Title: Operations MOC
1Section 33 Operations / MOC
. . . Dan Mandl EO-1 Operations Manager
2Contents
- Overview of Operations Dan Mandl
- Testing and Verification Status
- MOC H/W Status
- MOC Procedure Status
- Launch Overview
- Documentation
- Configuration Management
- SOMO Institutional Mission Operations Support
- RFA Status from Previous Reviews
- Readiness and Residual Risks Redbook Candidates
- Special Topics
- MOC Simulations Gus Gustafson
- Contingency Operations Pete Spidaliere
- Ampex Recorders
Dan Mandl - How Ops Plans to Avoid Instr Overheating
Bruce Trout - Operator Training
Joe Howard - Operator Staffing Versus Functions-Overloaded?
Joe Howard - Planned Cooperation with Landsat
Bob DeFazio
3Operational Philosophy
- 1 year mission
- During Normal Ops
- 3-8 passes/day (2 for science dumps)
- During LEO
- 14 passes/day (2 for science dumps) during first
week - 8 passes/day (2 for science dumps) from L8 to
L60 - 80 Gb of data max (typ 2 DCEs) from instruments
per day - Staffing
- 24 hr x 7 day staffing for operations during
first 60 days - Phase down to 8hr x 5 day after L60 contingent
on review at L30 - After phase down, use automation for non-manned
hours - Weekends and evenings
Ops Overview
4Operations Overview
Ops Overview
5Operational Phases
- Launch Early Orbit
- Launch and the first several orbits, spacecraft
checkout, and instrument turn-ons - Approximately 15 days (20 days to get to 1 min
behind Landsat) - 1 minute behind Landsat 7
- Instrument Checkout
- Full instrument checkout
- Approximately 45 days
- Nominal Ops
- Science Validation
- 10 months
- End of Life
- Deorbit burn for reentry within 25 years
Ops Overview
6 Ground System Requirements Summary
- Ground stations to receive, process, and route
science and housekeeping data to GSFC - X-band
- Receive up to 80 Gbits of science data each day
at 105 Mb/s - Record the received X band data on hard media,
mail to GSFC, and store raw data for 30 days - S-band
- Receive data at selected rates up to 2 Mb/s
- Housekeeping data
- Route selected virtual channels to GSFC in real
time - Record up to 200 Mbits of data each day
- FTP recorded data to EO-1 MOC within two hours
- Store raw data for 30 days
- Backup science data (up to 5 Gbits per day)
Process as with X band
Ops Overview
7 Ground System Requirements Summary
- Process Hyperion, MS/PAN, AC science data to
provide at least 200 paired scene comparisons
with Landsat 7 - 55 scenes for ALI, AC during 60 day checkout
- 55 Hyperion, AC scenes
- 1000 scenes total first year
- Maintain an orbit of sufficient precision for
scene comparisons - Follow Landsat 7 Ground Track
- /- 3 km cross track
- 1 minute behind /- 6 seconds
- 1 minute later than Landsat in mean local time at
the descending node
Ops Overview
8 Ground System Requirements Summary
- Maintain the health and safety of the spacecraft
and instruments - Validate and calibrate on-board orbit and
attitude subsystems - Perform orbit maneuver control to enable
formation flying - Provide mission planning and command management
for - Image operations
- Other technology validation operations
- Calibration operations
- Contingency operations
- Archive raw and processed data
Ops Overview
9Verification Approach
- Verified against
- EO-1 Ground Functional and Performance
Requirements - Detailed Mission Requirements (SOMO services)
- System testing done by the developers of each
subsystem - Acceptance testing and Mission Readiness Testing
done by the FOT to verify each subsystems
requirements and end-to-end performance of ground
components - Simulations performed by FOT, Instrumenters, and
S/C subsystem engineers for final end-to-end
check of teams ability to perform required tasks - Post-Launch Verification of new releases of
ground S/W - Regression testing by means of shadowing
operations and comparing results with previous
version
Testing Verification
10EO-1 Operations Testing Status
S Acceptance Testing T Mission Readiness
Test M Simulation
Testing Verification
11(No Transcript)
12Requirements Verification
- 94 of the requirements verified
