Title: Project Management
1PROJECT MANAGEMENT
Dr. ANANDA KUMAR Professor Department of Mgt.
Studies Christ College of Engg.
Tech. Puducherry, India. Mobile 91 99443
42433 E-mail searchanandu_at_gmail.com
2- Unit 1
- Project Meaning classification importance
of project management An Integrated Approach
Project Portfolio Management System The Need
Choosing the appropriate Project Management
structure Organizational considerations and
project considerations steps in defining the
project project Rollup Process breakdown
structure Responsibility Matrices External
causes of delay and internal constraints.
3Project
- A project is a one-shot, time-limited,
goal-directed, major undertaking, requiring the
commitment of varied skills and resources. - A project is temporary in that there is a defined
start (the decision to proceed) and a defined end
(the achievement of the goals and objectives).
4Project Management
- PM is the application of knowledge, skills, tools
and techniques to a broad range of activities in
order to meet the requirements of the particular
project. - Project Management knowledge and practices are
best described in terms of their component
processes. - These processes can be placed into five Process
Groups Initiating, Planning, Executing,
Controlling and Closing.
5Project Management Constraints
Time Cost Scope
Manage these or they will manage you!
6Project Management Activities
- 1. Planning the work
- 2. Assessing and justifying risk
- 3. Estimating resources
- 4. Organizing the work
- 5. Acquiring human and material resources
- 6. Assigning tasks
- 7. Directing activities
- 8. Controlling project execution
- 9. Reporting progress
- 10.Analyzing the results based on the facts
achieved
7Project Life Cycle
Executing
Level of effort
Planning
Delivering
Defining
Start Time
End
Defining 1.Goal 2.Specifications 3.Tasks 4.Respons
ibilities
Planning 1.Schedules 2.Budgets 3.Resources 4.Risks
5.Staffing
Executing 1.Status reports 2.Changes 3.Quality 4.F
orecasts
Delivering 1.Train Customer 2.Transfer
documents 3.Release Resources 4.Lessons learned
8Classification of Project
- On the basis of Expansion
- On the basis of Magnitude of the resources to be
invested. - On the basis of Sector
- On the basis of Objective
- On the basis of productivity
- On the basis of nature of benefits
- On the basis of risk involved in the product
- On the basis of Economic life of the project
9- On the basis of Expansion
- Project expanding the capacity
- Project expanding the supply of knowledge
- On the basis of Magnitude of the resources to be
invested - Giant projects affecting total economy
- Big projects affecting at one sector of the
economy - Medium size projects
- Small size projects (depending on size,
investment impact)
10- 3. On the basis of Sector
- Industrial Project
- Agricultural project
- Educational project
- Health project
- Social project
- 4. On the basis of Objective
- Social Objective project
- Economic objective project
11- 5. On the basis of Productivity
- Directivity productive project
- Interactively productive project
- 6. On the basis of nature of benefits
- Quantifiable project
- Non-Quantifiable project
12- 7. On the basis of risk involved in the project
- High risks project
- Normal risks project
- Low risks project
- 8. On the basis of economic life of the project
- Long term project
- Medium term project
- Short term project
13Importance of Project Management
- Compression of the Product Life Cycle
- Global Competition
- Knowledge Explosion
- Corporate Downsizing
- Increased Customer Focus
- Rapid Development of Third world and Closed
Economies - Small Projects Represent Big Problems
14Project Management Today An Integrative Approach
- Integration of Projects with the Strategic Plan
- Integration within the Process of Managing Actual
Projects - Implement Strategies through Projects
15Customer
Integrated Management of Project
Environmental Analysis External
Internal Firm Mission, Goals, Strategies Prioriti
es
Projects
System
Environment Culture
Project Implementation
16The Technical Sociocultural Dimensions of the
Project Management Process
Socio Cultural Leadership Problem
Solving Teamwork Negotiation Politics Customer
Expectations
Technical Scope WBS Schedules Resource
Allocation Baseline Budgets Status reports
17Project Portfolio Management
Vision Mission Strategy Resource
Allocation Project Prioritization Performance
Tracking Needs Assessment Project
Proposals Project Deliverables
Enterprise Management
Portfolio Management
Project Portfolio
Executives Teams
Management
Project Management
18Project Portfolio Management PPM
- A collection of projects or programs and other
work that are grouped together to facilitate
effective management of that work to meet
strategic business objectives. - Portfolio Management is the middleware between
Strategic Planning and Project Delivery. - It means a systematic process of selecting,
supporting, and managing the firms collection of
projects. - Portfolio management ensures projects are
aligned with strategic goals appropriately. - It provides information to make better business
decisions.
