Title: CPETECET 470 Project Management


1
CPET/ECET 470Project Management
  • Class 3 - Planning Scheduling

2
Course Topics
  • Focus
  • Understanding project planning and control
  • Specific Topics
  • Planning
  • Definition of Work
  • Scheduling
  • Budgets
  • Measuring Progress/Controlling Cost
  • Easy to do
  • Your role in the process
  • Risk Management
  • Risk Evaluation
  • Risk Mitigation

3
Stages of Planning
Define Ultimate Goal
Construct Statement of Work
Define Work Breakdown Structure
Create Summary Level Schedule
Create Detailed Schedule
Define Budgets
4
Work Definition Levels
SOW Requirement
SOW
SOW/WBS Overlap
SOW WBS
Upper Level WBS Element
Cost Account
WBS Schedule
WBS/Schedule Overlap
Work Package
Schedule
Task
Schedule
5
Responsibility Assignment Matrix
  • Responsibility Assignment matrix (RAM) is an
    integration of the Program Organization Chart
    (Organizational Breakdown Structure) and the CWBS
  • The RAM ties the work to the responsible person
  • Establishes responsibility for WBS elements
  • Assigns the Cost Account Manager (CAM)

6
Assigning Work
Assignment of a single work element to a single
team allows better control and Facilitates
rollup of efforts In both directions.
WBS
control account
ORGANIZATION
7
RAM The Cost Account Manager
  • Empowered by the
  • Management Team
  • Understand the baseline
  • Manage assigned effort
  • Technical
  • Schedule
  • Cost
  • Report monthly variance analysis

COST
SCHEDULE
TECHNICAL
CAM
COST ACCOUNT MANAGER (CAM)
8
Myth 4
  • I dont need a schedule, because I already know
    what needs to be done.
  • Maybe you do
  • However, you need the schedule to communicate to
    others what needs to be done
  • The team needs a vehicle to keep you informed of
    their plans

LESSON The schedule is a communication tool
9
Top Level Schedules
  • Work scope, ownership, interrelationships, time
    durations are all key data needed prior to
    schedule development
  • This is the time and place to document key
    program objectives, assumptions, groundrules, and
    constraints
  • This will be the vehicle for communicating to the
    program team members and other stakeholders
  • The top level plan must be developed by the CIPT
  • Collectively the team will provide information
    that you or other individual team members may
    miss
  • This also establishes ownership of the plans at
    an early stage
  • The top level plan should be developed down to
    the cost account level determined by the RAM

10
Top Level Schedules 5 Easy Steps
  • List Program Tasks
  • Brainstorming is a good method to generate this
    list
  • All schedules should follow the WBS
  • Note Updates to the WBS should be expected as a
    result of the scheduling process.
  • Start with major deliverables and key milestones
  • Sequence Tasks
  • This is simply putting the tasks in the order
    they will occur
  • Identify Relationships between tasks
  • This requires team members who are cognizant of
    the processes involved
  • Assign Durations to Tasks
  • Analyze plan against program objectives

11
Now that you have an overall plan,
  • It is time to flesh out the details
  • But how much detail?
  • Too much detail becomes unmanageable, and makes
    the plan difficult to use
  • But, if the plan has too little detail, it is
    difficult to anticipate the development of
    problems

12
Detail the Schedule
  • It is imperative that the team members who will
    do the work are involved in the detail planning
    phase to the extent possible. As with the top
    level planning,
  • This increases the probability of an accurate and
    complete plan
  • Engages team in the process early and increases
    ownership
  • FACT Planning/scheduling is an iterative
    process
  • Many iterations are normally made during the
    initial planning
  • Be sure to allow enough time, and do not rush the
    process
  • As new information arise, assumptions will change
  • This process is laying the groundwork for a solid
    program plan
  • Stimulates inter- and intra- team discussions
  • Surfaces risk areas
  • Identifies resource issues
  • Surfaces required inputs from others

