Operations MOC - PowerPoint PPT Presentation

1 / 82
About This Presentation
Title:

Operations MOC

Description:

Readiness and Residual Risks: Redbook Candidates. Special Topics. MOC ... How Ops Plans to Avoid Instr Overheating Bruce Trout. Operator Training Joe Howard ... – PowerPoint PPT presentation

Number of Views:728
Avg rating:3.0/5.0
Slides: 83
Provided by: danm2
Category:

less

Transcript and Presenter's Notes

Title: Operations MOC


1
Section 33 Operations / MOC
. . . Dan Mandl EO-1 Operations Manager
2
Contents
  • Overview of Operations Dan Mandl
  • Testing and Verification Status
  • MOC H/W Status
  • MOC Procedure Status
  • Launch Overview
  • Documentation
  • Configuration Management
  • SOMO Institutional Mission Operations Support
  • RFA Status from Previous Reviews
  • Readiness and Residual Risks Redbook Candidates
  • Special Topics
  • MOC Simulations Gus Gustafson
  • Contingency Operations Pete Spidaliere
  • Ampex Recorders
    Dan Mandl
  • How Ops Plans to Avoid Instr Overheating
    Bruce Trout
  • Operator Training
    Joe Howard
  • Operator Staffing Versus Functions-Overloaded?
    Joe Howard
  • Planned Cooperation with Landsat
    Bob DeFazio

3
Operational Philosophy
  • 1 year mission
  • During Normal Ops
  • 3-8 passes/day (2 for science dumps)
  • During LEO
  • 14 passes/day (2 for science dumps) during first
    week
  • 8 passes/day (2 for science dumps) from L8 to
    L60
  • 80 Gb of data max (typ 2 DCEs) from instruments
    per day
  • Staffing
  • 24 hr x 7 day staffing for operations during
    first 60 days
  • Phase down to 8hr x 5 day after L60 contingent
    on review at L30
  • After phase down, use automation for non-manned
    hours
  • Weekends and evenings

Ops Overview
4
Operations Overview
Ops Overview
5
Operational Phases
  • Launch Early Orbit
  • Launch and the first several orbits, spacecraft
    checkout, and instrument turn-ons
  • Approximately 15 days (20 days to get to 1 min
    behind Landsat)
  • 1 minute behind Landsat 7
  • Instrument Checkout
  • Full instrument checkout
  • Approximately 45 days
  • Nominal Ops
  • Science Validation
  • 10 months
  • End of Life
  • Deorbit burn for reentry within 25 years

Ops Overview
6
Ground System Requirements Summary
  • Ground stations to receive, process, and route
    science and housekeeping data to GSFC
  • X-band
  • Receive up to 80 Gbits of science data each day
    at 105 Mb/s
  • Record the received X band data on hard media,
    mail to GSFC, and store raw data for 30 days
  • S-band
  • Receive data at selected rates up to 2 Mb/s
  • Housekeeping data
  • Route selected virtual channels to GSFC in real
    time
  • Record up to 200 Mbits of data each day
  • FTP recorded data to EO-1 MOC within two hours
  • Store raw data for 30 days
  • Backup science data (up to 5 Gbits per day)
    Process as with X band

Ops Overview
7
Ground System Requirements Summary
  • Process Hyperion, MS/PAN, AC science data to
    provide at least 200 paired scene comparisons
    with Landsat 7
  • 55 scenes for ALI, AC during 60 day checkout
  • 55 Hyperion, AC scenes
  • 1000 scenes total first year
  • Maintain an orbit of sufficient precision for
    scene comparisons
  • Follow Landsat 7 Ground Track
  • /- 3 km cross track
  • 1 minute behind /- 6 seconds
  • 1 minute later than Landsat in mean local time at
    the descending node

Ops Overview
8
Ground System Requirements Summary
  • Maintain the health and safety of the spacecraft
    and instruments
  • Validate and calibrate on-board orbit and
    attitude subsystems
  • Perform orbit maneuver control to enable
    formation flying
  • Provide mission planning and command management
    for
  • Image operations
  • Other technology validation operations
  • Calibration operations
  • Contingency operations
  • Archive raw and processed data