- Unverified requirements
- 7 Instrumenter requirements not verifiable before
launch because involve providing LEO support - SVF shall receive DCE and calibration requests
from Science Validation Team - SVF shall perform Level 1 processing of AC data
after receipt of code from AC Instrumenters - Interface with FDF algorithms to schedule
activities/commands for momentum management - Mostly tested, waiting for delivery by 4/15/00 of
enhancement to complete verification
Testing Verification
13Requirements Verification
- Unverified requirements (continued)
- 4 GN requirements only testable post launch,
involves performance of personnel at ground
stations - 2 CGS requirements involve testing capability of
SERS to page FOT member - Capability in process of testing
Testing Verification
14Ground Discrepancy Reports (DR) Status as of
3-16-00 Critical DRs
- DR 58-FDSS Add Solar Array modeling to
computation of reaction wheel speeds - Fix in testing, complete by 4/15/00
- DR 150-Networks During simulation, lost socket
connection to STGT for commanding - Under investigation
Testing Verification
15Ground DR Status as of 3-16-00 Urgent DRs
- DR 16-ASIST Capability to change limits from
database lookup window - Under investigation
- DR 18 67-ASIST Slow playback
- Fix being developed, complete 4/30/00
- DR 163-ASIST SOH HDF files have error
- Fix in process for patch to be delivered by
4/30/00 - DR 10-DHDS Playback cant be automated
- Same fix as DR 18 and DR 67
- DR 82-FEDS Translator needed for VC4
- In process of being developed. Date of delivery
TBD - DR 114-FEDS Command interface problem with SN.
Statistics wrong - Under investigation
- DR 164-Ground During Time correlation test, PTP
offset time by 300 msec - Under retest by 3/21/00
- DR 55-MOPSS MOPSS needs fail-over capability
- In process of configuring dual workstation
fail-over mode. Almost complete - DR 169-MOPSS Problem with command DB ingest
- Problem fixed, waiting for retest
- DR 79-Net Ampex recorder at Wallops broken
Testing Verification
16Ground DR Status as of 3-16-00 Urgent DRs
(continued)
- DR 151-Net ATS load configured S/C for 2K
coherent. - Under investigation
- DR 71-OPS Need to build ground station summary
report - Action assigned to FOT
- DR 84-Ops WARP directory needs to be a flat
file - Action assigned to FOT
- DR 107-Ops Monitor was unreadable
- Action assigned to Jim Weidman, system admin.
- DR 111-Ops Command to SCP rejected
- Under investigation
- DR 115-Ops When command TDRSS 4k downlink, page
shows error. Possible RDL problem - Under investigation
- DR 109-S/C During sim, TSMs 53, 63, 71, 72 and
73 failed - Submit as S/C PR
- DR 119-S/C During sim, unable to go backward in
time - Under investigation by K. Blackman
- DR 120-S/C During sim, no command link.
Problem in IT - Assigned to IT
- DR 166-S/C Limits need to be changed for new
command DB for MOPSS
Testing Verification
17S/C to MOC Testing(1 of 2)
Testing Verification
18S/C to MOC Testing(2 of 2)
P - Planned
Testing Verification
19Simulations
- Typical content of Launch and Day 2 simulation
and contingencies are discussed in the MOC Sim
special topic
Testing Verification
20EO-1 Data Link Configuration for Testing and LEO
21EO-1 Data Link Configuration for Normal Ops
22MOC Hardware Status
- All MOC hardware in place except the following
- Trending system waiting for delivery of PC
- Using temporary PC in the meantime
- MOC firewall
- Have in house, but waiting for NISN approval of
revised Security Plan - Will be installed during 4/00
Hardware Status
23MOC Procedure Status
- Regular Procedures tested
- ACS 66/66
- PSE 13/13
- RCS 2/2
- GPS 8/11
- LFSA 2/2
- MV 7/8
- WARP 14/32
- Combined Inst 17/17
- AC 11/11
- ALI 25/35
- Hyperion 32/43
- COM/CDH 5/9
- RF 4/9
- Timecode 3/3
- Ground 6/6
- ATS 9/9
- Recorder 3/5
- Total 233/284 82
MOC Procedure Status
24Launch
- Launch Vehicle
- Launched from WTR on a Delta 7320
- Co-manifested with the Argentine SAC-C
spacecraft. EO-1 separates first. - Launch Window
- EO-1 has an instantaneous launch window with a
30 second allowance for collision avoidance.