13
Detail the Schedule
  • The initial organizing and planning done to this
    point (WBS, RAM, Top Level Schedule) is used as
    the guidance to initiate detail planning of the
    cost accounts
  • Each CAM must take this guidance (at the cost
    account level) and detail plan the work assigned
    to him/her.
  • Break down each cost account into work packages
    and tasks
  • Define duration and resources needed for
    completion of each task
  • Define completion criteria for each task
  • Define task interrelationships
  • Most difficult step
  • Where most plans fail to capture the reality of
    what needs to happen
  • Is the most common cause of a schedule that needs
    a miracle at the end to be successful during
    execution

14
Work Package Characteristics
  • Subset of cost account
  • Detailed plan made for near term work (work
    packages)
  • Future work is not detailed planned (planning
    packages)
  • Reasonably short in duration
  • Consistent with top level schedules
  • Discrete and Measurable
  • Exit criteria is a product, accomplishment or
    event
  • Generate drawing package
  • Conduct design review
  • Assemble power supply
  • Work packages must be 100 complete prior to
    closing the package

15
Developing Detail Plans 7 Easy Steps
  • List Program Tasks
  • Start with the Top Level Program Schedule
  • Identify the products from your cost account
  • Identify tasks required to develop the products
  • Identify all inputs needed to perform your work
    as a milestone
  • Sequence Tasks
  • Identify Relationships between tasks
  • Involve any team members who will be performing
    the required tasks
  • Assign Durations to Tasks
  • Assign Earned Value Method to Tasks
  • Assign Resources to Tasks
  • Populate the custom category fields attached to
    each task

16
Assigning Durations Earned Value
  • Tip Apply a single unit of duration throughout
    plan (i.e. weeks, days, hours)
  • Task durations should not exceed 6 weeks
  • Goal is to have tasks span no more than two
    fiscal months
  • Earned Value (EV) Techniques
  • Method How Value is Earned
  • 0/100 Zero EV at start, 100 EV finish
  • 50/50 50 EV at start, 50 EV at finish
  • Percent Complete Subjective
  • Level of Effort EV taken based on passing of
    time
  • Apportioned Based on progress of a related task

17
Assigning Resources
  • Applying resources to the planned work
  • Determine the type of resources needed for
    completing each task and how long each one is
    needed to complete the activities.
  • The duration of any activity is usually
    influenced by the amount of resources assigned to
    it and the duration of most programs is
    influenced by the quality of the resources
    assigned to them.

18
Defining Task Interrelationships
  • Remember that the devil is in the details?
  • This is the details
  • Knowing how tasks relate to each other is
    critical to a good plan
  • This knowledge must be resident within those
    planning the effort. The knowledge comes from
    experience, wisdom and careful consideration

19
Myth 5
  • I dont have to put that task on the schedule.
    It is inferred from the phase of the program that
    it occurs in.
  • Inference is based on your level of cognizance,
    at the present time. Others will be using the
    schedule to manage their work
  • Program team members change throughout the life
    of the program
  • All program efforts must be on the plan, at some
    level
  • If it is not on the schedule, it will likely be
    forgotten .until it is too late, causing
    regression

Truth The schedule should document the plan
20
Dos and Donts
  • Do identify any inputs that you require to
    perform your task as a milestone on you detail
    plan
  • Dont constrain start/finish dates of tasks
  • Dont link summary tasks
  • Dont use lead/lag as a substitute for thorough
    planning
  • Do ensure Task titles are descriptive
  • Do use a consistent unit for durations
  • Do start planning early.it is never too early
  • Do involve the team in the early development of
    the schedule

21
Schedule Analysis
  • What is schedule analysis?
  • Identifying the Critical Path
  • Forward and backward pass analysis
  • Identifying slack
  • Crashing the schedule

22
Analyze the Plan
  • It is important to analyze any plan to determine
  • The overall health of the plan
  • Level of detail
  • Proper scheduling techniques applied
  • Compliance with significant milestones
  • The viability of the plan
  • Amount of margin in the plan
  • Changes in the plan
  • Areas of the plan that require action
  • Current and potential problem areas
  • Progress against the plan
  • Schedule position

