Title: Presentation to the
1- Presentation to the
- Planning and Environment Committee
- RE Trail Road Landfill Leachate
- and Nepean Landfill
- Contaminated Groundwater
- Presented by the Public Liaison Committee
- November 23, 2004
- __________________________________________________
__________________________________________________
_______________________ - (Speaking Notes in yellow)
- Good Morning Chair Hume and Councillors.
- My name is Mary Elin Moore. I am a member of the
Public Liaison Committee and on behalf of the PLC
I am making this presentation to you. - The Public Liaison Committee was established by
the City under this EA process to ensure that the
public is properly informed and that their views
are properly reflected and taken into account in
the EA.
2Overview
- History of Trail Road, Nepean Landfill and
Leachate treatment - The PLC reminds this committee of the
extremely long history of this issue for City
officials and Councillors, as well as for the
public and stakeholders in South Nepean. - Facts on Leachate and Treatment Options
- The Pipeline and what it will mean to our
community - Why choose on-site treatment?
- Reasons why on-site treatment is the only
viable solution. - Results of Public Consultation and the views of
other Stakeholders - Concluding remarks
2
3Chronology
- 1995 - Trail Road Environmental Assessment
completed and approved by Regional Council - 1998/1999 - Proposed pipeline route through
Barrhaven following the CN tracks - 2000 - Regional Council approves pipeline route
- January 2003 - City proceeds with notification
of design and construction of pipeline - It is also important to note that over the
past decade, the City has always proposed
pipeline as the preferred method and has changed
the proposed pipeline route SEVERAL TIMES From
Barrhaven, to Cambrian West, to Golflinks and
most recently to Jockvale in March 2003.
3
4Chronology (contd)
- March 2003 Council directs staff to work with
Monarch Homes to modify the alignment of the
pipeline - July 2003 Council gives direction to staff to
re-open the EA after significant concern
expressed by the Stonebridge community - November 2003 Consultants and PLC begin work
- May 2004 VOCs added to the EA
4
5Quick Facts Did you know?
- The City spends 500,000 annually to transport 10
tanker trucks of leachate each working day to
ROPEC - due to this environmental issue not being
permanently addressed - EAs,studies, and public consultations between
1994 2004 on the issue have cost taxpayers
approximately 2.6 million - The City has spent 9 million buying up close to
400 acres of contaminated land around the Trail
Road Landfill facility
5
6Quick Facts Did you know?
- Stonebridge currently has 950 homes, to be built
out to 2600 homes by 2015 - In the next 15 to 20 years 40,000 new residential
dwellings will be built that would be affected by
the Jockvale pipeline route. - It is imperative that we come up with a solution
that also takes future residents into account.
6
7Implications of Pipeline
- Pipelines have an inherent risk of failure
- Digging and construction are major factors in the
disruption of electricity, water mains and sewer
mains. Slow leaks are virtually undetectable for
long periods of time and can only be reacted to
(it is nearly impossible to be proactive with
respect to a pipeline). - Pipelines do rupture. Proof of this, you will
see on Slide 8 which shows the Richmond
Forcemain pipe that burst On October 26, 2004,
the day of the Trail Road Open House, held by the
city ---to promote its choice of a leachate
forcemain as a safe alternative. -
- Property valuation
- The pipeline would also have a negative impact on
our property values - The costs to nearby landowners, farms, residents
and business have not been included in the
assessment of a pipeline. This can only adversely
affect the values. The City has never adequately
demonstrated to the citizens of Stonebridge that
a pipeline will not reduce their property values. - The definition of environment (according to the
Municipal Class EA) includes the social,
economic and cultural conditions that influence
the life of humans or a community. FURTHERMORE,
the Municipal Class EA Assessment guidance
document (June 2000) states Typical factors to
consider in conducting studies should include
change in property value as a recognized
potential factor.
