CIV Board of Directors Board and General Membership Meetings - PowerPoint PPT Presentation

1 / 46
About This Presentation
Title:

CIV Board of Directors Board and General Membership Meetings

Description:

System Test Acceptance on schedule for April 3. User Acceptance Test follows. ... Add additional functionality for Food Stamps. Add Medi-Cal, CalWORKs. Add ... – PowerPoint PPT presentation

Number of Views:192
Avg rating:3.0/5.0
Slides: 47
Provided by: kitbatt
Category:

less

Transcript and Presenter's Notes

Title: CIV Board of Directors Board and General Membership Meetings


1
C-IV Board of Directors Board andGeneral
Membership Meetings
  • SAWS Consortium IV, C-IV System
  • January 30, 2009

2
Agenda
3
Agenda cont.
4
Migration Project Status Overview
On Time and On Budget!
5
Update on Migration Development
  • Completed do no harm to Original County testing
    for CMSP Online Rules. Deployed to C-IV
    Production June 2008 (8.06).
  • Completed development currently in System Test
    and on progress for deployment to C-IV Production
    July 2009 (9.07)
  • Replication of approximately 100 batch programs,
    29 interfaces
  • CMSP Reports/Forms/NOAs/Eligibility
  • New interface development (Warrant Print, Auditor
    Controller, Direct Deposit, etc.)
  • New Reports/Forms (35 local/rush warrant
    templates, MEDS Progress Reports, etc.)
  • System Test Acceptance on schedule for April 3.
    User Acceptance Test follows.
  • Remaining Development
  • The project accommodated over 80 enhancements
    (SMCRs) by reallocation of time on items not yet
    worked and allocation of 500 hours managed by the
    Consortium
  • Over 80 of these SMCRs are complete. Remaining
    items include Stale and Paid Warrants, Siskiyou
    Warrant Print Check Stock, CMSP Policy changes.

6
Update on Migration Conversion - Data Clean-up
  • Current Status
  • Currently 3 Data Cleansing requests have been
    sent to the counties (All Waves)
  • No show stoppers currently identified
  • A higher volume of Data Cleansing requests is
    expected to start in March 2009 (All Waves)
  • This aligns with the Conversion Team completing
    build activities and entering Conversion System
    Test March 1

7
Update on Migration Conversion - Data Clean-up
  • Data Cleansing Tracking
  • C-IV is tracking the progress of each Data
    Cleansing item on a monthly basis beginning
    mid-February 2009
  • The Data Cleansing Tracking Report will show a
    summary of the items left to be cleaned-up and
    detailed breakdown of the activity per month
    completed on each item
  • By the 15th of each month an updated CIT will be
    sent to the County notifying them that updated
    Data Cleansing Reports have been posted to the
    Web Portal and a new Data Cleansing Tracking
    Report has been posted
  • The Data Cleansing Tracking Report will report on
    progress through the end of the prior month. (On
    April 15th the counties will receive a report of
    progress through March 31st)

8
Update on Migration Conversion Mock Conversions
  • Mock Conversions
  • There are currently 7 Mock Conversions scheduled
  • Wave 1 May 2009 September 2009 (4)
  • Wave 2 December 2009 January 2010 (2)
  • Wave 3 April 2010 (1)
  • Each County will have access to their converted
    data (accessed through the C-IV System) for a
    period of 4 weeks during a Mock Conversion for
    the Wave
  • Wave 1 7/5/09 7/23/09 8/10/09 8/14/09
  • Wave 2 1/4/10 1/22/10 2/1/10 2/5/10
  • Wave 3 4/5/10 4/23/10 5/3/10 5/7/10
  • County provides resources to confirm that their
    data is being migrated effectively
  • This is the Countys opportunity to preview the
    migrated data before cutover
  • It is anticipated that the County resources will
    be able to access C-IV from the County

9
Update on Migration Development Status Release
Schedule and Scope Management
  • New Scope Management Change Requests (SMCRs) will
    not be included in the Migration Release (9.07)
  • Release 9.07 includes all of Migration required
    modifications
  • Critical path from System Test to UAT to Training
    to Wave 1 Go Live!