Ops Overview
9
Verification Approach
  • Verified against
  • EO-1 Ground Functional and Performance
    Requirements
  • Detailed Mission Requirements (SOMO services)
  • System testing done by the developers of each
    subsystem
  • Acceptance testing and Mission Readiness Testing
    done by the FOT to verify each subsystems
    requirements and end-to-end performance of ground
    components
  • Simulations performed by FOT, Instrumenters, and
    S/C subsystem engineers for final end-to-end
    check of teams ability to perform required tasks
  • Post-Launch Verification of new releases of
    ground S/W
  • Regression testing by means of shadowing
    operations and comparing results with previous
    version

Testing Verification
10
EO-1 Operations Testing Status
S Acceptance Testing T Mission Readiness
Test M Simulation
Testing Verification
11
(No Transcript)
12
Requirements Verification
  • 94 of the requirements verified
  • Unverified requirements
  • 7 Instrumenter requirements not verifiable before
    launch because involve providing LEO support
  • SVF shall receive DCE and calibration requests
    from Science Validation Team
  • SVF shall perform Level 1 processing of AC data
    after receipt of code from AC Instrumenters
  • Interface with FDF algorithms to schedule
    activities/commands for momentum management
  • Mostly tested, waiting for delivery by 4/15/00 of
    enhancement to complete verification

Testing Verification
13
Requirements Verification
  • Unverified requirements (continued)
  • 4 GN requirements only testable post launch,
    involves performance of personnel at ground
    stations
  • 2 CGS requirements involve testing capability of
    SERS to page FOT member
  • Capability in process of testing

Testing Verification
14
Ground Discrepancy Reports (DR) Status as of
3-16-00 Critical DRs
  • DR 58-FDSS Add Solar Array modeling to
    computation of reaction wheel speeds
  • Fix in testing, complete by 4/15/00
  • DR 150-Networks During simulation, lost socket
    connection to STGT for commanding
  • Under investigation

Testing Verification
15
Ground DR Status as of 3-16-00 Urgent DRs
  • DR 16-ASIST Capability to change limits from
    database lookup window
  • Under investigation
  • DR 18 67-ASIST Slow playback
  • Fix being developed, complete 4/30/00
  • DR 163-ASIST SOH HDF files have error
  • Fix in process for patch to be delivered by
    4/30/00
  • DR 10-DHDS Playback cant be automated
  • Same fix as DR 18 and DR 67
  • DR 82-FEDS Translator needed for VC4
  • In process of being developed. Date of delivery
    TBD
  • DR 114-FEDS Command interface problem with SN.
    Statistics wrong
  • Under investigation
  • DR 164-Ground During Time correlation test, PTP
    offset time by 300 msec
  • Under retest by 3/21/00
  • DR 55-MOPSS MOPSS needs fail-over capability
  • In process of configuring dual workstation
    fail-over mode. Almost complete
  • DR 169-MOPSS Problem with command DB ingest
  • Problem fixed, waiting for retest
  • DR 79-Net Ampex recorder at Wallops broken

Testing Verification
16
Ground DR Status as of 3-16-00 Urgent DRs
(continued)
  • DR 151-Net ATS load configured S/C for 2K
    coherent.
  • Under investigation
  • DR 71-OPS Need to build ground station summary
    report
  • Action assigned to FOT
  • DR 84-Ops WARP directory needs to be a flat
    file
  • Action assigned to FOT
  • DR 107-Ops Monitor was unreadable
  • Action assigned to Jim Weidman, system admin.
  • DR 111-Ops Command to SCP rejected
  • Under investigation
  • DR 115-Ops When command TDRSS 4k downlink, page
    shows error. Possible RDL problem
  • Under investigation
  • DR 109-S/C During sim, TSMs 53, 63, 71, 72 and
    73 failed
  • Submit as S/C PR
  • DR 119-S/C During sim, unable to go backward in
    time
  • Under investigation by K. Blackman
  • DR 120-S/C During sim, no command link.
    Problem in IT
  • Assigned to IT
  • DR 166-S/C Limits need to be changed for new
    command DB for MOPSS