7
8Implications of Pipeline
As well
- Transportation of Leachate and Contaminated
Groundwater by a pipeline route of more than 40Km
will indeed greatly increase the level of health
and safety risks as well as expand the geographic
area at risk. What will happen to residents if
their wells become contaminated due to gradual or
sudden pipeline failures? -
- Any time something is transported to another
area, the risk of something going wrong
increases. The risk is eliminated entirely with
on-site treatment. The area is contained and the
proposed on-site option would include holding
cells to account for unforeseen natural
occurrences such as the 100 year rainfall of
Sept 9, 2004. -
- There are also environmental and regulatory
issues. For example, there will still be a need
for pre-treatment in order to comply with the
Sewer Use Bylaw. How well will the water be
treated at ROPEC, the centre is designed for
sewage. What are the long-term effects of
removing this volume of water from the Jock River
watershed? -
7a
9Ruptured section of Richmond Forcemain (Oct 26/04)
Note that the longitudinal rupture occurred in
straight section of the pipe, a possible
indication that the forcemain is reaching the end
of its 20-year lifetime.
8
10Above photo shows ruptured pipeline.
Photo at top left shows Leachate dumping out of a
pipe.
Photo at immediate left shows a burst pipeline
under the road.
9
11Jock River in mid-August of 2001
a river already under severe stress
during dry summers. An eco-system
approach necessitates keeping water in the
watershed.
10
12 Implications of Pipeline
Therefore
- Pipelines have an inherent risk of failure
- Property valuation
- Transportation of Leachate and Contaminated
Groundwater raises the risk level, expands the
area of risk as well - Environmental Issues.
10a
13On-site ranking versus Pipeline
Now that weve outlined some of the risks
associated with the pipeline, we would like to
discuss the results of the EA.
2) The two options also scored the same for
groundwater resources which is odd given that
on-site treatment substantially improves the
groundwater Removing the water from the
watershed earns a 10 for the pipeline.
3) As well, both options scored the same for
surface water. This also seems inaccurate seeing
Environmental Responsibility
as on-site treatment significantly improves the
water quality, whereas a pipeline maintains the
same poor quality of untreated leachate. 4) In
terms of social impacts, no consideration of the
Social Impact
System Performance
Social Impact
Environmental Responsibility
Land Use
Land Use
You will see in this slide how closely the
on-site and pipeline options fared. The green
bars represent on-site and the purple represent
the pipeline option. The associated scores were
extremely close 9.3 for the pipeline vs. 8.99
for the on-site
System Performance
risk of pipeline rupture was factored into the EA
nor were property values.
Capital Cost
Capital Cost
5) In addition, the two options scored the same
for drinking water. However, if a pipe ruptures,
the groundwater and wells will become
contaminated. This is not the case for on-site
treatment.
a difference of only 0.3. That being said,
there are some issues of contention with the
ranking and evaluation criteria which the PLC
raised 1) For example, on-site and pipeline
scored the same for vegitation and wildlife even
though the on-site provides more benefits by
improving the landscape and adding a wetland (no
change for the pipeline).
11
14On-site ranking versus Pipeline Without Capital
Cost Differentiation
Social Impact
Environmental Responsibility
Social Impact
Environmental Responsibility
System Performance
System Performance
Land Use
Land Use
This graph shows that once upfront capital costs
are removed from the equation the two options
pipeline and on-site rank virtually the same.
12
15Why Choose On-site?
- The Triple Bottom-line
-
- The 2020 strategic plans are based on a
triple bottom line which balances economic
against social and environmental factors. As
such, it is important that we look at each of
these factors equally and NOT in isolation from
one another. - Economic
- Environmental
- Social
- Provide a safe, reliable, and efficient treatment
method at an asset shared by ALL citizens of
Ottawa - Cutting-edge technology
13
16Why Choose On-Site?
- The Triple Bottom-Line
- Economic
- First, there are Economic Factors Onsite
treatment, according to the EA, could cost 4.7M
more in capital than the pipeline over 60-years
(8.2 million vs. 3.8 million). While the
capital would be higher for onsite, we understand
that Budget 2005/06 can accommodate the majority
of these costs through an existing 3.1 million
pot remaining funds required in 2006. It may
also be possible for some of the 10 to 15M
surplus in 2005-06 for the Old Landfill
Management Strategy to accommodate some of these
additional costs. - According to the citys figures While
capital costs, at the front-end, would be more
for the on-site option, it is important to note
that ongoing operation and maintenance costs for
both options are practically the same. - We need to also factor in other financial
implications - For example timing delays would be inevitable if
a pipeline was chosen due to bump-ups to the
Minister of the Environment, OMB hearing(s), etc.