10
Update on Migration Development Status UAT
  • UAT Plan is complete
  • Recruitment of UAT Testers began in January
  • Testing will be conducted April 1 June 5, 2009
  • UAT Testing will be conducted at the project site
  • UAT testing will focus on CMSP functionality,
    Reports, Forms, NOAs and Rush Warrant Print
  • UAT will include both scripted and unscripted
    testing
  • There is funding for salaries, benefits and
    travel

11
Overview of the Migration Implementation and
Communications
12
CIV Consortium By the Numbers...
Original 4 Counties
Migration Counties
C-IV Production Counties
Merced 400 Users 9 Offices
Wave 1 2907 Users 78 Offices
Imperial 398 Users Inyo 23 Users Kern 1612
Users Kings 251 Users Mono 8 Users Monterey 554
Users San Benito 62 Users
Stanislaus 543 Users 6 Offices
Riverside 1985 Users 51 Offices
San Bernardino 3308 Users 65 Offices
Wave 1 2907 Users 78 Offices
Total 6236 Users 131 Offices
Wave 2 2358 Users 90 Offices
Wave 2 2358 Users 90 Offices
Alpine 1 User Amador 27 Users Calaveras 40
Users El Dorado 119 Users Glenn 51 Users Lake 120
Users Madera 288 Users Marin 140
Users Mariposa 18 Users Mendocino 156
Users Napa 95 Users San Joaquin 1217
Users Tuolumne 55 Users
Total 9143 Users 209 Offices
Total 11501 Users 299 Offices
Wave 3 1585 Users 74 Offices
Total C-IV Consortium at completion of Migration
13,086 Users 373 Offices
Wave 3 1585 Users 74 Offices
Butte 363 Users Colusa 32 Users Del Norte 66
Users Humboldt 197 Users Lassen 41 Users Modoc 16
Users Nevada 69 Users Plumas 19 Users Shasta 291
Users Sierra 3 Users Siskiyou 81 Users Sutter 152
Users Tehama 115 Users Trinity 22 Users Yuba 150
Users
Migration Total 6850 Users 242 Offices
13
Overview of the Migration Implementation and
Communications Plan, Schedule Deliverables
  • Pre-Implementation
  • Create Implementation Plans (Deliverables) with
    County Review
  • Conduct Site Prep and Installation of
    Hardware/Software
  • Build and Test Interfaces
  • Verify End Users and Type of Training Required
  • Prepare Adhoc Report Users for New Reporting
    Methods
  • Prepare County Points of Contacts for Project
    Activities
  • Conduct Change Management Analysis and Train
    Staff on Process Changes
  • Conduct C-IV System Training
  • Conduct Data Cleansing and Conversion Prep/Mock
    Conversion
  • Cutover to C-IV
  • Prepare Counties for Go Live
  • Cutover Weekend
  • Post-Implementation
  • Provide In-County Support
  • Issues Resolution

14
Sample Implementation Activities by Wave
15
Overview of the Technical Migration Development
and Implementation Activities
  • Migration Development
  • Commodities Procurement 4 February 2009
  • Server Installation and Configuration May 2009
  • Performance Testing Through May 2009 and
    Continuously After
  • Oracle RAC Upgrade August 2009
  • System Operations and Support Plan Through April
    2010
  • Migration Implementation
  • Hardware and Software Acquisition Plan December
    2008
  • Imaging Plan December 2008
  • Site Survey, Preparation, and Installation
    Through March 2010

16
Review DTS POP Network Issue and Status
  • Dec. 11 - Met with DTS OSI to discuss Technical
    and Service Delivery issues. DTS to provide
    document on issues in two weeks
  • Dec. 15-18 Conference calls with DTS POP
    counties to inform of status of issue and options
  • Dec. 24 Received documents from DTS. Technical
    issues largely resolved. Service Delivery issues
    still outstanding
  • Jan. 5 Submitted C-IV response to DTS documents
    to OSI
  • Jan. 5 Napa County formally requests to change
    to County POP Model
  • Jan. 22 Follow-up conference call held with DTS
    POP counties