The window occurs once per day at about 1826
GMT. - Formation flying with Landsat 7
- To enable EO-1 to co-fly with Landsat 7, it is
necessary to place EO-1 one minute (/-6 sec)
behind Landsat 7 and within 3 km crosstrack. - The launch vehicle injection point is near the
start of first ascending node. The Local time
will be 2204. - Depending on the performance of the Launch
Vehicle, between 6 and 8 maneuvers will be
required to position EO-1 behind L7. - Final Orbit
- 705 km, circular, sun-synchronous, inclination of
98.2 degrees
Launch Overview
25Space Network Ground Network Coverage
- Space Network
- Use of TDRS is planned for powered flight and the
first few orbits after separation and later
during initial maneuvers - Ground Network
- Norway
- Alaska
- Wallops
- McMurdo
Launch Overview
26Launch Day Orbit Ground Trace
Launch Overview
27Highlights of LEO
- Day 1
- Launch, Launch vehicle separation, SA deployment
- B-dot and sun acquisition
- Turn on IRU heaters, Star Tracker, GPS, and ALI
outgas heaters - Initialize Kalman Filter
- Day 2
- Begin use of Kalman Filter
- Begin use of GPS for time
- Test Safehold Logic
- Go to Earth Pointing
- Day 3
- Pitch Slew for IMU calibration
- Yaw Slew for IMU calibration
- Roll Slew for IMU calibration
- Reengineering Thruster Burn
- Day 4
- Enable Enhanced Formation Flying Software in
monitor mode - WARP checkout
- X-band Phased Array on and dump of WARP test
pattern
Launch Overview
28Highlights of LEO
- Day 5
- ALI turn on and initial check out
- Inclination burn
- Day 6
- Begin Hyperion turn on and initial checkout (done
over 3 days) - Turn on and checkout Atmospheric Corrector (done
over parts of 2 days) - Day 7
- Continue Hyperion and AC checkout
- Day 8
- Continue Hyperion Checkout
- Perform all instrument data collection event
- Day 9
- Rest Day (contingency)
- Day 10
- Safehold test
- S/C recovery from safehold
- Day 11
- Instrument recovery from safehold
- Activity plan lays out the detailed plan for the
first 11 days
Launch Overview
29LEO Organization
Launch Overview
30Documentation Philosophy
- All required documents to operate the S/C are on
the EO-1 website - Copies of required documents will be at the
console during operations - Mission Operations Manager and FOT Lead will be
responsible for a Controlled Document List and
will assure that all printed documents are in
concurrence with the this list - Gabrielle Araiza is librarian to assure that
documents in MOC library are up to date
Documentation
31Key Documents for Operations
Documentation
32Key Documents for Operations
Documentation
33S/C Users Guide Status
- Completion of S/C Users Guide scheduled for 6/00
after all training is done and the feedback
folded into the Users Guide
Documentation
34Mission Procedures Document
- Mission Procedures Document (MPD) on EO-1 website
- MPD Vol 1 is the Ops Concepts
- MPD Vol 2, Detailed Ops Plans
- Launch Early Orbit (LEO)
- Pre-Launch Script (in process of being created)
- Launch Script (baselined)
- Instrument Checkout Scrip(baselined)
- LEO Specific Procedure
- Normal
- Normal operations procedures
- Contingency procedures (flowcharts and scripts)
- General
- Telemetry and Statistics Monitors (baselined)
- FDCs (baselined)
- Relative Time Sequences (baselined)
- List of pages
- List of S/C Event messages
- Problem escalation procedures
- CM Plan for Procs, Pages, Documents and S/W
Documentation
35Configuration Management
- Documents are on EO-1 CM website
- http//eo1.gsfc.nasa.gov (select configuration
management) - ISO Compliant
- Procedures
- Tested
- Placed global procedure directory
- Write privileges only by sys admin
- Changed via Operations Change Request
- Database Pages
- All pages inherited from IT
- Build latest version and placed in configured
directory - Only DB administrator can access
- Temporary changes placed in global directory by
any FOT member - Changes via DB change request forms
Configuration Management
36SOMO Institutional Mission Operations
- FOT and sustaining engineering under a CSOC SODA
- Ground station and Space Network support under
CSOC - Requirements driven by Detailed Mission