These delays would result in additional costs
for interim trucking which would put the costs of
the pipeline even higher. We have seen how it
has already cost the City 16M to date due to
delays over the past decade. - There would also be additional costs to the City
to pay MOE fines, pay for OMB hearings and legal
fees for City due to potential legal action by
developers and/or residents. -
13a
17Why Choose On-site?
- The Triple Bottom-line
-
- Economic
- Environmental
- There are several environmental
considerations that support on- site treatment. - With on-site treatment, there is a reduced risk
of contaminating further lands and zero water
exported out of the watershed. - There would also be high removal of effluent
quality and an opportunity to replenish the Jock
River (rehabilitate the water quality and
aqua-habitat). - We would be dealing with the problem in a
contained area while at the same time
replenishing the Jock River. - The potential to turn the contaminated land back
to agrable lands within 5-10 years for farming or
land-fill expansion. - Given that the City just approved a Master
Environmental Plan in its first term leads us to
believe that on-site treatment would be the
preferred choice. -
13b
18Why Choose On-site?
- The Triple Bottom-line
- Economic
- Environmental
- Social
- There are also social factors that need to be
considered. - First of all, on-site treatment is more safe,
reliable and efficient. It is more sensitive to
changes in leachate and contaminated groundwater
chemistry. - Secondly, pipeline construction would be
disruptive to Stonebridge and other residents,
farmers and businesses in South Nepean. - Thirdly, why should the residents of South Nepean
have to pay the health, safety and monetary costs
for everyone in the citys garbage! We need to
recognize that this is a City-wide issue. -
14
19Why Choose On-site?
To
review
- The Triple Bottom-line
- Economic
- Environmental
- Social
- Provide a safe, reliable, and efficient treatment
method at an asset shared by ALL citizens of
Ottawa - Cutting-edge technology
15
20Grassroots Support for On-site Treatment
- E-mail and Correspondence
- Recently, Councillor Harder, her colleagues, the
Mayor, community associations, PLC members, etc.
have been inundated with concerns from the public
who are voicing their strong views against a
pipeline. - Councillor Harder has received 155 e-mails, phone
calls, and faxes in just the past week or so. - Community Associations
- There are signed letter from several community
associations (Barrhaven, Orchard Estates,
Grenfell Glen, Fallowfield Village, and
Stonebridge) as well as from developers and
homebuilders all indicating their support for
on-site treatment. - Open Houses
- Over 250 people attended the October 2004 open
house with strong support for on-site treatment. - Petition / Poll results
- 412 people signed a Petition supporting on-site
and over 300 people completed our on-line poll,
with 94 of respondents indicating support for
on-site treatment - Todays presenters
Here to lend their democratic voice
in support of the right solution.
16
21Conclusion - Weighing the Costs
- Financial implications
- Environmental implications
- Ive already touched on the financial and
environmental implications but I would like to
comment on community mobilization. - Community mobilization
- We need to put an end to this 10-year
community controversy. The history attached to
it makes it unique from other leachate issues
across the City. -
- The Barrhaven community has been galvanized since
1998 and will continue to fight any pipeline.
Stonebridge residents feel that adequate public
consultation was not done initially and now it is
the appropriate time to rectify past wrongs and
plan appropriately for the future. - Council has already said no to a pipeline going
through Barrhaven and going down Golflinks and
down Jockvale. Why would it now support a
pipeline running down Jockvale? Why would
Council listen to citizens along previously
proposed pipeline routes but not for this one?
Shouldnt all citizens be treated equally and
listened to equally? -
- Now is the perfect opportunity to take advantage
of onsite technology and to be a an environmental
steward and leader while at the same time
respecting the wishes of the citizens of south
Nepean a win-win situation for everyone. - Thank you.
17
22- Presentation to the
- Planning and Environment Committee
- RE Trail Road Landfill Leachate
- and Nepean Landfill
- Contaminated Groundwater
- Presented by the Public Liaison Committee
- November 23, 2004
- End