Title: INTERVENORS PRESENTATION
1INTERVENORS PRESENTATION
- Ontario Energy Board Hearing on the Ontario Power
Authoritys Integrated Power System Plan - Board File EB-2007-0707
2Intervenors
- The Northwestern Ontario Municipal Association
(NOMA) - The Town of Atikokan
- The City of Thunder Bay
3Statement of Purpose
- Understand and consider the unique nature of the
electrical system in Northwestern Ontario - Appreciate that the IPSP fails to comply with the
Ministers directive on several material points
4Concerns
- The concerns of the three Intervenors are
threefold - The IPSP as it stands does not provide for
transmission line upgrades that must be put in
place the OPA fails to provide any justification
for not selecting upgrades that in northwestern
Ontario would significantly improve system
efficiency in northwestern Ontario. - Secondly, the IPSP fails to provide for
replacement generation for the two thermal
generators it proposes to shut down in
northwestern Ontario, contrary to the requirement
in section 5 of the Ministers directive. -
- 3. The proposed replacement of the 517 megawatts
(MW) of energy that would be lost in the shutdown
of the two thermal generating stations does not
provide for system reliability required in
section 5 of the Ministers Directive.
5Electricity Act, (Section 1(a))
to ensure the adequacy, safety, sustainability,
and reliability of electricity supply in Ontario
through responsible planning and management of
electricity resources, supply and demand
- Obviously underpins the goals set out insection
5 of the Ministers Directive for an IPSP that - ensures adequate generating capacity
- Ensures electrical system reliability, and
- Calls for replacement generation
6Intervenors are requesting, pursuant to section
25.30(5) of the Electricity Actrefer all
portions of the IPSP affecting northwestern
Ontario back to the OntarioPower Authority for
reconsideration as to
- How system efficiency and integration of new
supply (section 6 of the Ministers directive)
can be achieved by further upgrades to the
transmission system in northwestern Ontario - How adequate generating capacity and system
reliability are to be maintained through
replacement generation in northwestern Ontario
upon shutting down the two thermal generating
plants - How levels of energy sufficient to meet base load
capacity in northwestern Ontario can be
maintained upon shutting down the two plants
7The Issue
- In the alternative to having the Board refer the
portions of the IPSP back for reconsideration,
the three Intervenors seek to have the following
added to the list of issues to be considered by
the Board in Phase II of this hearing - Does the IPSP plan for
- Replacement generation
- Adequate generating capacity
- Strengthening of the transmission system
- System efficiency, and
- System reliability
- in the substantively different circumstances of
northwestern Ontario? - In deciding on either alternative, the Board will
need to understand more about northwestern Ontario
8Understanding Northwestern Ontario
9(No Transcript)
10Kenora
Wawa
Thunder Bay
Ottawa
Toronto
Windsor
11Kenora
Wawa
Thunder Bay
Ottawa
Toronto
Windsor
12Kenora
Wawa
Thunder Bay
Ottawa
Toronto
Windsor
13Kenora
Wawa
Thunder Bay
Ottawa
Toronto
Windsor
14Kenora
Wawa
Thunder Bay
Ottawa
Toronto
Windsor
15Kenora
Wawa
Thunder Bay
Ottawa
Toronto
Windsor
16Kenora
Wawa
Thunder Bay
Ottawa
788 km corridor Population 9.5 million
Toronto
Windsor
17785 km corridor Population 250,000
Kenora
Wawa
Thunder Bay
Ottawa
788 km corridor Population 9.5 million
Toronto
Windsor
18Generating Capacity
- Northwestern Ontario
- 1197 megawatts of installed generating capacity
- Less than 5 of the 27,000 megawatt installed
capacity for the entire province
19Source of Generation
- 680 megawatts of installed hydro-electric
generating capacity - 517 megawatts of installed thermal generating
capacity
20Base Load Generation
- Hydro-electric generation
- Very economical
- Not reliable
- Current three-year drought conditions actual
generation, on occasion, been no greater than 30
of the installed capacity - Hydro-electric generation is not a reliable
component in base load capacity
21Base Load Generation
- Essential to understand 517 megawatts of thermal
generation constitutes the base load capacity in
northwestern Ontario - Southern Ontario relies on nuclear generation for
