Title: 7x24 Exchange
17x24 Exchange
- Power Quality Troubleshooting
- Dallas, May 5th 2005
2What is Power Quality ?
- Power The ability to do something
- Quality The degree of excellence
3What is Power ?
- Major utility company had a faulty electrical
switch and had to open the branch while under
load. - Note that one of the air switches, refused to
disconnect immediately. - Watch the result!!!
4How is your Power today?
- Is it good?
- Is it bad?
- Is it getting better?
- Is it getting worse?
- Where is it getting worse?
- Why is it getting worse?
5Expensive Downtime
- Semiconductor Manufacturer 3,000,000 per
event - Intel, Motorola, AMD
- Telecom Switch 50,000 per minute
- Bell, Sprint, MCI
- Data Center 20,000 to 1,000,000 per min
- EDS, Fidelity, American Express
- dot.com IBX centers
- Car Manufacturer 25,000 per minute
- General Motors, Ford
6PQ Troubleshooting tools
- Voltage logger.
- Single phase. voltage
- Transient capture
- Sags, swells
- Hand held portable.
- Single phase power
- In-Rush current
- N-G bonding
7PQ Troubleshooting tools
- Power Quality.
- 3 phase. Voltage, current
- Transient capture
- Sags, swells, Harmonics
- Unbalance
- Power Quality.
- 3 phase power
- Cycle by Cycle
- Full Disclosure capture
8PQ Troubleshooting Philosophy
- Start at the scene of the crime
- Examine the victim (the load)
- Take time to visually inspect
- What is the business cycle?
- Ask questions?
9PQ Troubleshooting Bottom-up
- Example High harmonics everywhere
- Load location
- Problem location, most likely causes
- Monitoring issues
10PQ Troubleshooting Getting Started
- Make a simplified as-built one-line
- Do a walk-around
- Interview witnesses
11Power Distribution System
3. Feeder loads
1. Branch circuit and service panel
- 2. Distribution Transformer
12Receptacle Line to Neutral Voltage
13The Case of the Rural Transformer Failure
- Scene of the crime
- Rural area surrounded by farmland and open space
- Enigma
- Utility transformer failure occurred in location
where power quality problems are rare - Risk
- Loss of power
14Utility Electrical Engineers Notes
Load consists of 3 end-users
What happened during the day of the transformer
failure?
15Single Phase Measurements
Battery chargers are non-linear loads that
generate harmonic currents
16Utility Electrical Engineers Notes
- Problem
- All three end-users experienced peak loads at the
same time (5 7pm) - Residential peaks occur at dinnertime with use of
TV sets, stoves, dishwashers, etc. - Addition of the large battery charger load on the
day of the golf tournament caused the transformer
to overheat
17Utility Electrical Engineers Notes
Solution
- Golf club supervisor agreed to use careful load
management - Restrict number of chargers connected at one time
- Avoid use of chargers during peak times
-
18Takeaways
- Transformers can overheat and fail if heavily
loaded with harmonic currents - Battery chargers are non-linear loads that
generate harmonic currents - Golf clubs and marinas are vulnerable to sudden
large battery charger loads - Timing was important in solving this case history
always ask for timing info - Careful load management can usually avoid
overloads
19Power Quality TroubleshootingService Panel
20Feeder Current
21Feeder Phase Balance
ØA
ØB
ØC
- How much current do you expect on the feeder
neutral?
22Neutral Current
3rd harmonic 37.35A
Fundamental 3.71A
- Neutral current
- 180 Hz waveform
- 40.57A
233rd Harmonic
24The Case of the 5th Harmonic Resonance
- Scene of the crime
- A small city gets its water from a mountain lake
30 miles away - A pumping system at the lake brings water through
a pipeline that feeds the citys water
distribution system - Enigma
- Under generator power, the backwash filtering
system suddenly shuts off - Risk
- Interruption of water supply to the city
25Water Plant Electrical Engineers Notes
Diagram of the water plant
Utility System has no problem when utility power
is connected
Generator Backwash pump shuts off partway
through the start sequence
26Water Plant Electrical Engineers Notes
Generator Why does the backwash pump shut off
partway through the start sequence?
- Backwash pump shuts off partway through the start
sequence due to a stop signal from the
protection circuit
- Fluke 43B showed 5th harmonic distortion rising
to 80 of the fundamental prior to the stop
signal
- Distortion caused by high resonance current at
the 5th harmonic flowing between the motor
inductance and the PF correction caps
- Harmonic current flowing into the generator
impedence caused enough voltage distortion to
produce a stop signal
27Water Plant Electrical Engineers Notes
Solution
Move the capacitors to the utility side of the
transfer switch so that the capacitors are out of
the circuit when the generator is operating
28Takeaways
- System operation on generator power should be
tested for all load combination - Voltage distortion is usually higher when
operating on a generator due to higher impedance
of the generator - Power factor correction caps can make the system
resonant near the 5th harmonic - Semiconductor soft start circuits are often not
compatible with PF correction caps - Common test equipment is not adequate for
harmonic analysis.
29Voltage Severity ITIC
30Voltage Severity ITIC
31Selected Event
32Why Worry About Sags?
Sags are the most prevalent event
- Voltage quality was monitored at the wall outlet
at 112 North American locations from 1990-1994 - Sags average 27.9 per month with an average sag
amplitude of 99.3Vrms. - The median sag duration is 260ms (4.3 cycles)
2-10cycles
10c-1s
1-10s
gt1min
10s-1min
41
22
20
6
11
33RMS Inrush Measurement
- Half cycle rms value of the r.m.s. current
measured over each half-period - Inrush current begins when the half-cycle rms
current rises above the inrush threshold, and
ends when the half cycle rms current is equal to
or below the inrush threshold minus a
user-selected hysteresis value. The measurement
should be the half cycle rms values. Each
half-cycle interval is contiguous and
non-overlapping. -
34Inrush Current
35Transients
- Utility transformer tap switching
- Capacitors switching on.
- Lightning
- Motors switching off (Elevators)
- Switch and relay contact bounce
- Damage semiconductor junctions
- Couple into adjacent circuits because of high
frequency (fast rise times) - Corrupt data signals
- Protection TVSSTransient Voltage Surge
Suppressors
36Case Study Re-active decision
- Large European Wafer Plant
- 5,000 employees
- Serious failure condition
- No monitoring
- Costly downtime
- Installed equipment to prevent similar incident
37Case Study Pro-active decision
- Major US bank
- Central HQ for ATM and On-Line customer
transactions - Failure of UPS system
- SCR misfiring
- Bank identified problem
- Corrective action in place
38New ways of thinking
The old way Did anything happen? What
happened? What is the cause? The new way What
will happen next? When will it happen again? How
can I prevent it?
39FULL DISCLOSURE MONITORING
- BREADTH OF MEASUREMENTS
- DEPTH OF MEASUREMENTS
40BREADTH OF MEASUREMENTS
- Power Quality
- Power Consumption
- Harmonics
- Flicker
- Imbalance
- Ground loops
- Oscilloscopes
41DEPTH OF MEASUREMENTS
- Cycle by Cycle measurements RMS, harmonics,
THD, W, VA, VAR, PF, etc. - Power Quality No thresholds set limits
after the fact use power tolerance curve use
indices to track conditions
42Power Quality Index
PQ Index 100
PQ Index 100
PQ Index 0
PQ Index 0
43time
441250 1000 750 500 250 0
1250 1000 750 500 250 0
Atlanta Power Quality Index Peak 270 Mean
55
45(No Transcript)
467x24 Exchange
- Thank you for attending
- john.carroll_at_fluke.com