Title: Template
1BNL - FNAL - LBNL - SLAC
LARP Model Magnet RD DOE Review of the LHC
Accelerator Research Program June 1-2,
2005 Gian Luca Sabbi
2Model Magnet RD Guidance
- Programmatic issues
- Approach as RD program, not as a construction
project (DOE) - Investigate Nb3Sn technology options for IR
upgrades (DOE) - Concentrate on quadrupole magnets first (CERN,
LAPAC) - Down-select options prior to experimental
investigation (LAPAC) - Collaboration issues
- Coordinate program and effort across
laboratories (DOE, LAPAC) - Compare technologies, develop common procedures
(LAPAC) - Technical objectives
- Investigate performance limits, as input for IR
design (DOE, CERN) - Demonstrate long Nb3Sn magnets as soon as
feasible (CERN, LAPAC)
3Magnet Program Goals
Overall goal Provide options for future
upgrades of the LHC Interaction Regions
FY09 Milestone Demonstrate viability of
Nb3Sn technology for Quad-first option
1. Capability to deliver predictable,
reproducible performance TQ (Technology
Quads) D 90 mm, L 1 m, Gnom gt 200 T/m 2.
Capability to scale-up the magnet length
LQ (Long Quads) D 90 mm, L 4 m, Gnom gt 200
T/m 3. Capability to reach high gradients in
large apertures HQ (High Gradient Quads) D
90 mm, L 1 m, Gnom gt 250 T/m
4Program Plan FY05-FY09
5Technology Quads Features and Goals
- Objective develop the technology base for LQ and
HQ - evaluate conductor and cable performance
stability, stress limits - develop and select coil fabrication procedures
- select the mechanical design concept and support
structure - demonstrate predictable and reproducible
performance - Implementation two series, same coil design,
different structures - TQS models shell-based structure
- TQC models collar-based structure
- Magnet parameters
- 1 m length, 90 mm aperture, 11-13 T coil peak
field - Nominal gradient 200 T/m maximum gradient
215-265 T/m
6TQS01 TQC01 Conductor Coil
- Strand
- OST-MJR, 0.7 mm diameter
- Jc 2 kA/mm2 (12 T, 4.2 K)
- Is gt 1 kA w/optimized HT
- Cable
- 27-strand, 10.05 mm width
- Mid-thickness 1.26 mm
- Keystone angle 1.0 deg
- Insulation S-2 glass sleeve
- Coil
- double-layer, shell-type
- one wedge/octant (inner layer)
- MJR strand
- same strand for both models
- 70 kg borrowed from FNAL
- replacement order in FY06
Coil cross-section
Coil end (inner layer)
7TQS models Shell-based Structure
- Concept
- Aluminum shell over iron yoke
- Assembly w/hydraulic bladders
- Advantages
- Can deliver high pre-stress
- Pre-stress increases at cool-down
- Easy disassembly/reassembly
- Issues
- Coil alignment (RD w/SQ series)
- Length scaling (RD w/LR series)
Shell transverse strain vs key interference
8TQC models Collar-based Structure
- Concept
- Support by thick SS collars
- Assembly w/external press
- Advantages
- Proven coil positioning
- Proven length scale-up
- Issues
- Maximum pre-stress delivered
- Pre-stress overshoot at assembly
- Flexibility for RD
- Modified MQXB (LHC IR quad) collar blocks
- Outer-layer poles provided by the collars
- Inner-layer poles are glued into the coil
- Pole spacers for alignment and yoke gap control
- Mid-plane shim to control coil-yoke interference
9Short Sample Parameters
MJR strand Jc 2 kA/mm2 (12 T, 4.2 K) 48 Cu
RRP strand Jc 3 kA/mm2 (12 T, 4.2 K) 50 Cu
Gradient range 215-265 T/m depending on
conductor and operating temperature
10FY05 Progress on TQS01 TQC01
- Finalized cable and coil design 2D 3D
magnetic analysis completed - Completed coil parts design procurements are in
progress - Completed winding tooling design and procurement
- Completed structure designs, procurements are in
progress - Reaction/potting tooling 2 sets needed for
schedule 1 procured, 1 in order - Finalized inter-lab coil fabrication plan and
agreed on procedures - Fabricated cable for practice coils finalized