17
Update on C-IV MO
  • The MO Phase of the Project has been underway
    for 50 months.
  • MO highlights since the September 2008
  • Automated Medi-Cal Redetermination Packets
  • Upgraded to Java 5, Web-Logic 10
  • Implemented 3 of the 5 phases for Time Limits
    enhancements - database and page updates
    complete. The last 2 phases will increase
    automation and will occur post-Migration.
  • Enhanced Resource Data Bank to show cross county
    impacts

18
Update on C-IV MO
  • MO Planned Release Highlights, available to all
    39 counties as they migrate
  • CMIPS-II Design for C-IV Online IHSS referral
    processing
  • 9.01 Add Spell Check, County maintained
    valuables (45 enhancements)
  • 9.02 ACL 08-30 Reporting, EBT PIN unlock
  • 9.03 Training Data Refresh, FNS 209 Report
    Updates
  • 9.04 County maintained mileage rates, CA 237 FC
    Report Updates
  • 9.05 Automate Cal-Learn, Enhance Intake
    Scheduling, Confidential Case Restrictions, CA
    812 Report Updates
  • 9.07 Merge Migration Code with MO Code
  • 9.09 Change EBT Vendor from JPM Chase to ACS,
    WPR Enhancements
  • 9.11 New programs for C4 Yourself CMSP,
    CalWORKs, Medi-Cal

19
C-IV MO Release 9.01 Recap
  • Release 9.01 deployment was delayed 1 week to
    February 1. This was the first time in 53 monthly
    releases there has been a delay.
  • What happened
  • The database structure is changing to support an
    SCR which creates tighter coupling of the Person
    and their Application Status. This involves over
    57 million rows of database updates.
  • This SCR was tested through CIV development
    lifecycle and was applied to Staging to get a
    Production timing estimate of 15-20 hours, within
    the deployment timeframe of 2am Sunday to 2am
    Monday.
  • The Production timing estimate was inaccurate due
    to additional time needed to update both Disaster
    Recovery and Ad-hoc databases while maintaining
    archive and rollback logs. At 2pm Sunday the
    update was 12 hours through running with 20
    hours projected remaining. After functional and
    technical review confirmed no mandate for
    deployment timing, rollback was initiated to
    ensure C-IV Online would be up Monday morning.
  • What we measures are we researching, to execute
    differently this weekend
  • Increase Rollback and archive logs (both size and
    scale) to reduce contention.
  • Segment database structure update into
    subroutines some of which can start earlier in
    the deployment cycle.
  • Decouple Ad-hoc database update from Production
    and Disaster Recovery. This may result in a delay
    of Ad-hoc availability until Tuesday. This SLA
    exception has been approved to provide greater
    contingency.
  • Research any network tuning parameters to improve
    file transfer speeds.

20
Update on C-IV Work Participation Rate (WPR)
functionality and status
  • The project has planned the rollout of WPR as
    follows
  • Data Collection (C-IV page changes necessary for
    adequate data entry and tracking) targeted for
    July 2009 implementation
  • Work Eligible Individuals (WEIs) Determination
    (mandatory participants) targeted for March
    2009 implementation
  • Work Participation Rate (WPR) Determination (the
    percentage of mandatory participants that meet
    the federal work participation requirements)
    targeted for November 2009 implementation
  • Reporting (integrate all necessary WPR
    reporting into C-IV Solution) -targeted for
    November 2009 implementation

21
Update on C-IV Work Participation Rates (WPR)
functionality and status
22
Update on C-IV Medi-Cal PII Safeguards
  • C-IV is in compliance with the physical and
    security safe guard requirements set forth by the
    State, with the exception of the following
  • All systems must time out after 20 minutes of
    inactivity. Currently, C-IVs time out is set at
    30 minutes. SCR 33323 has been created to address
    this issue and will be implemented prior to June
    2009