19Project Portfolio Management System
- Portfolio management requires
- decision making
- prioritization
- review
- realignment
- reprioritization
20PPM Essentials
21Major Phases of PPM
- 1. Establish
- 2. Evaluate
- 3. Prioritize
- 4. Select
- 5. Manage
22Major Phases of PPM
-
No Revise Submit -
No - Reject -
-
yes - Cancelled
- Completed
Evaluate project alignment to the corporate
strategy
Project Proposal
Establish Portfolio strategy
Postponed
Prioritize project and hold pending funding
Manage Active projects On plan Off plan In
Trouble
Select a balanced portfolio using the
prioritized projects
23Major Phases of PPM
- 1. Proposed
- 2. Aligned
- 3. Prioritized
- 4. Selected
- 5. Active
- 6. Postponed
- 7. Cancelled
- 8. Completed
24Need for an Effective PPM System
- Problem 1 The Implementation Gap
- Problem 2 Organization Polities
- Problem 3 Resource Conflicts and Multitasking
25- Problem 1 The Implementation Gap
- Conflicts frequently occur among functional
managers and cause lack of trust. - Frequent meetings are called to establish or
renegotiate priorities. - People frequently shift from one project
to another, depending on current priority.
Employees are confused about which projects are
important. - People are working on multiple projects and
feel inefficient. - Resources are not adequate.
26- Problem 2 Organization Politics
- Politics exist in every organization and can
have a significant influence on which projects
receive funding and high priority. This is
especially true when the criteria and process for
selecting projects are illdefined and not aligned
with the mission of the firm. Project selection
may be based not so much on facts and sound
reasoning, but rather on the persuasiveness and
power of people advocating projects.
27- Problem 3 Resource Conflicts and Multitasking
- Most project organizations exist in a multi
project environment. This environment creates
the problems of project interdependency and the
need to share resources. - Resource sharing also leads to multitasking.
Multitasking involves starting and stopping work
on one task to go and work on another project,
and then returning to the work on the original
task. People working on several tasks
concurrently are far less efficient, especially
where conceptual or physical shutdown and startup
are significant.
28Choosing the Appropriate Project Mgt Structure
- Organization Considerations
- Project Considerations
291. Organization Considerations
- If an organization has both standard
products and projects, then a matrix arrangement
would appear to be appropriate. If an
organization has very few projects, then a less
formal arrangement is probably all that is
required. Temporary task forces could be created
on an as-needed basis and the organisation could
out-source project work.
301. Organization Considerations
- Organizing Projects within the Functional
Organisation - Organizing Projects within a Matrix Arrangement
- Organizing Projects within a Network organisation
31Organizing Projects within the Functional
Organisation
Delta manufacturing, inc. President
Finance Administration
Human Resources
Marketing
Procurement
Manufacturing
Engineering
Software Engineering
Electronics Engineering
Receiving Inspection
Purchasing
Design
Mechanical Engineering
Customer service
International Sales
Domestic Sales
Production Scheduling
Testing
Assembly
Fabrication
32Organizing Projects within a Matrix Arrangement
Zeta manufacturing inc. President
Human Resources
Finance
Director of Projects
Engineering
Manufacturing
Marketing
Project Admin.
Testing
Assembly
Mechanical engg.
Software engg.
Design Engg.
Customer Service
P A PM
1
2
1
2
1
2
P B PM
1
3
1
1
3
1
1
P C PM
2
1
2
2
33Organizing Projects within a Network organisation
Tool Die firm
Marketing Firm
Parts Supplies
Advertising firm
Mountain Bicycle
Manufacturer
Legal firm
Project Manager
Inventor
Bicycle Company
342. Project Considerations
- At the project level, the question is how
much autonomy the project needs in order to be
successfully completely. Hobbs and Menard
identify seven factors that should influence the
choice of project management structure - 1. Size of project
- 2. Strategic importance
- 3. Novelty and need for innovation
35- Need for integration (number of departments
involved) - Environmental complexity (number of external
interfaces) - Budget and time constraints
- Stability of resource requirements
36Defining the Project
- One of the best ways to meet the needs of
the customer major project stakeholders is to
use an integrated project planning and control
system that requires selective information. - Project managers who manage a single, small
project can plan and schedule the project tasks
without a formal planning and information system.