its base load capacity
22Transmission Map
23Transmission Map
- Northwestern Ontario has only 5 of its
transmission lines looped. 95 of the
northwestern Ontario Grid is in radial circuits. - Transmission map shows only 40 of the land mass
of northwestern Ontario
24Ratio of Industrial to Residential Demand
- Southern Ontario70-80 residential
- Northwestern Ontarioindustrial use constitutes
the largest sector - 70 of electricity customers are Industrial
25Scale of Industrial Users
- Scale of the industrial users in northwestern
Ontario is comparatively much larger than the
typical industrial user in southern Ontario - One paper mill consumes between 100 and 210
megawatts of power - The largest one of the paper mills is typically
among the highest energy users in the province - There are five paper mills operating in
northwestern Ontario today - Those five paper mills operating today consume
the equivalent to something in the order of ten
to fifteen automobile assembly plants
26Inadequate Supply
ERCO Chemical Plant
27Inadequate Supply
ERCO Plant
- High Amperage
- Supply had to be on a radial line that also
served two paper mills which, conversely,
required high voltage. - Decided that it would make more sense for them to
consolidate their operations in Calgary - Ship their product over 2,000 km to the paper
mill in Thunder Bay - IPSP as it is currently framed is inadequate for
the demand needs of northwestern Ontario
28Boreal Forest Map
Hudson Bay Lowlands
North of the Undertaking
Boreal Forest
Great LakesSt. Lawrence Forest
Deciduous Forest
29Mining in Northwestern Ontario
Approximately 300 active exploration programs
4 producing gold mines 1 producing PGE mine
McFaulds Lake
Red Lake
Greenstone
Rainy River
30Mining in Northwestern Ontario
44.6 of the active mining claims in Ontario
31New Industrial Users
- Supply for an electric smelting plant. Currently
such a plant would be impossible without
additional generation transmission supply over
and above the proposed replacement supply 517
megawatts of the two thermal generating stations
32NWO as Electrical Island
33Where Northwestern Ontario Stands in Compliance
with Ministers Directives
- A) Conservation targets for northwestern Ontario
34Where Northwestern Ontario Stands in Compliance
with Ministers Directives
- Conservation and Demand Management
- Ministers Directive targets 1,350 megawatts cut
from peak demand for the entire province by 2010
and 3,600 more megawatts by 2025 - The problem has already been dealt with in
northwest Ontario
35Where Northwestern Ontario Stands in Compliance
with Ministers Directives
- For their own economic necessity
- Cooperated with both the former Ontario Hydro and
local utilities to level off periods of peak
demand in the northwestern Ontario grid - Some 200 megawatts in peak demand eliminated from
the northwestern Ontario system some fifteen
years ago - By production shifting
- Industrial users cooperate in shifting key
elements of their production to other time
periods - Irony, because northwestern Ontario is an
electrical island. - Surplus power saved in leveling peak demands in
northwestern Ontario cannot be exported to
Southern Ontario
36Where Northwestern Ontario Stands in Compliance
with Ministers Directives
- B) Residential Conservation
- Southern Ontario
- Much of the conservation targets set by the
Ministry will likely be met through more
effective residential use. - Residential use constitutes an estimated 70-80
of the demand as in southern Ontario - Reduction in demand will undoubtedly be large
37Where Northwestern Ontario Stands in Compliance
with Ministers Directives
- B) Residential Conservation
- Northwestern Ontario
- The comparatively small residential use (some
20-30 of demand) correspondingly, small
reduction in a correspondingly small segment of
Ontarios energy demand - Less than 5
- There is no recognition in the IPSP of how these
facts affect the achievability of the targets for
northwestern Ontario
38Renewable Energy
- Biomass
- Economic necessity industrial users in
northwestern Ontario have and continue to develop
biomass generation - For example, one of northwestern Ontarios paper
mills produces as much as 50 megawatts of its own
210 megawatts electrical energy needs - Difficult, therefore, for the OPA to propose
anything not already being implemented out of