Testing Verification
17
S/C to MOC Testing(1 of 2)
Testing Verification
18
S/C to MOC Testing(2 of 2)
P - Planned
Testing Verification
19
Simulations
  • Typical content of Launch and Day 2 simulation
    and contingencies are discussed in the MOC Sim
    special topic

Testing Verification
20
EO-1 Data Link Configuration for Testing and LEO
21
EO-1 Data Link Configuration for Normal Ops
22
MOC Hardware Status
  • All MOC hardware in place except the following
  • Trending system waiting for delivery of PC
  • Using temporary PC in the meantime
  • MOC firewall
  • Have in house, but waiting for NISN approval of
    revised Security Plan
  • Will be installed during 4/00

Hardware Status
23
MOC Procedure Status
  • Regular Procedures tested
  • ACS 66/66
  • PSE 13/13
  • RCS 2/2
  • GPS 8/11
  • LFSA 2/2
  • MV 7/8
  • WARP 14/32
  • Combined Inst 17/17
  • AC 11/11
  • ALI 25/35
  • Hyperion 32/43
  • COM/CDH 5/9
  • RF 4/9
  • Timecode 3/3
  • Ground 6/6
  • ATS 9/9
  • Recorder 3/5
  • Total 233/284 82

MOC Procedure Status
24
Launch
  • Launch Vehicle
  • Launched from WTR on a Delta 7320
  • Co-manifested with the Argentine SAC-C
    spacecraft. EO-1 separates first.
  • Launch Window
  • EO-1 has an instantaneous launch window with a
    30 second allowance for collision avoidance.
    The window occurs once per day at about 1826
    GMT.
  • Formation flying with Landsat 7
  • To enable EO-1 to co-fly with Landsat 7, it is
    necessary to place EO-1 one minute (/-6 sec)
    behind Landsat 7 and within 3 km crosstrack.
  • The launch vehicle injection point is near the
    start of first ascending node. The Local time
    will be 2204.
  • Depending on the performance of the Launch
    Vehicle, between 6 and 8 maneuvers will be
    required to position EO-1 behind L7.
  • Final Orbit
  • 705 km, circular, sun-synchronous, inclination of
    98.2 degrees

Launch Overview
25
Space Network Ground Network Coverage
  • Space Network
  • Use of TDRS is planned for powered flight and the
    first few orbits after separation and later
    during initial maneuvers
  • Ground Network
  • Norway
  • Alaska
  • Wallops
  • McMurdo

Launch Overview
26
Launch Day Orbit Ground Trace
Launch Overview
27
Highlights of LEO
  • Day 1
  • Launch, Launch vehicle separation, SA deployment
  • B-dot and sun acquisition
  • Turn on IRU heaters, Star Tracker, GPS, and ALI
    outgas heaters
  • Initialize Kalman Filter
  • Day 2
  • Begin use of Kalman Filter
  • Begin use of GPS for time
  • Test Safehold Logic
  • Go to Earth Pointing
  • Day 3
  • Pitch Slew for IMU calibration
  • Yaw Slew for IMU calibration
  • Roll Slew for IMU calibration
  • Reengineering Thruster Burn
  • Day 4
  • Enable Enhanced Formation Flying Software in
    monitor mode
  • WARP checkout
  • X-band Phased Array on and dump of WARP test
    pattern

Launch Overview
28
Highlights of LEO
  • Day 5
  • ALI turn on and initial check out
  • Inclination burn
  • Day 6
  • Begin Hyperion turn on and initial checkout (done
    over 3 days)
  • Turn on and checkout Atmospheric Corrector (done
    over parts of 2 days)
  • Day 7
  • Continue Hyperion and AC checkout
  • Day 8
  • Continue Hyperion Checkout
  • Perform all instrument data collection event
  • Day 9
  • Rest Day (contingency)
  • Day 10
  • Safehold test
  • S/C recovery from safehold
  • Day 11
  • Instrument recovery from safehold
  • Activity plan lays out the detailed plan for the
    first 11 days

Launch Overview
29
LEO Organization
Launch Overview
30
Documentation Philosophy
  • All required documents to operate the S/C are on
    the EO-1 website
  • Copies of required documents will be at the
    console during operations
  • Mission Operations Manager and FOT Lead will be
    responsible for a Controlled Document List and
    will assure that all printed documents are in
    concurrence with the this list
  • Gabrielle Araiza is librarian to assure that
    documents in MOC library are up to date