37Steps in Defining the Project
- Step 1 Defining the Project Scope
- Step 2 Establishing Project Priorities
- Step 3 Creating the Work Breakdown Structure
- Step 4 Integrating the WBS with the
Organization - Step 5 Coding the WBS for the Information
System
38Step 1 Defining the Project Scope
- Defining the project scope sets the stage for
developing a project plan. Project scope is a
definition of the end result or mission of your
project a product or service for your
client/customer. The primary purpose is to
define as clearly as possible the deliverable for
the end user and to focus project plans. - Many research clearly shows that a poorly defined
scope or mission is the most frequently mentioned
barrier to project success.
39Cont
- Before work on the project can be started, its
necessary to clearly define what the outcomes of
the project will be. This involves not only what
specifications and criteria the final project
must meet, but when it must be completed and what
the budget is. - Whats the objective?
- What are the expected, required, and desired
results? - How will success be measured?
- Whats the timeframe?
- What are the resource implications?
40Step 2 Establishing Project Priorities
- Quality and the ultimate success of a project are
traditionally defined as meeting and/or exceeding
the expectations of the customer and/or upper
management in terms of cost (budget), time
(schedule), and performance (scope) of the
project.
Scope
Quality
Time
Cost
41Cont
- The interrelationship among these criteria
varies. For example, sometimes it is necessary
to compromise the performance and scope of the
project to get the project done quickly or less
expensively. Often the longer a project takes,
the more expensive it becomes. However, a
positive correlation between cost and schedule
may not always be true. - Other times project costs can be reduced by using
cheaper, less efficient labor or equipment that
extends the duration of the project.
42Step 3 Creating the WBS
- Once the scope and deliverables have been
identified, the work of the project can be
successively subdivided into smaller and smaller
work elements. The outcome of this hierarchical
process is called the work breakdown structure
(WBS). The WBS is a map of the project. - Use of WBS helps to assure project managers that
all projects and work elements are identified, to
integrate the project with the current
organization, and to establish a basis for
control. Basically, the WBS is an outline of the
project with different levels of details.
43Hierarchical Breakdown of the WBS
Level Hierarchical
breakdown Description 1
Complete project 2
Major deliverable
3
Supporting deliverable
4
Lowest Mgt
responsibility level
Grouping of work
5
packages for
monitoring progress
and responsibility
Project
Deliverable
Sub deliverable
Lowest subdeliverable
Cost Account
Work package
44Step 4 Integrating the WBS with the
Organization
- An integral part of the WBS is to define the
organizational units responsible for performing
the work. In practice, the outcome of this
process is the organization breakdown structure
(OBS). The OBS depicts how the firm has
organized to discharge work responsibility. The
purpose of the OBS are to provide a framework to
summarize organization unit work performance,
identify organization units responsible for work
packages, and tie the organizational unit to cost
control accounts.
45Integration of WBS and OBS
Personal Computer prototype
Vendor, software, application
Disk storage units
Mouse, keyboard, voice
Microprocessor unit
External USB
Hard
Optical
ROM
Utilities
File
I/O
RAM
Read/write head
Chassis frame
Circuit board
Motor
46Step 5 Coding the WBS for the Information
System
- Gaining the maximum usefulness of a breakdown
structure depends on a coding system. The codes
are used to define levels and elements in the
WBS, organization elements, work packages, and
budget and cost information. The codes allow
reports to be consolidated at any level in the
structure. The most commonly used scheme in
practice is numeric indention.
47Project Rollup
- The work packages and cost accounts serve as a
database from which all other planning,
scheduling, and controlling processes are
coordinated. Cost accounts include one or more
work packages. Each work package has time,
budget, resource, responsibility, and control
points that can be used to track project progress.
48Work Package Estimates
- WP Description Final Version
Page 1 of 1 - WP ID 1.1.3.2
Project
PC proto - Deliverable Circuit Board
Date 9/29/xx - Original Unit Software
Estimator RMG - WP Duration 3 work weeks
Total Budget 265
49Project Planning
- Once the outcome of the project has been defined,
its important to develop a plan of what work
needs to be done, what resources are needed, who
will do it, and when. The level of detail needed
in the plan will be determined by the complexity
of the project and the number of people involved.