Requirements(DMR) Mission Operations Support
Plan(MOSP)
SOMO Institutional Support
37RFA Status
- 23 RFAs were assigned from the original MOR and
are closed - 20 RFAs were assigned from the Delta MOR
- 19 are closed
- 1 response was submitted and still under review
- 14 RFAs were assigned from the FOR
- 10 closed
- 5 responses resubmitted and still under review
RFA Status
38Critical RFA Status
RFA Status
39Critical PR
- Critical PR 675-20-2, 829-30-2 and 829-30-3 are
being held open - S/C side is okay
- Ground has some residual problem on the PTP front
end at the ground stations - As a result recent tests stay marginally within
specs for time correlation operations activities - PTP problems presently under investigation
RFA Status
40Readiness and Residual Risks Redbook Candidates
- No significant residual risk
- WARP repair provides additional simulation and
training opportunities - No Redbook candidates
- Operations is on schedule to support the launch
41Special Topic MOC Simulations
. . . Gus Gustafson EO-1 Simulation Manager
42Simulation Summary
- Sim 1 Normal operations during Thermal/Vac
10/10,13,16/99 - Primary ATS loads exercising the instruments in
routine operational modes - All three instruments exercised
- 3 separate days of operating were conducted (16
hours ea.) including X-band dumps and data
processing activities - Exercised the MOPSS
- Ground stations not involved
- Sim 2 Launch simulation days 1, 2 and 3 (no
contingencies) - 10/28/99, day 1 Prelaunch and launch activities
through 5 orbits resulting in S/C having achieved
sum acquisition and being power positive - Included Star Tracker and GPS turn on
43Simulation Summary
- Sim 2 Day 2 10/29/99
- Real world orbits 12 through 42, activities
compressed into 7 orbits - Energized slewing to Earth pointing
- One of three Gyro calibration slews
- Delta V thruster burn
- Sim 2 Day 3 11/3/99
- Real world orbit 44 through 103, activities time
compressed into 12 hours - Included WARP and instrument turn-ons as scripted
- S-band and X-Band downlinks exercised
- Data processing activities conducted
- Ground stations not involved, however used TDRSS
support during Day 1 - 2 unplanned contingencies
44Simulation Summary
- Sim 3 Launch simulation with contingencies
(Days 1 2) 12/13 14/99 - Same scripting as Sim 2 but with contingencies
- 6 planned contingencies, 1 unplanned
- Sim 4 science end-to-end simulation, Day 23
- Included ground stations (SGS, AGS and WGS)
- No S/C interface
- Verified command and telemetry interfaces from
MOC to all three stations - Verified the science planning interfaces
- Stations provided
- Tracking data files
- Station status messages
- Standard Autonomous File Server (SAFS) data
- Post pass summaries
45Simulation Summary
- Sim 4 science end-to-end simulation, Day 23
- Exercised the Data Processing System for S-band
and X-band data processing, including
distribution of data products - Exercised data links to TRW and MIT/LL for
realtime and playback data - Exercised the Data Quality Monitor system at WGS
- Provided tapes to the Science Validation Facility
- Exercised MOC trending capability
- Sim 5 Repeat of science end-to-end 1/4/00
- Sim 6 Launch simulation with contingencies (Day
1 only) 1/14/00 - 4 planned contingencies
- Sim 7 Launch simulation with contingencies
(Days 1 2) 1/2428/00 - 13 planned contingencies and 2 unplanned
46Simulation Summary
- Sim 8 Repeat of science end-to-end 2/2/00
- Sim 9 Mini-Sim exercising safehold and safehold
recovery 2/4/00 - Sim 10 Mini-sim exercising a thruster burn
2/16/00 - Sim 11 Launch sim with contingencies (Day 1
2) 2/1718/00 - 15 planned contingencies
- Sim 12 Repeat of the science end-to-end
simulation 2/23/00 - Sim 13 Simulation of the S/C tumbling post
separation 3/9/00 - Sim 14 Launch sim with contingencies
- 4 planned and 1 green card
47Subsystems Exercised with Contingencies
Planned 43 Unplanned 5 Total 48 Note
Since a given contingency may affect more than
one subsystem, this explains the difference
between the number of contingencies totaled in
the line above and the number of total number
from the right most column of the chart.