23
Myth 6
  • I do not need a schedule because I already know
    what the critical path is.
  • You may have a sense of what the critical path is
  • When you prepare a detail schedule, items that
    you did not expect or were not watching will
    surface on the critical path
  • Action must be taken to move these items off the
    CP
  • The individuals performing the work will plan for
    details that you may not be aware of

Truth The critical path must be managed, not
dictated
24
The Critical Path Definition
  • A set of activities which determine the earliest
    completion of the project, where any delay in any
    activity will delay the project by an equivalent
    amount
  • The path(s) in the task network with zero slack
  • The path with the longest duration through the
    network

25
Critical Path Exercise
  • Sum the times along each path in a network to
    determine the overall duration of each path.
  • The longest path in the network is the critical
    path.
  • The project cannot end before the critical path
    ends.
  • What is the critical path of the following
    network?
  • How long will this project take to complete?

Task G 6 days
Task C 3 days
Task A 3 days
Task D 7 days
Task H 1 day
Task F 5 days
Task E 4 days
Task B 2 days
26
Critical Path for an Entire Project
  • All tasks are compared to the latest task in the
    project. If a delay in a task would impact this
    date then the task is considered critical

Critical Path 0 7 5 4 0 16 days
27
Critical Path for multiple sets of tasks
  • Each chain of tasks calculates critical path
    separately within its own set of tasks. A
    critical path is calculated for each finish task
    within the project. A task is considered
    critical if it impacts the end of its network of
    tasks.
  • The example shows two chains of connected tasks
    within a single project, each calculating
    critical path from the finish tasks.

Critical Path 0 7 5 4 0 16
days Critical Path 0 6 9 15 days
28
Critical Path Analysis (CPA)
  • The Key Concept used by CPA is that a subset of
    project activities, which make up the longest
    path through the activity network, control the
    entire project
  • If these "critical" activities could be
    identified and assigned to responsible persons,
    management resources could be optimally used by
    concentrating on the few activities which
    determine the fate of the entire project
  • Non-critical activities can be replanned,
    rescheduled and resources for them can be
    reallocated flexibly, without affecting the whole
    project
  • There are three steps to performing Critical Path
    Analysis
  • Forward Pass
  • Backward Pass
  • Float Calculation

29
Forward Pass
  • The forward pass is calculation of the Earliest
    Start and Earliest Finish dates for each task in
    the network
  • Early Start Date the date at which the task's
    predecessors have all been completed
  • Early Finish Date the Early Start Date plus the
    task duration
  • A typical format of reflecting these dates in a
    network is

30
Forward Pass - Exercise
  • Start with the first task in the path and
    calculate the Early dates
  • Assume the project starts on Day 1 of the Project

ES
EF
ES
EF
Task G 6 days
Task C 3 days
ES
EF
Task A 3 days
ES
EF
ES
EF
Task H 1 days
Task D 7 days
ES
EF
Task F 5 days
ES
EF
ES
EF
Task B 2 days
Task E 4 days
31
Forward Pass - Exercise
  • Start with the first task in the path and
    calculate the Early dates
  • We will do the first two tasks together

Day 4
Day 6
ES
EF
Task G 6 days
Task C 3 days
Day 1
Day 3
Task A 3 days
ES
EF
ES
EF
Task H 1 days
Task D 7 days
ES
EF
Task F 5 days
ES
EF
ES
EF
Task B 2 days
Task E 4 days
32
Backward Pass
  • The backward pass is calculation of the Latest
    Start and Latest Finish dates for each task in
    the network
  • Late Start Date the date after which the task
    causes slippage of the project end date. It is
    determined by starting at the end of the project
    and working backwards
  • A typical format of reflecting these dates in a
    network is

33
Backward Pass - Exercise
  • Start with the last task in the path and
    calculate the Latest Dates
  • The Early Finish of the last task on the CP is
    equal to its Latest Finish

LS
LF
LS
LF
LS
LF
LS
LF
LS
LF
34
Backward Pass - Exercise
  • Start with the last task in the path and
    calculate the Latest Dates
  • We will do the first two tasks together

Day 7
Day 12
Task G 6 days
Day 10
Day 15
LS
LF
Day 16
Day 16
LS
LF
35
Forward and Backward Pass
  • Review the Critical Path
  • What do you Notice about the Early and Late Dates?

