Automated Collimation Operation - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Automated Collimation Operation

Description:

Collimation Controls Steering team (Cocost) Stefano Redaelli (high level control ... During the SPS MD, not able to make clean cut in the beam distribution ... – PowerPoint PPT presentation

Number of Views:187
Avg rating:3.0/5.0
Slides: 17
Provided by: jon46
Category:

less

Transcript and Presenter's Notes

Title: Automated Collimation Operation


1
Automated Collimation Operation
  • LHC-MAC 2007 06 15
  • M.Jonker
  • On behalf of the collimation project
  • (as the controls coordinator)

2
Collimation Controls
  • Collimation Controls Steering team (Cocost)
  • Stefano Redaelli (high level control
    applications)
  • Maciej Sobczak (css, middle level)
  • Roberto Losito (low level control)
  • Alessandro Masi (low level control)
  • Ralph Assmann (project leader)
  • Michel Jonker (controls coordinator)
  • Invited
  • Philippe Gayet (plcs)
  • Rudiger Schmidt (machine protection)
  • Bernd Dehning (beam loss monitors)

3
Outline
  • 94 (up to 160 in final upgrade) collimators, to
    protect against machine damage and magnet
    quenches.
  • The collimation process is a multi-staged process
    that require precise (0.1 ?beam) setting of the
    jaws with respect to the beam envelope.Goal for
    positioning accuracy is ?20 ?m (0.1 ?beam at 7
    TeV).
  • Actual beam envelope (position and size) may
    change (from fill to fill ?, by how much?)

4
Collimation Optimisation
  • Adapt to changing beam parameters to guarantee
    machine protection and to keep good cleaning
    efficiency
  • There are 376 degrees of freedom (4 motors per
    collimator) (188 if not considering the angle of
    the jaws)
  • 30 seconds per degree of freedom (a very
    efficient operator) still requires about 3 hours.
  • ? We need automated tools and procedures

5
Setup Procedures
  • Beam probing
  • Determine beam positions and size at every
    collimator by touching the beam.
  • Required for initial setup of a machine optics
    (injection and top energies ), or after
    substantial changes in beam parameters.
  • Setup at with a low intensity beam 5 nominal LHC
    bunches (equivalent to the Tevatron Beam in
    stored energy).Extrapolation from 5 to 3000
    bunches(bunch train effects?)
  • Fast beam based setup
  • Position collimators based on loss patterns, not
    on measured beam positions and sizes
  • Further systematic optimisation with nominal
    intensity beam
  • Response matrix corrections
  • Correct collimator positions guided by loss
    patterns.

6
Response matrix corrections
  • Fine tune and optimise the cleaning efficiency
    (at injection or top energy).
  • Collimator response matrices to translate a given
    beam loss pattern into an adjustment of multiple
    collimator positions PC Mblc ? BL
  • Theoretical matrices have been calculated based
    on Fluka and Struct programs.
  • Ambitious procedure, commissioning of this
    process will require many machine studies.
  • Not for the beginning
  • Not discussed here

BLM loss pattern
Collimator Settings
7
Beam Probing
  • Establishes the beam positions, angle and size by
    probing the actual beam.A traditional method
  • Starts with producing a well-defined cut-off in
    the beam distribution.
  • Each collimator jaw is moved until the beam edge
    is touched. This step defines an absolute
    reference position for each jaw. (and angle if
    two motors are moved independently)

Beam Loss Monitor
Beam Loss Monitor
  • Note Best done from the last element in the
    cleaning insertion to the first
  • Collimators may stay in place
  • Machine is better protected against quenches
  • Disadvantages
  • Only possible with low intensity beam (i.e. 5
    bunches).
  • Slow if done manually (188 positions )
  • Delicate (e.g. moving a collimator too far
    changes the cut-off in the beam distribution).

8
Beam Probing in SPS MD
  • Beam probing was tested in the collimation MD at
    the SPS in 2006 with the collimation control
    system.
  • The jaws were driven in by the control
    application either manually or in repetitive
    steps.
  • The control application simultaneously displays
    jaw position and Beam Loss Data

In the MD, to speed up we used successively
smaller steps, and while doing so we scraped the
beam away bit by bit.
9
Fast beam based setup
  • Complements the traditional set-up method.
  • Adjust positions to reproduce known beam loss
    pattern.
  • Based on experience of other acceleratorsCollima
    tion efficiency is more closely related to beam
    loss patterns than to absolute collimator
    positions, which are sensitive to orbit
    deviations, beta beat, etc.
  • Move jaws in hierarchical order into the beam
    halo up to the point where a specified beam loss
    level is recorded in the adjacent beam loss
    monitors.

