Title: Project Analysis
1Chapter 8
Project Analysis (??????)
2Topics Covered
- How Firms Organize Their Investment Process
- Some What If Questions
- Sensitivity Analysis
- Break Even Analysis
- Flexibility in Capital Budgeting
- Decision Trees
- Options
3Capital Budgeting Process
- Capital Budget - The list of planned investment
projects. - The Decision Process
- 1 - Develop and rank all investment projects
- 2 - Authorize projects based on
- Government regulation or law
- Production efficiency
- Capacity requirements
- NPV
4Capital Budgeting Process
- Capital Budgeting Problems
- Consistent forecasts (??????????)
- Conflict of interest
- (????????????????)
- Forecast bias
- (?????????????????)
- Selection criteria (NPV and others)
5How To Handle Uncertainty
- Sensitivity Analysis - Analysis of the effects of
changes in sales, costs, etc. on a project. - Scenario Analysis - Project analysis given a
particular combination of assumptions. - Simulation Analysis - Estimation of the
probabilities of different possible outcomes. - Break Even Analysis - Analysis of the level of
sales (or other variable) at which the company
breaks even (Accounting vs. NPV break-even)
6Sensitivity Analysis (?????)
- Example
- Given the expected cash flow forecasts listed on
the next slide, determine the NPV of the project
given changes in the cash flow components using
an 8 cost of capital. Assume that all variables
remain constant, except the one you are changing.
7Sensitivity Analysis
NPV 478
8Sensitivity Analysis
- Example - continued
-
- Possible Outcomes
9Sensitivity Analysis
- Example - continued
- NPV Calculations for Pessimistic Investment
Scenario
NPV (121)
10Sensitivity Analysis
- Example continued
- NPV Possibilities
- (Check out the values! Some of them are wrong)
11??
????????
12Break Even Analysis (??????)
- Example
- Given the forecasted data on the next slide,
determine the number of planes that the company
must produce in order to break even, on an NPV
basis. The companys cost of capital is 10.
13Break Even Analysis
14Break Even Analysis
- Answer
- The break even point, is the of Planes Sold
that generates a NPV0. -
- The present value annuity factor of a 6 year
cash flow at 10 is 4.355 - Thus,
15Break Even Analysis
Answer Solving for Planes Sold
16Operating Leverage (????)
- Operating Leverage- The degree to which costs
are fixed. - Degree of Operating Leverage (DOL) - Percentage
change in profits given a 1 percent change in
sales.
17Operating Leverage
- Example - A company has sales outcomes that range
from 16mil to 19 mil, Depending on the economy.
The same conditions can produce profits in the
range from 550,000 to 1,112,000. What is the
DOL?
18Flexibility Options
- Decision Trees - Diagram of sequential decisions
and possible outcomes. - Decision trees help companies determine their
Options by showing the various choices and
outcomes. - The Option to avoid a loss or produce extra
profit has value. - The ability to create an Option thus has value
that can be bought or sold.
19Decision Trees
Success
Test (Invest 200,000)
Pursue project NPV2million
Failure
Stop project NPV0
Dont test
NPV0
20Decision Trees
- Allow us to graphically represent the
alternatives available to us in each period and
the likely consequences of our actions. - This graphical representation helps to identify
the best course of action.
21Example of Decision Tree
Squares represent decisions to be made.
Good
Circles represent receipt of information e.g. a
test score.
Test Market
OK
Failure
The lines leading away from the squares represent
the alternatives.
Do not Test
D
F
22Stewart Pharmaceuticals
- The Stewart Pharmaceuticals Corporation is
considering investing in developing a drug that
cures the common cold. - A corporate planning group, including
representatives from production, marketing, and
engineering, has recommended that the firm go
ahead with the test and development phase. - This preliminary phase will last one year and
cost 1 billion. Furthermore, the group believes
that there is a 60 chance that tests will prove
successful. - If the initial tests are successful, Stewart
Pharmaceuticals can go ahead with full-scale
production. This investment phase will cost 1.6
billion. Production will occur over the next 4
years.
23Stewart Pharmaceuticals NPV of Full-Scale
Production following Successful Test
- Note that the NPV is calculated as of date 1, the
date at which the investment of 1,600 million is
made. Later we bring this number back to date 0.
24Stewart Pharmaceuticals NPV of Full-Scale
Production following Unsuccessful Test
- Note that the NPV is calculated as of date 1, the
date at which the investment of 1,600 million is
made. Later we bring this number back to date 0.