economic necessity - Mandate of every mill manager appointed in the
last fifteen years to cut production costs - Especially given Ontarios uncompetitive
electricity costs
39Renewable Energy
- Wind Power Generation
- Planned Wind Generation
- IPSP proposes wind power installation
- One for example is on the shores of Lake Nipigon
in northwest Ontario - Other wind power developments elsewhere in
northwestern Ontario - Useful only as additional energy
- Unpredictability of wind means that its energy
generation cannot be considered part of the base
load capacity - Industrial users need to be able to rely upon
secure and adequate base load supply - Lack of suitable Inertial Reserve in Wind Farms
40Renewable Energy
- Related to dynamic behaviour and stability
- Due to the fact that wind generators will replace
conventional generators, possible problems in the
considered zones may arise related to - Reduced short circuit level, which could have an
impact on line protection. - Risk of local voltage collapse or risk of
prolonged voltage sags during grid faults - Reduced system inertia could impact stability in
island operation, if relevant - Small signal stability could be affected
Exhibit C-11-2 Attachment 29.9 page 28click here
for citation
41Renewable Energy
- In the NE and NW zones lack of sustained short
circuit power can become a problem. This would
have an impact in situations, when most of the
demand can be covered by the wind generation in
the zone. If in this case the majority of
synchronous generators are stopped due to the
limited export capacity and a line fault occurs
in the transmission system, the fault
contribution from one side may decay, so that
line distance protections cannot detect faults. - In the NE and NW zones, the behaviour of wind
turbines during grid faults can have significant
impact with risk of local voltage collapse in the
worst case or prolonged voltage dips due to
delayed voltage recovery in the best case.
42Renewable Energy
- Solar Generation
- Solar generation will be welcome as additional
energy - Cannot be considered part of the capacity
43Renewable Energy
- Hydro-electric Generation
- Many potential sites for new hydro-electric
generation within the northwestern Ontario
watersheds have been identified - The largest would produce 20 to 25 megawatts of
electricity - Exception is Little Jackfish 132 megawatts
- Considered peak power only, as water reserve is
exhausted in 4 hours
44Renewable Energy
- Hydro-electric Generation
- Desirable for local small-scale use
- Contributing very economically to the overall
supply of energy - None would be suitable for the base load capacity
industrial users must be able to rely upon - Caution
- Drought conditions that can and have reduced
production to around 30 of installed capacity
45Demand Management Uniquely Different
- Generally Demand Management will refer to the
efficient management of existing demand - For example, northwestern Ontario has succeeded
in leveling peak demands - Essential to realize that Demand Management in a
region that develops natural resources is
entirely different - The Demand to be planned for in northwestern
Ontario - Is beyond existing users
- Is beyond demographic projections
- Demand Management to be planned for northwestern
Ontario means planning to encourage development
46Issues for Phase IIRadial Circuits
- Radial circuitry that constitutes 95 needs to be
substantially upgraded - Looping the circuits in order to ensure more
stable and secure supply to industrial users - The IPSP as it is presently drafted has no
provision for looping any of the remote radial
transmission lines
47Northern Ontario Transmission System
48Red Lake Loop
- Loop of the Red Lake line with the Musselwhite
tap of the Ear Falls by Pickle Lake 115 kv
circuit could be installed - Such a loop would significantly increase the
stability and security of supply for - Existing Mines
- Municipal ties
- Proposed manufacturing of value added wood
products
49Longlac \ Geralton Loop
- Loop of the Longlac line with the Terrace Bay
line could be installed - Such a loop would make the same improvements for
similar customers in that part of northwestern
Ontario
50Without Such Loops
- Without such loops, at present, existing radial
transmission supply means - That downtime maintenance must be conducted only
on statutory holidays - In the event of any fault in the radial