Beam Loss Monitor
Beam Loss Monitor
  • Fast if implemented as an automated procedure
  • Start at a fixed offset relative to a previously
    known position (only have to move short
    distances, no need to be retracted.
  • Two beam can be tuned in parallel in the two
    cleaning insertions IR3 and IR7

10
Fast beam based setup
  • Procedure in practice
  • The collimators are set at 1.5 s retracted with
    respect to the last optimised value.
  • The jaws are optimised one by one in a precise
    order.
  • Optimization by moving in steps of 0.05 s until
    the associated set of Beam Loss Monitors (BLM)
    detects a predefined value of beam loss.The BLM
    reference levels are found empirically and may be
    updated from fill to fill.
  • Timing implications
  • Starting position 1.5 s, step size of 0.05 s
    (?50 µm _at_ 450 GeV)
  • ? 30 steps/motor ? 9600 steps in total (only
    position, no angles, final upgrade).
  • Available time 5 min. two rings in parallel ? 60
    ms per step (16 Hz)
  • _at_ 2mm/s 50 µm ? 25 ms per step needed for motor
    movement
  • gt 35 ms for driving, data collection, reading
    BLM, deciding

11
Controls Architecture
  • Control room software
  • Management of (critical) settings (LSA)
  • Preparation for ramp
  • Assistance in collimator tuningPost Mortem data
    collection and Analysis
  • Based on standard LSA components
  • Dedicated graphical interface for collimator
    control and tuning
  • Collimator Supervisor System (CSS)
  • Support building, VME / FESA
  • Fesa Gateway to Control Room Software
  • Synchronization of movements
  • Beam Based Alignment primitives
  • Takes action on position errors (FB)
  • Receives timing, send sync signals over fiber to
    low level (Ramp Beam Based Alignment)
  • Synchronization and communication with BLM
  • Low level control systems
  • 3 distinct systems
  • Motor drive (PXI)
  • Position readout and survey (PXI)
  • Environment Survey (PLC)

BLM system
12
Fast Optimisation Primitives
  • Collimator Supervisory System (CSS)
  • Send a trigger to adjacent BLM system on every
    motor movement
  • BLM system sends a short transient data to the
    CSS
  • Optimization primitive command (on CSS)
  • Move until BLM-level
  • Parameters
  • Motors and step size
  • BLM signals and limits
  • Repetition frequency
  • Maximum steps
  • Example
  • Move Jaw-left in steps of 10 um every 30 ms until
    BL signal reaches 103
  • This optimization primitive can be used by a
    central application for
  • Beam Probing
  • Fast beam based optimization

Beam Loss Monitor
13
Fast Optimisation Primitives
During optimization, positions are continuously
measured, If the position gets out of tolerance,
the procedure will be interrupted.
15 µm
25 µm mechanical play
R. Losito et al
14
BLM Transient in SPS MD
  • Adjacent BLM triggered by collimator movements.
  • Collected data
  • Transient Data Buffer (2.5 ms sampling 80 ms for
    BLM based FB).
  • Post mortem data (40 us sampling over 1.7
    seconds)
  • (For analysis)
  • Data needs carefull interpretation.
  • LHC acquisition chain tested, including link with
    collimators (trigger and data transmission).
  • Plots from Daniel Kramer

15
Conclusion
  • Fast collimator optimisation is technically
    possible.
  • The controls architecture contains the necessary
    elements to deal with these requirement
    (synchronisation lines, BLM data acquisition and
    connection)
  • The principles have been tested during an SPS MD
    in 2006
  • Fully automated steering application and
    procedures to be developed and tested (2008)
  • However, the real challenge
  • beam dynamics
  • SPS md BLM responds to collimator movement over
    time scales of 100th of ms

16
Conclusion
During the SPS MD, not able to make clean cut in
the beam distribution Re-populatution of tails
over 100th of ms.
Long tails after collimator movement, Large noise
components
50, 150, 300, 450 600 Hz noise
SPS MD in 2007 to investigate the origins of
these problems If these effect are also present
in the LHC, optimisation will me more challenging.
17
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com