23
Update on C-IV Medi-Cal PII Safeguards
  • In addition to C-IVs compliance, each county in
    the consortium will need to take appropriate
    action(s) to confirm they are in compliance with
    each section of the Privacy and Security
    Agreement. For example
  • Section I/X General confidentiality policies
    must be signed for all contracted staff (cleaning
    crews, temporary workers, etc)
  • Section II/IV Training for staff that have or
    will have access to PII and maintaining
    certifications of agreement to comply with
    privacy/confidentiality and security safeguards.
  • Section III Risk Management reviews/corrective
    action plans
  • Section V Physical security onsite and at
    applicable storage warehouses.
  • Section VI Remote access of PII and encryption
    of portable media devices.
  • Section VII Paper document controls within the
    county.
  • Section VI/VIII This section relates to the
    policies and procedures, which address
    identifying and responding to suspected or known
    security incidents. C-IV contains this ability
    however, counties must request the functionality
    be turned on in order to obtain the log entries
    of a particular person, case, etc.
  • Section IX Self assessments

24
Review Workstation Distribution Policy
  • Utilizes workstation counts from RFP
  • Prioritizes distribution - Core Users first
  • Provides Methodology for true-up by Wave
  • Options to address additional needs
  • True-Up Allotment (100 per wave)
  • Use County-owned PCs as non-managed
  • Use State-owned (ISAWS) PCs as non-managed
  • County Purchase Process

25
Overview of Strategic Direction and Status from
October JPA Board Retreat C4Yourself
  • C4 Yourself www.c4yourself.com
  • FNS Grant C4Yourself implemented in all C-IV
    counties on 10/29/2007. Currently receiving over
    300 applications per week. Total processed as of
    12/31/2008
  • Enhancements targeted for November 2009
  • Add additional functionality for Food Stamps
  • Add Medi-Cal, CalWORKs
  • Add CMSP program

26
Overview of Strategic Direction and Status from
October JPA Board Retreat C4Yourself
  • FNS funding was approved by the Board last month
  • CMSP funding was approved by the CMSP Board on
    December 18th and was submitted for JPA Board
    approval today
  • We have conducted 2 workgroup meetings and are on
    schedule to have enhancements complete by
    November 2009

27
Overview of Strategic Direction and Status from
October JPA Board Retreat Enhanced IVR
  • First Steps
  • Share marketing tools/plan with production
    counties
  • Complete staff survey to determine types of
    questions received from customer phone calls to
    determine what additional information could be
    included on IVR

28
Overview of Strategic Direction and Status from
October JPA Board Retreat Electronic Signature
  • Identified possible options upon completion of
    research in the following
  • State Correspondence
  • Civil Code
  • Other States/systems using electronic signature
  • Accenture completing technical research of
    identified options
  • Will work with the Counties on solution and
    identifying/discussing any other issues
  • End product a global solution that will work for
    online self service or worker supported use

29
Overview of Strategic Direction and Status from
October JPA Board Retreat Imaging
  • Production Counties and five additional Migration
    Counties plan to acquire new imaging system
  • Counties are working together to
  • Identify funding
  • Develop justification for qualifying MC PII funds
  • C-IV is working with counties to identify funding
    approaches and timelines

30
Overview of Strategic Direction and Status from
October JPA Board Retreat Tech Enabled Worker
Automation
  • Ideas will be requested from County staff via CIT
    / CRFI, on how to utilize the C-IV System to
    streamline a worker's daily tasks. Current Cost
    Saving Ideas (CSI) are being gathered in
    Stanislaus.
  • Some current ideas are
  • Using the C-IV System to pre-populate
    recertification documents so that customers would
    only enter changed information
  • Use electronic signature capabilities to enhance
    worker interviews with customers in the office
  • Use the new imaging solution to streamline the
    flow of paper documentation within the agency
  • Use an enhanced IVR System to reduce the amount
    of time a worker is answering customer's routine
    questions

31
Update on C-IV Consortium Staffing (MO and DI)
  • M O
  • Riverside has received applications and
    interviews are scheduled for one vacancy
  • One vacancy (Merced) remains to be filled as soon
    as possible
  • D I
  • 11 vacancies remain. El Dorado may be able to
    contract for some positions. Openings include
  • 1 Site Prep
  • 1 Implementation Coordinator
  • 1 Change Management Coordinator
  • 3 Training Coordinators
  • 4 Trainers
  • 1 Admin Assistant

32
Budget Update/Overview Migration DI Budget
  • SFY 2008/09
  • Planned expenditures on target
  • SFY 2009/10
  • Migration DI fully funded
  • SFY 2010/11
  • IAPDU planning in progress