The plan will probably not be followed exactly
things will happen that lead to adjustments and
modifications.
50Steps for Project Planning
Identify Parameters / Constraints
Identify Hot Spots
Break the project into hunks, chunks, and bites
Write down the tasks in sequence
Identify who is responsible for each item
Determine when each task will be done
Determine the projected cost
51Planning Steps Answer
1. Identify parameters/constraints What are the requirements for quality /specifications, cost/budget/other resources, and time/schedule? Which of the three is highest priority?
2. Identify hot spots Where are the potential problems? How could these problems be addressed?
3. Break the project into hunks, chunks, and bites What are the major pieces of the project, the minor pieces that make up the major pieces, and the individual tasks within the minor pieces?
4. Write down the tasks in sequence What tasks can be done concurrently, or in parallel? What tasks cannot be done until others are completed?
525. Identify who is responsible for each item Do the project manager and team have the resources needed?
6. Determine when each task will be done Which tasks are required, and which may be just nice to have? How long will each task take? What are the start and finish dates, based on sequence and time to complete?
7. Determine the projected cost Based on the schedule, what will be the final cost?
53Process Breakdown Structure
- The WBS is best suited for design and build
projects that have tangible outcomes such as an
off-shore mining facility or a new car prototype.
The project can be decomposed or broken down
into major deliverables, subdeliverables, and
ultimately to work packages. - It is more difficult to apply WBS to less
tangible, process-oriented projects in which the
final outcome is a product of a series of steps
or phases. Here, the big difference is that the
project evolves over time with each phase
affecting the next phase.
54PBS for Software Development Project
- 1 Level
- Major phases
- 2 Level
- Activities
- 3 Level
- Activities
Software Development Project
Rollout
Analysis
Design
Construct
Test
Define user interface
Develop detailed design
Establish quality requirements
Develop technical design
Define application architecture
Design system interfaces
Design logical database structure
Define processing flow
55Responsibility Matrices
- In many cases, the size and scope of the project
do not warrant an elaborate WBS or OBS. One tool
that is widely used by project managers and task
force leaders of small projects is the
responsibility matrix (RM). - The RM (sometimes called a linear responsibility
chart) summarizes the tasks to be accomplished
and who is responsible for what on a project. In
its simplest form an RM consists of a chart
listing all the project activities and the
participants responsible for each activity.
56Responsibility Matrices
Task Richard Dan Dave Linda Elizabeth
Identify target customers R S S
Develop draft questionnaire R S S
Pilot-test questionnaire R S
Finalize questionnaire R S S S
Print questionnaire R
Prepare mailing labels R
Mail questionnaires R
Receive monitor returned questionnaires R S
Input response data R
Analyze results R S S
Prepare final report R S
57External causes of delay
- There are several reasons, including
socio-political, economic, technological, macro
and micro-global reasons, for the delay of
several projects according to the response of
several project managers. - Professional project managers need to identify
the real reasons in order to prevent such delays
in future. - The external constraints arise due to the
following reasons
58External causes of delay
- global macro-level government policies
influenced by social, economic, political,
regional or global pressures affecting currency
fluctuations, trade relations, foreign aid, etc.
Typical examples are India-china confrontation,
India-Pakistan disputes, Arab-Israel crises,
Iran-Iraq war etc. - Indian government policies
- import regulations
- panic taxation
- defense expenditure
59External causes of delay
- political situation
- inflation
- law and order problems
- natural disasters, like earthquakes, floods,
etc.
60Internal Contraints
- The internal constraints, which can be
anticipated, planned and controlled relate to the
programmes and policies of the company. Some of
the important causes for such restraints are
listed below. These can be broadly classified
into people, funds, and organisation. - The corporate culture and the style of leadership
are the key areas, as the project manager is not
appointed at the conception of the project and
is, therefore, not totally involved in the
formulation of objectives. The other internal
constraints may be listed as under
61Internal Constraints
- inappropriate choice of site
- disputes with local agencies
- inadequacy of foreign collaboration agreements
- lack of skilled workers
- technical incompetence
- inadequate project planning preparation
- change of scope because of government
regulations - lack of infrastructure of water and
electricity - poor monitoring and control etc.