strand map for production cable - Winding of first practice coil has started, with
good results
Practice coil winding
Coil curing cavity
Winding tooling
11TQS01 TQC01 Schedule
Q3 2005 Q4 2005 Q1 2006 Q2 2006
Practice coils mech. models
TQS01 Fab/Test
TQC01 Fab/Test
Spare coils
12TQS01-TQC01 Sub-tasks Cost
FNAL
LBNL
BNL
FY04 FY05 FY06
FY04 FY05 FY06
FY05 FY06
- Coil design
- Tooling parts
- Coil winding/curing
- 0.67 M
- Coil design
- Tooling parts
- Coil reaction/potting
- 0.46 M
Shared TQ1a/2a 1.14 M
Test setup 0.01 M
- TQS01 design
- TQS01 structure
- TQS01 assembly
- 0.46 M
TQ1a Specific 0.53 M
TQS01 test 0.06 M
- TQC01 design
- TQC01 structure
- TQC01 test
- 0.48 M
Conductor and cabling cost are not
included! (covered by Materials)
TQ2a Specific 0.48 M
13TQ program following TQS01/TQC01
- 1. Additional tests using the same coil design
- TQS02 reconfigure/optimize based on TQS01
results - Increase preload? (e.g. 4.2 K to 1.9 K) Modify
structure? (as for HD1) - Replace quadrant with spare? (if localized
quenches observed) - TQC02 new coils (w/RRP conductor) in
collar-based structure - Feedback from TQC01 can be incorporated at
assembly - Coils might be redirected to TQS depending on
test results - TQE01 coil-structure exchange
- Disassemble TQC01 coil and test in TQS01
structure - Some technical issues to be addressed decision
after TQS01/TQC01 tests - 2. Coil iteration and fabrication of TQS03
TQC03 coils
14TQ schedule following TQS01 and TQC01
Q1-06 Q2-06 Q3-06 Q4-06
Q1-07
TQS02
TQC02
TQE01
Coil iteration practice coil
TQS03 TQC03 Coils
15Coil Design Iteration
- Depending on test results, changes may be
implemented - Adjust cable parameters (new conductor etc.)
- Increase keystone angle (better radial
positioning) - Redesign or eliminate wedge
- Modify end design (magnetic, mechanical)
- Modify insulation scheme (reliability, cost,
length scale-up) - Several factors need to be taken into account
- Performance issues and optimization
- Reproducibility goal
- Length scale-up goal
16Mechanical Support
- The design selection requires addressing a
complex set of issues - Pre-load targets to achieve design performance
w/minimum training - Maximum allowed stress in the coils
- Trade-offs between stresses in the coil and
structure - End support, axial pre-load requirements
- Field/gradient/aperture scale-up
- Maximum pre-stress delivered (collar-based
structure) - Length scale-up and alignment (shell-based
structure) - A combined effort of the magnet program is
required - Design studies (analysis and comparisons of
different approaches) - Supporting RD (simplified tests using SQ and
LR) - Model magnet RD (full scale testing and
validation)
17FY08-09 Long Quads (LQ)
- RD issues
- long cable fabrication and insulation
- stress control during coil reaction, cable
treatment, pole design - coil impregnation procedure, handling of reacted
coils - support structures, assembly issues
- reliability of design and fabrication
Plan scale-up the TQ design to 4 meter length
(LQ)
- FY06 fundamental scale-up issues addressed by
Supporting RD - general infrastructure and tooling
- long racetrack coil fabrication and test
- scale-up and alignment issues for shell-based
structure
18FY08-09 High-gradient Quads (HQ)
3-layer G260-290 T/m
4-layer G280-310 T/m
FY06 conceptual design studies (DS),
conductor/cable RD (MAT)
19FY06 Tasks and Budget
20Summary
- The RD plan being developed is consistent with
LARP guidance - All three labs provide contributions
- TQ models will test coil fabrication and
mechanical issues - Moving forward with first two quads TQS01 and
TQC01 - Converged on the same coil design for both
models - Converged on fabrication procedures and plan
- Winding of practice coil has started
Rate of progress and successful completion of
TQS01 and TQC01 are essential benchmarks towards
meeting the FY09 milestone