Documentation
31
Key Documents for Operations
Documentation
32
Key Documents for Operations
Documentation
33
S/C Users Guide Status
  • Completion of S/C Users Guide scheduled for 6/00
    after all training is done and the feedback
    folded into the Users Guide

Documentation
34
Mission Procedures Document
  • Mission Procedures Document (MPD) on EO-1 website
  • MPD Vol 1 is the Ops Concepts
  • MPD Vol 2, Detailed Ops Plans
  • Launch Early Orbit (LEO)
  • Pre-Launch Script (in process of being created)
  • Launch Script (baselined)
  • Instrument Checkout Scrip(baselined)
  • LEO Specific Procedure
  • Normal
  • Normal operations procedures
  • Contingency procedures (flowcharts and scripts)
  • General
  • Telemetry and Statistics Monitors (baselined)
  • FDCs (baselined)
  • Relative Time Sequences (baselined)
  • List of pages
  • List of S/C Event messages
  • Problem escalation procedures
  • CM Plan for Procs, Pages, Documents and S/W

Documentation
35
Configuration Management
  • Documents are on EO-1 CM website
  • http//eo1.gsfc.nasa.gov (select configuration
    management)
  • ISO Compliant
  • Procedures
  • Tested
  • Placed global procedure directory
  • Write privileges only by sys admin
  • Changed via Operations Change Request
  • Database Pages
  • All pages inherited from IT
  • Build latest version and placed in configured
    directory
  • Only DB administrator can access
  • Temporary changes placed in global directory by
    any FOT member
  • Changes via DB change request forms

Configuration Management
36
SOMO Institutional Mission Operations
  • FOT and sustaining engineering under a CSOC SODA
  • Ground station and Space Network support under
    CSOC
  • Requirements driven by Detailed Mission
    Requirements(DMR) Mission Operations Support
    Plan(MOSP)

SOMO Institutional Support
37
RFA Status
  • 23 RFAs were assigned from the original MOR and
    are closed
  • 20 RFAs were assigned from the Delta MOR
  • 19 are closed
  • 1 response was submitted and still under review
  • 14 RFAs were assigned from the FOR
  • 10 closed
  • 5 responses resubmitted and still under review

RFA Status
38
Critical RFA Status
RFA Status
39
Critical PR
  • Critical PR 675-20-2, 829-30-2 and 829-30-3 are
    being held open
  • S/C side is okay
  • Ground has some residual problem on the PTP front
    end at the ground stations
  • As a result recent tests stay marginally within
    specs for time correlation operations activities
  • PTP problems presently under investigation

RFA Status
40
Readiness and Residual Risks Redbook Candidates
  • No significant residual risk
  • WARP repair provides additional simulation and
    training opportunities
  • No Redbook candidates
  • Operations is on schedule to support the launch


41
Special Topic MOC Simulations
. . . Gus Gustafson EO-1 Simulation Manager
42
Simulation Summary
  • Sim 1 Normal operations during Thermal/Vac
    10/10,13,16/99
  • Primary ATS loads exercising the instruments in
    routine operational modes
  • All three instruments exercised
  • 3 separate days of operating were conducted (16
    hours ea.) including X-band dumps and data
    processing activities
  • Exercised the MOPSS
  • Ground stations not involved
  • Sim 2 Launch simulation days 1, 2 and 3 (no
    contingencies)
  • 10/28/99, day 1 Prelaunch and launch activities
    through 5 orbits resulting in S/C having achieved
    sum acquisition and being power positive
  • Included Star Tracker and GPS turn on

43
Simulation Summary
  • Sim 2 Day 2 10/29/99
  • Real world orbits 12 through 42, activities
    compressed into 7 orbits
  • Energized slewing to Earth pointing
  • One of three Gyro calibration slews
  • Delta V thruster burn
  • Sim 2 Day 3 11/3/99
  • Real world orbit 44 through 103, activities time
    compressed into 12 hours
  • Included WARP and instrument turn-ons as scripted
  • S-band and X-Band downlinks exercised
  • Data processing activities conducted
  • Ground stations not involved, however used TDRSS
    support during Day 1
  • 2 unplanned contingencies