62Project Management
63- Unit 3
- Project Evaluation under certainty Net Present
Value (Problems Case Study), Benefit Cost
Ratio, Internal Rate of Return, Urgency, Payback
Period, ARR Project Evaluation under
uncertainty Methodology for project evaluation
Commercial vs. National Profitability Social
Cost Benefit Analysis, Commercial or National
Profitability, social or national profitability. -
64Payback Period Method (PB)
- Payback period is defined as the length of time
required for the stream of cash proceeds produced
by an investment to equal the original cash
outlay required by the investment. - FORMULA
- Initial Investment in projects
- Payback period ------------------------
--- -
Annual cash inflow - It is the number of years required to recover the
investment. Incase of unequal cash inflow, it can
be found out by adding up the annual cash inflow
till the total is equal to the investment. Many
firms use the payback period as a decision
criterion because it is easy to calculate. Cash
inflow is the sum of net profit after tax and
depreciation which is a non-cash expense.
65Accounting Rate of Return or Average Rate of
Return ARR
- This method take into account the total earnings
expected from an investment proposal its full
life time. The method is called accounting rate
of return method, because it uses the accounting
concept of profit i.e., income after deprecation
and tax as criterion for calculation of return.
66Accounting Rate of Return or Average Rate of
Return
- Computation of A.R.R
- a.) Total income method
- Net Profit after dep Tax
- Accounting Rate of Return
--------------------------- x 100 -
Original investment scrap value - b.) Average investment method
- Net Profit after dep Tax
- Accounting Rate of Return
--------------------------- x 100 - Average investment
67- Average investment is again a dispute term. The
following four alternatives used - Original investment
- (i) Average investment
--------------------------- or - 2
- Original investment scrap value
- (ii)Average investment
--------------------------- or - 2
- Original investment scrap value
- (iii)Average investment
--------------------------- or - 2
- Original investment scrap value
- (iv)Average investment --------------------
------- Additional W.C scrap - 2
68Net Present Value NPV
- This method follows the DCF Technique and
recognizes the time value of money. It is an
index used to ascertain the economic worthiness
of the investment proposals. If the investment
i.e. cash outflow is made in the initial year,
then it is present value will be equal to the
amount of cash actually spent. If the cash
outflow is made in the second and subsequent year
also, its present value also should be found out
by applying the appropriate rate of interest
which is the firms cost of capital. It is the
minimum rate of return expected to be earned by
the firm on the investment proposals.
69Net Present Value NPV
- Similarly all the cash inflows (i.e. Net profit
after tax Depreciation) are also to be
discounted at the above rate in order to find out
the present value of cash inflows occurring in
the future periods. Then the net present value is
to be found out by subtracting the present value
of cash outflows from the present value of cash
inflows. It is defined as the difference between
the present value of cash outflow and present
value of cash inflows occurring in the future
periods over the entire life of the project.
70Net Present Value NPV
- ACCEPTANCE RULE
- If the NPV is positive or at least equal to zero,
the project can be accepted - NPV gt 0, the project is accepted
- NPV lt 0, the project is rejected
- NPV 0, the project is accepted or rejected on
non-economic considerations.
71Net Present Value NPV
- CALCULATION OF NPV
- NPV
- Where NPV Net present value
- R Cash inflows
- K Cost of capital
- I Cash out flows
72Internal Rate of Return IRR
- Internal rate of return is the rate of which is
the sum of discounted cash inflows equals the sum
of discounted cash outflows. In other words it is
the rate at which equals the aggregate discounted
cash inflow with the aggregate discounted cash
outflows. It is the rate of discount which
reduces the net present value of an investment to
zero. It can be stated in the form of a ratio
73Internal Rate of Return IRR
- Cash inflows
- IRR --------------------------- 1
- Cash out flows
- a) Where cash inflows are uniform the internal
rate of return can be calculated by locating the
factor in annuity table. The factor is calculated
as follows. - F I / C
- Where
- F factor to be located in annuity table
- I Investment or cash outflow
- C Cash inflows per year
74Project Evaluation under Uncertainty
- Investment decisions have to be based on the
knowledge of future expectations, and hence are
spun around forecasts, estimates and projections.
Generally, there is an irresistible urge in the
estimator or planner to invest the projections
with a certain degree of definiteness which is
most unlikely in a dynamic business setting. It
should be appreciated that even the defined
estimates and defined return analysis call for
continuous and close review for revisions, if
necessary.