transmission lines there is no alternate source
of supply - Inevitable result is unanticipated downtime
- Havoc with production schedules of the industrial
customer - Prolonged disruption to the residential customers
51- Enhancing the security and stability of the
electricity, a Red Lake looped and Longlac
looped, also enhance the possibility of radial
transmission from that loop - First Nation communities allowing them to replace
the diesel plants - To increase their capacity to develop local
industries - To assist in development of renewable generation,
such as small hydro-electric generation sites
52Inertia
53Inertia
- Southern Ontario
- Large number of looped transmission lines
- Many generating sources (especially large nuclear
generator turbines) - Transformers
- Other equipment
- Widely distributed industrial customers
- Create a very large inherent inertia in the
southern Ontario grid itself
- Northern Ontario
- By Contrast
- General absence of looped transmission lines
- Many small hydro-electric generating stations
- Even if wind turbine generation with their
relatively small turbines are included - All of these add little to inertia in the grid
- It is the two thermal generating plants that give
meaningful stability to the grid
54Energy Production Plus Inertia
- Section 5 of the Ministers Directive speaks of
replacement generation and adequate generating
capacity - Fundamental importance to appreciate the two
thermal generating stations contribute BOTH - 517 MW, and
- provide an estimated 40 inertia in the
northwestern Ontario grid - The Minister does NOT speak of replacement of
energy only but of generation (that is energy
PLUS inertia) - The IPSP provides only for energy replacement
55Remember the problems a few minutes ago related
to dynamic behaviour and stability in wind
generation?
56Energy Production Plus Inertia
- Due to the fact that wind generators will replace
conventional generators, possible problems in the
considered zones may arise related to - Reduced short circuit level, which could have an
impact on line protection - Risk of local voltage collapse or risk of
prolonged voltage sags during grid faults - Reduced system inertia could impact stability in
island operation, if relevant - Small signal stability could be affected
Exhibit C-11-2 Attachment 29.9 page 28click here
for citation
57LACK of RELIABILITY in Transmission Supply with
the IPSP
- Lack of system reliability Transmission supply
is not stable - The IPSP as it is currently drafted proposes
replacement of base load generation currently had
in the thermal generating stations with a
transmission supply that, in effect, is
purporting to be the base load supply
58LACK of RELIABILITY in Transmission Supply with
the IPSP
- In addition to the inertia taken out of the
northwestern Ontario grid, and not replaced, the
supply of energy through transmission supply has
the following problems - Transmission lines are vulnerable
- The 230 kv line from Manitoba to Marathon would
be the transmission source - Like all such transmission lines
- Vulnerable to transient and permanent faults
- Standard practice in electrical storms to reduce
transmission in the area of the storm to zero in
order to protect the lines and related equipment
59Electrical Storms
- In northwestern Ontario it is important
- That transmission of electricity in the 230 kv
line would be typically from west to east - That also is typically the course of an
electrical storm - As a result there is
- No reason to think that a transmission feed can
be considered a reliable source of base load
supply for northwestern Ontario even of energy
alone (forgetting inertia for the moment)
60Instability Over Length
- A maximum 350 megawatt load placed on the 230 kv
transmission line will by its nature cause the
supply of energy to be subject to voltage drops - That must be compensated for by using capacitors
- This will create instability and insecurity for
industrial users
61Likely Source of Energy
- Unlikely that the transmission feed will ever
come up from southern Ontario - Southern Ontario, obviously, needs everything it
can generate - The transmission feed on the 230 kv transmission
line will, in effect, come east from Manitoba - Impractical to theorize that the nuclear base
load supply in southern Ontario can be considered
to constitute a base load supply in northwestern
