1MPS Commissioning
- MPS commissioning may be split roughly in 2 parts
- A technical commissioning of all interlock system
clients to ensure that all systems work properly. - gtgt this part is discussed today!
-
- A beam commissioning where correct settings must
be established to provide protection up to a
defined energy/intensity (collimator absorber
positions, BLM thresholds).
2LHC BIS Overview
Movable Detectors
Beam Loss Monitors BCM
Experimental Magnets
Collimator Positions
Environmental parameters
LHC Devices
LHC Devices
Safe Beam Parameter Distribution
LHC Devices
LHC Experiments
Collimation System
Transverse Feedback and RF
Beam Aperture Kickers
SpecialBLMs
Operator Buttons CCC
Safe LHC Parameter
Software Interlocks
Sequencer
Beam Dumping System
Beam Interlock System
Safe Beam Flag
Powering Interlocks sc magnets
Powering Interlocks nc magnets
Magnet Current Monitor
Beam LifetimeFBCM
Screens / Mirrors BTV
Access System
Vacuum System
Beam loss monitors BLM
Timing System (Post Mortem Trigger)
Monitors aperture limits (some 100)
Monitors in arcs (several 1000)
Power Converters
Magnets
MPS (several 1000)
Power Converters 800
AUG
UPS
Cryo OK
Doors
EIS
Vacuum valves
Access Safety Blocks
RF Stoppers
3BIS core
- User connection tests in progress, finished
beginning July. - gtgt When a connection is tested, can start MPS
tests for the associated system. - Beam permit loop robustness tests in progress
(all inputs disabled) - Driven by B. Puccio his team.
4LHC Machine Protection Powering System gt50 of
all interlocks
- PIC
- Majority of interlocks are commissioned during
HC - Missing PIC-BIC connection / mapping of
circuits (unmask, mask, ignore) - PIC-BIC test to be done with the sequencer, ready
by July (needs BIC input add-on). - Time requirement 1 day/2 shifts per sector
pair. - Requires 2 adjacent sectors available reserved
for the tests. - Effort driven by Markus Z., Alvaro
Beam Interlock System
Powering Interlocks sc magnets
Powering Interlocks nc magnets
Magnet Current Monitor
- WIC FMCM
- Require powering of nc circuits.
- Test can be done together with PIC tests
- gtgt Proposal is to join with PIC tests
- Smaller number of tests wrt PIC gtgt manual tests ?
Power Converters
Magnets
MPS (several 1000)
Power Converters 800
AUG
UPS
Cryo OK
5LHC Machine Protection Vacuum System
- Vacuum valves in one octant (including long
straight section) can only be opened when
conditions allow for opening, (magnets cold
etc.). - Details to be defined
- Test (open/close) every single valve.
- Random sample testing
- Effort driven by Gianluigi, BIS team and VAC
Team. - Need to wait for later stage of HC.
6LHC Machine Protection Collimation System
Collimator Positions
Environmental parameters
- Collimator interlocks include position env.
parameters. - Tests do not interfere with HC relatively
independent. - Settings and tests have been agreed upon, comm.
driven the collimation team - Specs being updated.
- General strategy is defined, with automated
sequences to probe every sensor. - Starting soon
Collimation System
Beam Interlock System
7LHC Machine Protection Beam Dumping System
Beam Dumping System
Beam Interlock System
- Ongoing testing during dry runs (with special
BIS configuration), but such dry runs are not
really MPS tests ! - With LBDS every test is related to MPS
- IST spec seems to exist lots of testing
done/ongoing (EC dixit) - The MPS spec is . basically empty must cover
non IST, for example Beam Energy Tracking (BETS)
system. - gtgt Rather urgent need to define the tests (LBDS
team) - BETS tests can only be performed when all energy
sources are connected - MSDs, Q4s, kickers
- MBs 4-5, MBs 5-6, MBs 6-7, MBs 7-8 (½ of the
machine !)
8LHC Machine Protection Beam Loss Monitors
- Another special system ISTs and MPS tests are
basically the same, since almost every function
of the BLMs is associated to MP! - MPS spec in medium state, IST spec much better
- Replace MPS spec with IST spec?
- IST spec check ?
- Most of the effort will be driven by the BLM
team, coordination with MPS commissioning to be
sorted out in the coming days.
9LHC Machine Protection BTVs
- Tests are straight-forward and can be done as
soon as BIC connection is ready BTVs ready to
move. - The possibility to re-use the automated test SW
of the SPS transfer lines is under investigation
(JW). - Driven by R.Giachino JW.
10LHC Machine Protection Experiments
- Test categories
- Magnets must test the interlock on fault state.
- Movable detectors VELO, ALICE ZDC ???
- Emergency dump whoever is ready (ATLAS, LHCb
??). - Injection inhibit
- Not a lot of work, mostly coordination.
- Alick has (been) volunteered.
11LHC Machine Protection Injection System
- Partly tested during dry runs.
- Relatively modest system, many inputs are
similar to ring and transfer line interlock
systems - Vacuum.
- BLMs.
- MKI.
- FMCM.
- Collimators.
- Tests of the extraction interlock master BIC done
together with TL interlock tests (a significant
part already done). - In hands of Verena, Jan JW.
12LHC Machine Protection Other systems
- Operator button straightforward (Bruno with the
BIS Team) - Aperture Kicker
- Injection Kicker
- Beam Position IR6
- there is not much one can do before beam.
- RF and Transverse Feedback
- only cryo interlock on RF for the startup.
- Beam Current Monitor
- Access System
13SIS General
- LHC SIS is not as critical for safe operation at
the LHC as the SPS SIS is for the SPS and some of
its lines. - LHC SIS will produce 4 signals
- Injection inhibit beam 1 and beam 2 gtgt injection
BICs - Beam dump both beams gtgt CCR BIC
- (Some) alarms
- gtgt initially favour alarms over beam dumps
(reliability of clients!) - SIS running since a few months (also stress test)
with a period of 2 seconds between signal
updates. - Signals are not yet send to the BICs to avoid
interferences with BIS commissioning but can be
armed any time. - Configuration not yet final waiting for some
signals appear in the control system.
14SIS Commissioning
- Largest interlock group
- State of 800 (non-PICed) cold orbit correctors
gtgt inj. inhibit. - Configuration ready to be tested.
- Could be automated with sequencer.
- Many smaller groups that will require dedicated
time to cycle through states, modes etc - BTVs gtgt inj. inhibit
- Integrated field of CODs gtgt beam dump requires
the complete machine ! - Current limits on separation dipoles MCBX gtgt
inj. inhibit (exp. protection _at_ injection). - RF cryo gtgt inj. inhibit ( beam dump ?)
- Energy intensity limits (MPS limits) gtgt beam
dump - whatever pops up
- Im in charge
15Summary
- MPS commissioning effort to start soon, mostly
likely beginning of July - All BIS connections ready.
- Major systems (powering, collimators, ) ready
with test SW/sequences - - Powering comm. could be done in 8 shifts
- Clarifications are needed for BLMs and LBDS.
- Safe machine parameter commissioning to be
defined, BIS team Alick.