25Decision Tree for Stewart Pharmaceutical
60 chance
40 failure
Now Date0
Date1
26Stewart Pharmaceutical Decision to Test
- Lets move back to the first stage, where the
decision boils down to the simple question
should we invest? - The expected payoff evaluated at date 1 is
The NPV evaluated at date 0 is
So we should test.
27Options
- One of the fundamental insights of modern finance
theory is that options have value. - The phrase We are out of options is surely a
sign of trouble. - Because corporations make decisions in a dynamic
environment, they have options that should be
considered in project valuation.
28What is Real Option Analysis?
- Real options exist when managers can influence
the size and riskiness of a projects cash flows
by taking different actions during the projects
life. - Real option analysis incorporates typical NPV
budgeting analysis with an analysis for
opportunities resulting from managers decisions.
29Real Options
- The Option to Expand/Growth
- Has value if demand turns out to be higher than
expected. - The Option to Abandon/shutdown
- Has value if demand turns out to be lower than
expected. - The Option to Delay/Investment timing options
- Has value if the underlying variables are
changing with a favorable trend.
30Discounted Cash Flows and Options
- We can calculate the market value of a project as
the sum of the NPV of the project without options
and the value of the managerial options implicit
in the project. - M NPV Real Option
- A good example would be comparing the
desirability of a specialized machine versus a
more versatile machine. If they both cost about
the same and last the same amount of time the
more versatile machine is more valuable because
it comes with options.
31The Option to Abandon Example
- Suppose that we are drilling an oil well. The
drilling rig costs 300 today and in one year the
well is either a success or a failure. - The outcomes are equally likely. The discount
rate is 10. - The PV of the successful payoff at time one is
575. - The PV of the unsuccessful payoff at time one is
0.
32The Option to Abandon Example
Traditional NPV analysis would indicate rejection
of the project.
33The Option to Abandon Example
Traditional NPV analysis overlooks the option to
abandon.
Success PV 575
Sit on rig stare at empty hole PV 0.
Drill
-
300
Failure
Sell the rig salvage value 250
Do not drill
The firm has two decisions to make drill or not,
abandon or stay.
34The Option to Abandon Example
When we include the value of the option to
abandon, the drilling project should proceed
35Valuation of the Option to Abandon
- Recall that we can calculate the market value of
a project as the sum of the NPV of the project
without options and the value of the managerial
options implicit in the project. - M NPV Opt
- 75.00 38.61 Opt
- 75.00 38.61 Opt
- Opt 113.64
36Illustrating an Investment Timing Option
- If we proceed with Project L, its annual cash
flows are 33,500, and its NPV is 6,190. - However, if we wait one year, we will find out
some additional information regarding output
prices and the cash flows from Project L. - If we wait, the up-front cost will remain at
100,000 and there is a 50 chance the subsequent
CFs will be 43,500 a year, and a 50 chance the
subsequent CFs will be 23,500 a year.
37Investment Timing Decision Tree
-100,000 43,500 43,500 43,500
43,500
50 prob.
-100,000 23,500 23,500 23,500
23,500
50 prob.
0 1 2 3 4
5
Years
- At k 10, the NPV at t 1 is
- 37,889, if CFs are 43,500 per year, or
- -25,508, if CFs are 23,500 per year, in which
case the firm would not proceed with the project.
38Should We Wait or Proceed?
- If we proceed today, NPV 6,190.
- If we wait one year, Expected NPV at t 1 is
0.5(37,889) 0.5(0) 18,944.57, which is
worth 18,944.57 / (1.10) 17,222.34 in todays
dollars (assuming a 10 discount rate). - Therefore, it makes sense to wait.
39Issues to Consider with Investment Timing Options
- Whats the appropriate discount rate?
- Note that increased volatility makes the option
to delay more attractive. For example - If instead, there was a 50 chance the subsequent
CFs will be 53,500 a year, and a 50 chance the
subsequent CFs will be 13,500 a year, expected
NPV next year (if we delay) would be - 0.5(69,588) 0.5(0) 34,794 gt
18,944.57 - 34,794/1.131631gt17222gt6190
40Factors to Consider When Deciding When to Invest
- Delaying the project means that cash flows come
later rather than sooner. - It might make sense to proceed today if there are
important advantages to being the first
competitor to enter a market. - Waiting may allow you to take advantage of
changing conditions.