48Special Topic MOC Contingency Operations Plans
. . . Pete Spidaliere EO-1 Mission Systems
Engineer
49Contingency Procedures
- Anomalies are dealt with through the following
- On-board Telemetry and Statistics Monitors that
sense an anomalous condition and either warn the
Ground through an Event Message or initiate a
Relative Time Sequence to safe the instruments
and/or spacecraft. These are system level
protections. - Box or Instrument level Failure Detection and
Correction software that, like the system level
protection, sense and initiate safing events. - Ground-based contingency procedures that are used
to determine an unsafe condition exists and what
steps should be taken to return to a safe
condition. - Required and highly desired contingency
procedures have been identified and developed by
the Systems, Subsystem, Instrument, and Flight
Ops teams. - Testing of approximately 60 of the procedures
has occurred and the remainder will be tested
before shipment. - All simulations, except the first, have contain
anomalies. This allows for training the team on
how to use the procedures.
50Contingency Procedures
- Procedures exist in the form of STOL Procs and
Decision Trees. - All STOL Procs will be tested before use.
- Decision Trees will, by their nature, be verified
by review. - Most of the STOL Procs have been developed and
tested. The Flight Software Team has been
occupied with other high priority tasks, but is
now free to aid in the development of CDH STOL
Contingency Procs. - Many of the Decision Trees have been developed
and reviewed. Several have been tested during
Simulations, and the need for others has been
determined during the Simulations. None can be
considered final at this time, but most are quite
mature and have been through a round of Systems
Level review.
51STOL Contingency Procedures
52STOL Contingency Procedures (continued)
53STOL Contingency Procedures (continued)
54Decision Trees
- LV Separation Anomaly
- SA Fails to Deploy
- Communications Anomalies
- No Telemetry
- No Commanding
- TDRS Telemetry/Commanding anomaly
- MOC Misconfiguration
- Ground Station Loss of Comm
- NISN Contingency
- Power Anomalies
- Half Battery Voltage Differential
- Battery Temperature
- Battery Undervoltage
- Battery Overvoltage
55Decision Trees
- ACS
- BDOT System Momentum Not Decreasing
- Tip-Off rates higher than worst case
- Phasing error
- SA Drive Not Driving to Zero Degrees (early
orbit) - Sun Acquisition Mode Anomaly
- Residual magnetic dipole higher than expected
- Phasing error
- AST Failure
- MTR Failure
- TAM Failure
- IRU Failure
- RWA Failure
- XPAA Pointing Anomaly
56Critical PRs and RFAsAddressed in This Section
- RFA 18.15 Status and Verification of
Contingency Procedures - PR 675-20-4 Red High Limit on Atmospheric
Corrector Power Supply Card
57Special Topic Ampex Recorders
. . . Dan Mandl EO-1 Ground Systems Manager
58Ampex Recorder Status
- Ampex tape recorders (Special Topic)
- Reliability of Ampex tape recorders at ground
stations in question at FOR - Developed Ops procedure whereby during initial 30
days when tape is recorded, tape is played back
through DQM before shipping to MOC to verify good
data on tape - All Ampex tape units fixed at ground station and
are operational at present time
59Special Topic How Operations Plans to Avoid
Instrument Overheating
. . . Bruce Trout EO-1 Mission Planner/FOT
60On-Board Protections
- ALI, HIS, AC all utilize thermostatically
controlled heaters - TSMs in place / verified which monitor key
temperatures and safe instruments if necessary - ALI 28v service OFF if FPE board, ALI radiator,
or 28v service current too high - HSI 28v service OFF if ASPs too hot
- AC 28v service OFF and AC turn on RTSs disabled
if PSB too hot - Additional HSI internal FDC checks / safing
performed - Cal lamps OFF if lamps on too long
- HSI safehold if ASP temps too high
- ALI also performs internals checks / safing
- Temperatures (FPE radiator, motors)
- Currents (heaters, lamps, 28v input, motors,
HOPAs) - On time (FPE, HOPA, motors)
61Operations Plans
- Round the clock operations staffing planned
- Instrument reps to be co-located with FOT during
instrument check-out operations - Capability to view real time and archive
telemetry from instrument remote facilities also
exists and verified - Up to every orbit ground station coverage planned
to allow monitoring of S/C / instruments - MOC performs limit checking and can initiate
safing commanding if necessary - Command procedures developed and verified which
can be used to safe instruments and to perform
planned instrument operations - A number of functional tests and sims performed
to demo people, plans, and procedures
62Operations Plans (continued)
- Initial instrument ops performed during RT
contacts to allow monitoring / safing (if
required) - Ground initiated science collects
- Ensures instruments turned off following
science collects - Routine science ops performed from stored
command. Processes in place and verified numerous
times (TV, CPT, functional tests) to process
requests and schedule required commanding.