44
Simulation Summary
  • Sim 3 Launch simulation with contingencies
    (Days 1 2) 12/13 14/99
  • Same scripting as Sim 2 but with contingencies
  • 6 planned contingencies, 1 unplanned
  • Sim 4 science end-to-end simulation, Day 23
  • Included ground stations (SGS, AGS and WGS)
  • No S/C interface
  • Verified command and telemetry interfaces from
    MOC to all three stations
  • Verified the science planning interfaces
  • Stations provided
  • Tracking data files
  • Station status messages
  • Standard Autonomous File Server (SAFS) data
  • Post pass summaries

45
Simulation Summary
  • Sim 4 science end-to-end simulation, Day 23
  • Exercised the Data Processing System for S-band
    and X-band data processing, including
    distribution of data products
  • Exercised data links to TRW and MIT/LL for
    realtime and playback data
  • Exercised the Data Quality Monitor system at WGS
  • Provided tapes to the Science Validation Facility
  • Exercised MOC trending capability
  • Sim 5 Repeat of science end-to-end 1/4/00
  • Sim 6 Launch simulation with contingencies (Day
    1 only) 1/14/00
  • 4 planned contingencies
  • Sim 7 Launch simulation with contingencies
    (Days 1 2) 1/2428/00
  • 13 planned contingencies and 2 unplanned

46
Simulation Summary
  • Sim 8 Repeat of science end-to-end 2/2/00
  • Sim 9 Mini-Sim exercising safehold and safehold
    recovery 2/4/00
  • Sim 10 Mini-sim exercising a thruster burn
    2/16/00
  • Sim 11 Launch sim with contingencies (Day 1
    2) 2/1718/00
  • 15 planned contingencies
  • Sim 12 Repeat of the science end-to-end
    simulation 2/23/00
  • Sim 13 Simulation of the S/C tumbling post
    separation 3/9/00
  • Sim 14 Launch sim with contingencies
  • 4 planned and 1 green card

47
Subsystems Exercised with Contingencies
Planned 43 Unplanned 5 Total 48 Note
Since a given contingency may affect more than
one subsystem, this explains the difference
between the number of contingencies totaled in
the line above and the number of total number
from the right most column of the chart.
48
Special Topic MOC Contingency Operations Plans
. . . Pete Spidaliere EO-1 Mission Systems
Engineer
49
Contingency Procedures
  • Anomalies are dealt with through the following
  • On-board Telemetry and Statistics Monitors that
    sense an anomalous condition and either warn the
    Ground through an Event Message or initiate a
    Relative Time Sequence to safe the instruments
    and/or spacecraft. These are system level
    protections.
  • Box or Instrument level Failure Detection and
    Correction software that, like the system level
    protection, sense and initiate safing events.
  • Ground-based contingency procedures that are used
    to determine an unsafe condition exists and what
    steps should be taken to return to a safe
    condition.
  • Required and highly desired contingency
    procedures have been identified and developed by
    the Systems, Subsystem, Instrument, and Flight
    Ops teams.
  • Testing of approximately 60 of the procedures
    has occurred and the remainder will be tested
    before shipment.
  • All simulations, except the first, have contain
    anomalies. This allows for training the team on
    how to use the procedures.

50
Contingency Procedures
  • Procedures exist in the form of STOL Procs and
    Decision Trees.
  • All STOL Procs will be tested before use.
  • Decision Trees will, by their nature, be verified
    by review.
  • Most of the STOL Procs have been developed and
    tested. The Flight Software Team has been
    occupied with other high priority tasks, but is
    now free to aid in the development of CDH STOL
    Contingency Procs.
  • Many of the Decision Trees have been developed
    and reviewed. Several have been tested during
    Simulations, and the need for others has been
    determined during the Simulations. None can be
    considered final at this time, but most are quite
    mature and have been through a round of Systems
    Level review.

