumed that any additional large amounts
    of megawatts drawn on the transmission line from
    Manitoba in order to replace the thermal
    generation shutdown in the two generating
    stations in northwestern Ontario will actually
    end up coming from North Dakota
  • The source of North Dakotas export energy is
    coal fired generation

64
Lack of System Reliability
  • Transmission Supply is NOT Sufficient

65
2008 Status Quo
1200 1000 800 600 400 200 0
990
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
Load
66
2008 Status Quo
1200 1000 800 600 400 200 0
990
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
517
Load
Supply
Excess
67
2008 Status Quo
1200 1000 800 600 400 200 0
207 MW
1197
990
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
680
517
Load
Supply
Excess
68
2014 The Problem
1200 1000 800 600 400 200 0
990
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
680
Load
Supply
69
2014 The Problem
1200 1000 800 600 400 200 0
300
990
Maximum Transferable
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
680
Load
Supply
70
2014 The Problem
1200 1000 800 600 400 200 0
?
10
300
990
Maximum Transferable
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
680
Load
Supply
Shortfall
71
2014 The Problem Growth
1200 1000 800 600 400 200 0
?
?
10
?
300
990
Maximum Transferable
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
680
Load
Supply
Shortfall
72
2014 Worst Case
1200 1000 800 600 400 200 0
990
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
226
Drought
Load
Supply
Shortfall
73
2014 Worst Case
1200 1000 800 600 400 200 0
990
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
Maximum Transferable
300
226
Drought
Load
Supply
Shortfall
74
2014 Worst Case
1200 1000 800 600 400 200 0
?
990
464
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
300
Maximum Transferable
226
Drought
Load
Supply
Shortfall
75
2014 Worst Case
1200 1000 800 600 400 200 0
?
164
990
300
Maximum Transferable
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
300
226
Drought
Load
Supply
Shortfall
76
2014 Worst Case Growth
1200 1000 800 600 400 200 0
?
?
?
990
464
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
300
Maximum Transferable
226
Load
Supply
Shortfall
77
Conclusion
  • The IPSP as it is currently drafted fails to
    address northwestern Ontario as a sustainable
    system for electrical supply

Electricity Act, (Section 1(a))
to ensure the adequacy, safety, sustainability,
and reliability of electricity supply in Ontario
through responsible planning and management of
electricity resources, supply and demand
The statutory regime is relevant. It cannot be
thought to be within the purview of the Board to
approve something that is in contravention of the
Electricity Act.
78
Conclusion
  • 2. The IPSP as it is currently drafted fails to
    meet the goals of the Ministers Directive that
    the IPSP provide for
  • Replacement generation
  • Adequate generating capacity
  • Strengthening of the transmission system
  • System efficiency, and System reliability

79
Conclusion
  • The Intervenors
  • NOMA (that is the Northwestern Ontario Municipal
    Association)
  • The Town of Atikokan
  • The City of Thunder Bay
  • Urge the Board to review the IPSP as it pertains
    to northwestern Ontario with a view to directing
    the Ontario Power Authority, pursuant to section
    25.30(5) to further consider the plan as it
    pertains to northwestern Ontario

80
In The Alternative
  • These Intervenors propose the following be added
    as an Issue for consideration by the Board in
    Phase II
  • Does the IPSP plan for
  • Replacement generation
  • Adequate generating capacity
  • Strengthening of the transmission system
  • System efficiency, and
  • Power quality and System reliability
  • In the substantively different circumstances of
    northwestern Ontario?
Write a Comment
User Comments (0)
About PowerShow.com