Scenarios include - Images
- Solar Cals
- WARP Data Ops
- ALI Internal Cals
- Lunar Cals
63Special Topic Operator Training
. . . Joe Howard FOT Lead
64FOT Training
- Major finding of FOR was that classroom training
needed strengthening. This has been done - Training developed as result of FOR
- Plan follows CSOC ISO-9001 approved training plan
- Flight Dynamics Support
- Command Controller
- Mission Planner
- Data Processor
- Training consists of
- S/C subsystem classroom and video training
- Classroom ground system training
- Various specialty classes such as STK training
and familiarization with the Flight Dynamics
Support System - OJT through simulations and IT
- ATSC sponsored Center for Operations, Research
Engineering (CORE)
65FOT Training
- Training documented through Training Event
Reports, Job Requirement Checklist, Skills
Catalog, and Certification - Certification follows the CSOC approved
certification process - FOT member must complete their Skills Catalog and
receive favorable evaluations before FOT Lead and
Mission Operations Manager will sign
Certification Certificate
66S/C Training Status as of 3-8-00
67Ground Training Status as of 3-8-00
68Special Topic Operator Staffing Versus
Function-Overloaded
. . . Joe Howard FOT Lead
69Functional FOT Organization
- New team structure to cover 24 hour operations 7
days a week up to Launch plus 60 days - Review held at Launch 30 days on whether to
down-staff at Launch 60 days
70FOT Experience (Core)
71FOT Experience (Supplementing LEO)
72FOT Experience (Supplementing LEO)
73FOT Shift Profile
- Power up shift Before launch to L3 days
- 2 x 12 hour shifts for first 7 days and then
transitioning to 3 shift operations - L3 to L60 3 shifts supplemented with returning
TCs from west coast - At L30 L60 will have review to decide if we
will extend 24 hour operations - If Ops nominal then, during Normal Ops, will have
2 shifts offset by 4 hours to provide coverage 12
hours per day M - F otherwise continue 3 shift
24 hour coverage
74FOT Shift Support Week 1
(12 hours)
Prime shift
Back shift
75FOT Shift Support Week 2 to L60
(8 hours)
Prime shift
Swing shift
Night shift
76FOT Shift Support Normal Ops (w/ Automation)
(8 hours)
Prime shift
Swing shift
Night shift
Note that shifts for selected FOT will be offset
by 4 hours to provide 12 hours coverage M-F
77FOT Staffing Conclusion
- Based on the present operations plan, we are
adequately staffed
78Special Topic Planned Cooperation with Landsat 7
. . . Bob DeFazio EO-1 Flight Dynamics
79Landsat-7 / EO-1 Interface
- The Landsat-7 / EO-1 Interface is documented in
an ICD that was prepared, reviewed and signed off
by both projects - ICD content includes flight dynamics issues,
cloud cover products, Landsat-7 daily target list
and Landsat-7 cloud cover assessment scores
80Landsat-7 / EO-1 Flight Dynamics Planning
- To retain the Landsat-7 / EO-1 formation flying
configuration, Landsat-7 must inform EO-1 about
current Landsat-7 orbit position and future orbit
maneuver plans - Landsat-7 will provide a daily orbit state vector
and a weekly product set that details their orbit
maneuver plans over the next 6 weeks - EO-1 will use the Landsat-7 inputs to plan EO-1
maneuvers that maintain the Landsat-7 / EO-1
formation flying configuration
81Landsat-7 / EO-1 Co-Imaging
- To plan and validate the co-fly images taken by
Landsat-7 and EO-1 the following items will be
provided to EO-1 - From the National Center for Environmental
Predictions (NCEP) predicts of cloud coverage
will be available to EO-1 daily from the NOAA
NCEP website - A Landsat-7 daily target list will be available
to EO-1 Monday-Friday from a Landsat-7 website - Landsat-7 post-imaging cloud cover assessment
scores will be available to EO-1 from the Earth
Resources Observation System (EROS) Data
Center
82Landsat-7 / EO-1 Interface Validation
- Since October 1999
- Run FreeFlyer on Fridays to provide model of next
6 weeks of maneuvers for Landsat - Product output from FreeFlyer is input into
Autocon-G which then generates a 35 day ephemeris
for EO-1 - Products from Autocon-G are sent through FORMATS
and MOPSS to generate simulated image planning - Planned simulated EO-1 scenes are compared with
Landsat image plan as a check - This exercise is done on a weekly basis