51
STOL Contingency Procedures
52
STOL Contingency Procedures (continued)
53
STOL Contingency Procedures (continued)
54
Decision Trees
  • LV Separation Anomaly
  • SA Fails to Deploy
  • Communications Anomalies
  • No Telemetry
  • No Commanding
  • TDRS Telemetry/Commanding anomaly
  • MOC Misconfiguration
  • Ground Station Loss of Comm
  • NISN Contingency
  • Power Anomalies
  • Half Battery Voltage Differential
  • Battery Temperature
  • Battery Undervoltage
  • Battery Overvoltage

55
Decision Trees
  • ACS
  • BDOT System Momentum Not Decreasing
  • Tip-Off rates higher than worst case
  • Phasing error
  • SA Drive Not Driving to Zero Degrees (early
    orbit)
  • Sun Acquisition Mode Anomaly
  • Residual magnetic dipole higher than expected
  • Phasing error
  • AST Failure
  • MTR Failure
  • TAM Failure
  • IRU Failure
  • RWA Failure
  • XPAA Pointing Anomaly

56
Critical PRs and RFAsAddressed in This Section
  • RFA 18.15 Status and Verification of
    Contingency Procedures
  • PR 675-20-4 Red High Limit on Atmospheric
    Corrector Power Supply Card

57
Special Topic Ampex Recorders
. . . Dan Mandl EO-1 Ground Systems Manager
58
Ampex Recorder Status
  • Ampex tape recorders (Special Topic)
  • Reliability of Ampex tape recorders at ground
    stations in question at FOR
  • Developed Ops procedure whereby during initial 30
    days when tape is recorded, tape is played back
    through DQM before shipping to MOC to verify good
    data on tape
  • All Ampex tape units fixed at ground station and
    are operational at present time

59
Special Topic How Operations Plans to Avoid
Instrument Overheating
. . . Bruce Trout EO-1 Mission Planner/FOT
60
On-Board Protections
  • ALI, HIS, AC all utilize thermostatically
    controlled heaters
  • TSMs in place / verified which monitor key
    temperatures and safe instruments if necessary
  • ALI 28v service OFF if FPE board, ALI radiator,
    or 28v service current too high
  • HSI 28v service OFF if ASPs too hot
  • AC 28v service OFF and AC turn on RTSs disabled
    if PSB too hot
  • Additional HSI internal FDC checks / safing
    performed
  • Cal lamps OFF if lamps on too long
  • HSI safehold if ASP temps too high
  • ALI also performs internals checks / safing
  • Temperatures (FPE radiator, motors)
  • Currents (heaters, lamps, 28v input, motors,
    HOPAs)
  • On time (FPE, HOPA, motors)

61
Operations Plans
  • Round the clock operations staffing planned
  • Instrument reps to be co-located with FOT during
    instrument check-out operations
  • Capability to view real time and archive
    telemetry from instrument remote facilities also
    exists and verified
  • Up to every orbit ground station coverage planned
    to allow monitoring of S/C / instruments
  • MOC performs limit checking and can initiate
    safing commanding if necessary
  • Command procedures developed and verified which
    can be used to safe instruments and to perform
    planned instrument operations
  • A number of functional tests and sims performed
    to demo people, plans, and procedures

62
Operations Plans (continued)
  • Initial instrument ops performed during RT
    contacts to allow monitoring / safing (if
    required)
  • Ground initiated science collects
  • Ensures instruments turned off following
    science collects
  • Routine science ops performed from stored
    command. Processes in place and verified numerous
    times (TV, CPT, functional tests) to process
    requests and schedule required commanding.
    Scenarios include
  • Images
  • Solar Cals
  • WARP Data Ops
  • ALI Internal Cals
  • Lunar Cals

63
Special Topic Operator Training
. . . Joe Howard FOT Lead
64
FOT Training
  • Major finding of FOR was that classroom training
    needed strengthening. This has been done
  • Training developed as result of FOR
  • Plan follows CSOC ISO-9001 approved training plan
  • Flight Dynamics Support
  • Command Controller
  • Mission Planner
  • Data Processor
  • Training consists of
  • S/C subsystem classroom and video training
  • Classroom ground system training
  • Various specialty classes such as STK training
    and familiarization with the Flight Dynamics
    Support System
  • OJT through simulations and IT
  • ATSC sponsored Center for Operations, Research
    Engineering (CORE)