33
Budget Update/Overview C-IV MO Budget
  • SFY 2008/09
  • Increasing print volumes due to increased
    caseload and system functionality. 
    Re-allocations will cover additional costs
  • SFY 2009/10
  • MO fully funded
  • SFY 2010/11
  • IAPDU planning in progress

34
Budget Update/Overview Overview of SFY 08/09
County Administrative Expenses
  • Insurance Services and KPMG SAS70 Internal Audit
    Actuals were slightly less than planned.
  • VTD External Financial Audit Acct II Position
    Solely 4 Actuals will equal projections.
  • Acct. II Position Solely 35 Position remains
    open. Projection decreased.

35
Update on Status of Integration of Migration
Counties into C-IV MO Sub-committees
  • A draft recommendation is in review by CPMs
    which will include
  • Committee Structure
  • Representation
  • Voting
  • Committee Selection Process
  • Currently in development
  • Similar to the existing ISAWS selection process
  • Timeline
  • A final recommendation will be brought before the
    Project Steering Committee in February

36
Overview of ISAWS Project Migration Activities
  • Project Closure State Owned Equipment
  • MCRs
  • Conversion Activities
  • Dedicated County Issue

37
Overview of ISAWS Project Migration Activities
State Owned Equipment
38
Overview of ISAWS Project Migration Activities
State Owned Equipment
  • Notifications sent to ISAWS Counties
  • Why equipment will need to be decommissioned
    (ISAWS Project Closure and Public Contract Code
    Section 10389.1)
  • Again DO NOT PANIC!
  • Will work with Counties on Exemption requests
    where needed

39
Overview of ISAWS Project Migration Activities
MCRs
  • MCR 2381 Migration Work Activities (8/29/07 -
    7/30/10)
  • MCR 2398 GEMS Conversion (1/21/08 - 1/29/09)
  • MCR 2405 Legacy Data Solution (4/22/08 -
    7/30/10)
  • MCR 2411 Conversion Batch Process Analysis
    (6/30/08 - 3/31/09)
  • MCR 2412 Mock Conversion Activities (9/25/08 -
    3/31/10)
  • MCR 2415 Cutover Activities (11/17/08 -
    7/30/10)
  • MCR 2418 Conversion Data Validation (8/26/08 -
    1/29/09)
  • MCR 2421 Convert WTW NOAs to PDF format (2/2/09
    - 4/30/09)

40
Overview of ISAWS Project Migration Activities
Conversion Activities
  • Weekly Conversion Meetings
  • Meetings With Interface Partners As Needed
  • Converted Data Testing - Ongoing
  • Monthly System Loads - Ongoing
  • Incremental System Loads - Starting In February
  • Data Validation Testing Has Started
  • Mock Conversion In Requirements Phase

41
Overview of ISAWS Project Migration Activities
Dedicated County Issue
  • ISAWS Dedicated Counties
  • 11 Counties Listed by Wave and Equipment Install
    Start
  • Wave 1 Inyo, Mono, Imperial
  • Wave 2 Glenn, Lake, Alpine, Tuolumne, Amador,
    Mariposa
  • Wave 3 Colusa, Trinity
  • CTS Working With The Counties
  • Network Solutions
  • Equipment Installation
  • APDs
  • Coordination Of Effort With C-IV Equipment
    Installation
  • Goal Have completed 30 days prior to Equipment
    Installation
  • Tracking progress of all Counties not just ISAWS
    Dedicated Counties

42
C-IV Procurement Project
  • Business Need
  • The current Maintenance Operations (MO)
    contract with Accenture ends on October 31, 2011.
    The Consortium requires on-going goods and
    services to be secured from a qualified MO
    contractor at least six months prior to the end
    of the current contract term
  • C-IV Procurement Project Phases
  • Phase 1 Secure the services of a Planning
    Consultant
  • Phase 2 Secure the services of a Maintenance
    Operations Contractor

43
Overview of C-IV Procurement Calendar
44
Overview of JPA Board and General Membership
Calendar for 2009
45
Overview of JPA Board and General Membership
Calendar for 2009
46
Adjourn Meetings
Write a Comment
User Comments (0)
About PowerShow.com