Finn Addict Website Development Project Report - PowerPoint PPT Presentation

1 / 10
About This Presentation
Title:

Finn Addict Website Development Project Report

Description:

The Finn Addict website has all ready brought in business via the online form!! The Finn Addict website has greatly increased the opportunity for growth. ... – PowerPoint PPT presentation

Number of Views:58
Avg rating:3.0/5.0
Slides: 11
Provided by: webpages2
Category:

less

Transcript and Presenter's Notes

Title: Finn Addict Website Development Project Report


1
Finn Addict Website DevelopmentProject Report
Prepared by Robin Moore
2
Introduction
  • Project Objective
  • Create an appealing user friendly website that
    accurately portrays Finn Addict Charter Service
    and effectively markets its service.
  • Project Results
  • An expandable user-friendly website that displays
    extensive company information, opens
    communication lines and increases business
    opportunities by implementing online reservation.

3
Project Overview
  • Project Duration
  • September 27, 2005 to December 9, 2005
  • Team Members
  • Robin Moore Project Manager, Analyst Trainer
  • Phil Nelson Website Developer and Trainer
  • Shane Uecker Analyst

4
Project Performance MeasurementsEarned Value
Analysis
  • Project scheduled for 12 week period
  • Budget at completion based on forty hours of work
    for project manager, developer and analysts
    (current average salaries for similar IT
    positions) plus 300.00 domain/web-space package
  • Project finished on time and under budget

5
Project Performance Measurements Variance
Analysis
  • Week 2 shows negative variance analysis ? High
    probability of finishing over budget and behind
    schedule
  • After Week 3 variance analysis is positive ? High
    probability of finishing under budget and good
    chance of finishing on-time

6
Project Performance Measurements Performance Index
  • The efficiency of the CPI is above 1 for majority
    of project ?Under Budget.
  • The efficiency of the SPI is slightly under 1 for
    a majority of the project ? Behind Schedule
  • The efficiency of the SPI at week 12 is 1 ?
    Finished On-Time

7
Project Performance Measurements Estimate at
Completion
  • EAC exceeds BAC on week 2 ? High probability of
    project finishing over budget
  • EAC is less than BAC after week 3?High
    probability of project finishing under budget

8
Project Budget, Schedule, Scope
  • Labor 70 under budget
  • Materials 53 under budget

Project scope was achieved, Project deemed a
success!!
  • Project finished on-time

9
Project /Team Assessment
10
Project Acceptance