65
FOT Training
  • Training documented through Training Event
    Reports, Job Requirement Checklist, Skills
    Catalog, and Certification
  • Certification follows the CSOC approved
    certification process
  • FOT member must complete their Skills Catalog and
    receive favorable evaluations before FOT Lead and
    Mission Operations Manager will sign
    Certification Certificate

66
S/C Training Status as of 3-8-00
67
Ground Training Status as of 3-8-00
68
Special Topic Operator Staffing Versus
Function-Overloaded
. . . Joe Howard FOT Lead
69
Functional FOT Organization
  • New team structure to cover 24 hour operations 7
    days a week up to Launch plus 60 days
  • Review held at Launch 30 days on whether to
    down-staff at Launch 60 days

70
FOT Experience (Core)
71
FOT Experience (Supplementing LEO)
72
FOT Experience (Supplementing LEO)
73
FOT Shift Profile
  • Power up shift Before launch to L3 days
  • 2 x 12 hour shifts for first 7 days and then
    transitioning to 3 shift operations
  • L3 to L60 3 shifts supplemented with returning
    TCs from west coast
  • At L30 L60 will have review to decide if we
    will extend 24 hour operations
  • If Ops nominal then, during Normal Ops, will have
    2 shifts offset by 4 hours to provide coverage 12
    hours per day M - F otherwise continue 3 shift
    24 hour coverage

74
FOT Shift Support Week 1
(12 hours)
Prime shift
Back shift
75
FOT Shift Support Week 2 to L60
(8 hours)
Prime shift
Swing shift
Night shift
76
FOT Shift Support Normal Ops (w/ Automation)
(8 hours)
Prime shift
Swing shift
Night shift
Note that shifts for selected FOT will be offset
by 4 hours to provide 12 hours coverage M-F
77
FOT Staffing Conclusion
  • Based on the present operations plan, we are
    adequately staffed

78
Special Topic Planned Cooperation with Landsat 7
. . . Bob DeFazio EO-1 Flight Dynamics
79
Landsat-7 / EO-1 Interface
  • The Landsat-7 / EO-1 Interface is documented in
    an ICD that was prepared, reviewed and signed off
    by both projects
  • ICD content includes flight dynamics issues,
    cloud cover products, Landsat-7 daily target list
    and Landsat-7 cloud cover assessment scores

80
Landsat-7 / EO-1 Flight Dynamics Planning
  • To retain the Landsat-7 / EO-1 formation flying
    configuration, Landsat-7 must inform EO-1 about
    current Landsat-7 orbit position and future orbit
    maneuver plans
  • Landsat-7 will provide a daily orbit state vector
    and a weekly product set that details their orbit
    maneuver plans over the next 6 weeks
  • EO-1 will use the Landsat-7 inputs to plan EO-1
    maneuvers that maintain the Landsat-7 / EO-1
    formation flying configuration

81
Landsat-7 / EO-1 Co-Imaging
  • To plan and validate the co-fly images taken by
    Landsat-7 and EO-1 the following items will be
    provided to EO-1
  • From the National Center for Environmental
    Predictions (NCEP) predicts of cloud coverage
    will be available to EO-1 daily from the NOAA
    NCEP website
  • A Landsat-7 daily target list will be available
    to EO-1 Monday-Friday from a Landsat-7 website
  • Landsat-7 post-imaging cloud cover assessment
    scores will be available to EO-1 from the Earth
    Resources Observation System (EROS) Data
    Center

82
Landsat-7 / EO-1 Interface Validation
  • Since October 1999
  • Run FreeFlyer on Fridays to provide model of next
    6 weeks of maneuvers for Landsat
  • Product output from FreeFlyer is input into
    Autocon-G which then generates a 35 day ephemeris
    for EO-1
  • Products from Autocon-G are sent through FORMATS
    and MOPSS to generate simulated image planning
  • Planned simulated EO-1 scenes are compared with
    Landsat image plan as a check
  • This exercise is done on a weekly basis
Write a Comment
User Comments (0)
About PowerShow.com