Ontario - The 300 megawatt load limit of the tie lines at
Marathon prevents that
62Manitoba Energy
- Manitobas hydro-electric generation is
susceptible to a drought as is northwestern
Ontarios - Typically Manitoba experiences drought before
northwestern Ontario - Most of Manitobas current hydro-electric
generation is largely pre-sold on long-term
supply contracts to the USA - When Manitobas own needs exceed available
hydro-electric demand, those deficiencies are
covered by calling on Manitobas alternate
supply, North Dakota
63Manitoba Energy
- Unless this OPA can demonstrate otherwise, it
must be assumed that any additional large amounts
of megawatts drawn on the transmission line from
Manitoba in order to replace the thermal
generation shutdown in the two generating
stations in northwestern Ontario will actually
end up coming from North Dakota - The source of North Dakotas export energy is
coal fired generation
64Lack of System Reliability
- Transmission Supply is NOT Sufficient
652008 Status Quo
1200 1000 800 600 400 200 0
990
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
Load
662008 Status Quo
1200 1000 800 600 400 200 0
990
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
517
Load
Supply
Excess
672008 Status Quo
1200 1000 800 600 400 200 0
207 MW
1197
990
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
680
517
Load
Supply
Excess
682014 The Problem
1200 1000 800 600 400 200 0
990
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
680
Load
Supply
692014 The Problem
1200 1000 800 600 400 200 0
300
990
Maximum Transferable
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
680
Load
Supply
702014 The Problem
1200 1000 800 600 400 200 0
?
10
300
990
Maximum Transferable
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
680
Load
Supply
Shortfall
712014 The Problem Growth
1200 1000 800 600 400 200 0
?
?
10
?
300
990
Maximum Transferable
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
680
Load
Supply
Shortfall
722014 Worst Case
1200 1000 800 600 400 200 0
990
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
226
Drought
Load
Supply
Shortfall
732014 Worst Case
1200 1000 800 600 400 200 0
990
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
Maximum Transferable
300
226
Drought
Load
Supply
Shortfall
742014 Worst Case
1200 1000 800 600 400 200 0
?
990
464
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
300
Maximum Transferable
226
Drought
Load
Supply
Shortfall
752014 Worst Case
1200 1000 800 600 400 200 0
?
164
990
300
Maximum Transferable
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
300
226
Drought
Load
Supply
Shortfall
762014 Worst Case Growth
1200 1000 800 600 400 200 0
?
?
?
990
464
Load Coal Hydroelectric East West Tie
Line Manitoba Tie Line Surplus Shortfall
300
Maximum Transferable
226
Load
Supply
Shortfall
77Conclusion
- The IPSP as it is currently drafted fails to
address northwestern Ontario as a sustainable
system for electrical supply
Electricity Act, (Section 1(a))
to ensure the adequacy, safety, sustainability,
and reliability of electricity supply in Ontario
through responsible planning and management of
electricity resources, supply and demand
The statutory regime is relevant. It cannot be
thought to be within the purview of the Board to
approve something that is in contravention of the
Electricity Act.
78Conclusion
- 2. The IPSP as it is currently drafted fails to
meet the goals of the Ministers Directive that
the IPSP provide for - Replacement generation
- Adequate generating capacity
- Strengthening of the transmission system
- System efficiency, and System reliability
79Conclusion
- The Intervenors
- NOMA (that is the Northwestern Ontario Municipal
Association) - The Town of Atikokan
- The City of Thunder Bay
- Urge the Board to review the IPSP as it pertains
to northwestern Ontario with a view to directing
the Ontario Power Authority, pursuant to section
25.30(5) to further consider the plan as it
pertains to northwestern Ontario
80In The Alternative
- These Intervenors propose the following be added
as an Issue for consideration by the Board in
Phase II - Does the IPSP plan for
- Replacement generation
- Adequate generating capacity
- Strengthening of the transmission system
- System efficiency, and
- Power quality and System reliability
- In the substantively different circumstances of
northwestern Ontario?