EARLY DATES LATE DATES on the CRITICAL PATH
36
What is slack?
  • The time between a tasks planned completion date
    and its need date
  • The time available to delay the completion of an
    activity without impacting the project end date
  • Useful to help to determine the impact of tasks
    slippage on the overall program schedule
  • Slack is used to prioritize tasks for resource
    allocation (the less slack, the higher the tasks
    priority because it is more critical)
  • The difference between a tasks Earliest dates
    and its Latest Start / Finish dates
  • Also referred to as Float

37
SLACK Calculation - Exercise
  • How much Slack (or Float) does each task have?
  • Slack LF - EF

38
SLACK Defined
  • TOTAL SLACK The amount of time that the finish
    date of a task can be delayed without delaying
    the finish date of the project
  • FREE SLACK The amount of time a task can be
    delayed before its successor task is delayed
  • Use the Free Slack to determine whether a task
    has any time available for a delay
  • Slack Values
  • By definition, a task with 0 slack is considered
    a critical task.  If a critical task is delayed,
    the project finish date is also delayed
  • A negative slack value indicates the amount of
    time that must be saved so that the project
    finish date is not delayed

39
SLACK Example
  • TOTAL SLACK The amount of time that the finish
    date of a task can be delayed without delaying
    the finish date of the project
  • Task I can be delayed 3 days before Task D is
    effected
  • FREE SLACK The amount of time a task can be
    delayed before its successor task is delayed
  • Task I can be delayed 2 days before Task L is
    effected

40
Crashing the schedule
  • Efforts to accelerate a project schedule are
    commonly grouped under the term "crashing" the
    schedule. Maybe this term was coined to suggest
    that there is always some price for driving a
    project to completion sooner than normal. There
    are a number of ways to improve the schedule
  • Add people to the schedule. Additional staff must
    be added early in a project or they will slow it
    down while learning the ropes. If you add people,
    you may also need to add staff for supervision
    and coordination
  • Improve productivity and work longer hours. A
    good team atmosphere with management support can
    help make this happen. Without positive
    nourishment of this process, you could lose your
    team to attrition
  • Review schedule dependencies and look for
    opportunities to overlap tasks or make serial
    tasks concurrent or parallel activities. This
    requires greater coordination and sometimes
    involves increased risks which need to be managed
    carefully
  • Review the project scope and remove or delay
    features or functionality from the project
    critical path
  • Consider innovative approaches such as a
    different development methodology, alternative
    technologies, or out-sourcing options
  • When Crashing a schedule, consider the cost of
    crashing, and balance time and cost to avoid
    waste of resources

41
Establishing the Baseline
  • Once the plan has been analyzed and adjusted to
    reflect program objectives, the next step is to
    Baseline it
  • Baselining captures a snapshot of the plan
    (schedule and budgets) at a point in time
    particularly at the launch of a program
  • The baseline is established in order to initiate
    the Control process
  • The baseline allows measurement of progress
    against and/or deviations from the original plan
  • This comparison is useful in the analysis of the
    overall project

42
In Summary
  • Planning is fundamental to program management
  • Planning should be initiated early in the program
    life cycle
  • Program Managers facilitate the planning effort
  • The Schedule Analyst will support the PM in this
    role
  • The plan should be developed by those who will
    execute the plan
  • The schedule is the tool to plan, manage and
    report all program data

43
Class 3 Assignment
Dont Worry About This
  • Answer questions 12-5, 12-6 and 12-13 through
    12-16
  • Due Monday
  • Use Microsoft Project to assist you in providing
    answers if you want (good practice to learn the
    software)
  • Read ahead paragraphs 15.4 15.5
Write a Comment
User Comments (0)
About PowerShow.com