75Convert Uncertainties into Calculated Risks
- Future always holds surprises. Informed
decisions based on comprehensive study of
relevant data and trends are sound starts for
successful projects, but even these considered
assumptions and anticipations have to be
constantly reviewed and revalidated or modified,
as the case may be, to enable prompt corrective
actions during the project implementation and
operation phases. - Assumptions about political and economic
conditions that are likely to prevail, about the
market prospects and competitors strategies,
about customer preferences and technology
developments.
76Analysing Uncertainty
- Break-even analysis
- Sensitivity analysis
- Probability analysis
771. Break-even Analysis
- Break-even point (BEP) of production and/or sale
is that level at which there is neither profit
nor loss. Break-even analysis helps to determine
the lowest production and/or sales level at which
the project has to operate in order to keep out
of financial trouble. - The break-even point can get defined in terms of
the percentage of capacity utilization resulting
in given output quantity, or as a volume or sales
revenue. It can be further interpreted in terms
of the maximum purchase price for inputs or
minimum selling price for outputs.
782. Sensitivity Analysis
- Sensitivity analysis can be employed to examine
how the net present value or the value of any
other efficiency criterion changes with
variations in the value of any variable, such as
sales volume, selling price, unit variable cost.
The impact can be expressed in terms of the
absolute change in the efficiency criterion
divided by a given percentage, or absolute change
in a given variable or a given set of variables. - If it is observed that reduction in selling price
will have serious effect on contribution or on
the value added, price emerges as a sensitive
factor and great care needs to be taken in
arriving at pricing decisions in regard to the
products of the project.
793. Probability Analysis
- In analysing probability, we are looking at the
frequency of occurrence of an event. The number
of different ways that the specific event can
occur is expressed as a ratio of the total number
of possible outcomes. Probability analysis is
based on the identification of the possible range
of each variable, and attaching a probability of
occurrence for each possible value of the
variables within this range.
80Causes of Uncertainty
- Inflation
- Changes in technology
- Problems in attaining rated capacity
- Under-estimation of investment cost and time
factors.
81Project Appraisal Process
- Small projects get assistance from a single
institution, and in the case of larger projects,
the institutions extend assistance jointly
through syndication. - - Single Institution Assistance
- - Loan Syndication
821. Single Institution Assistance
- Application is received from the promoter
- The institution deputes a financial expert and
a technical expert to carry out the project
appraisal - After a preliminary review, the team submits
its report to the management, recommending
acceptance or rejection.
83Project Management UNIT 4
84UNIT 4
Developing a project plan Developing the project
network constructing a project network
(Problems) PERT CPM crashing of project
network (Problems - Case Study) resource
leveling and resource allocation how to avoid
cost and time overruns Steps in Project
Appraisal Process Project Control Process
control issues project audits the project
audit process project closure team, team
member and project manager evaluations.
85Steps to Creating a Project Plan
- Explain the project plan to key stakeholders and
discuss its key components. - Define roles and responsibilities
- Hold a kickoff meeting
- Develop a Scope Statement
- Develop scope baseline
- Develop the schedule and cost baselines
- Create baseline management plans
- Develop the staffing plan
- Analyze project quality and risks
- Communicate
861. Explain the project plan to key
stakeholders One of the most misunderstood terms
in project management, the project plan is a set
of living documents that can be expected to
change over the life of the project. Like a
roadmap, it provides the direction for the
project. And like the traveller, the project
manager needs to set the course of the project,
which in project management terms means creating
the project plan.
87- 2. Define roles and responsibilities.
- Not all key stakeholders will review all
documents, so it is necessary to determine who on
the project needs to approve which parts of the
plan. - Hold a kickoff meeting.
- The kickoff meeting is an effective way to
bring stakeholders together to discuss the
project. It is an effective way to initiate the
planning process. It can be used to start
building trust among the team members and ensure
that everyones idea are taken into account.
Kickoff meetings also demonstrate commitment from
the sponsor for the project.
884. Develop a Scope Statement The Scope Statement
is arguably the most important document in the
project plan. Its the foundation for the rest
of the project. It describes the project and is
used to get common agreement among the
stakeholders about the scope. The scope
statement clearly describes what the outcome of
the project will be. It is the basis for getting
the buy-in and agreement from the sponsor and
other stakeholders and decreases the chances of
miscommunication.
89- 5. Develop Scope Baseline
- Once the deliverables are confirmed in the scope
statement, they need to be developed into a work
breakdown structure (WBS), which is a
decomposition of all the deliverables in the
project. - Develop the schedule and cost baselines.
- Identify activities and tasks needed to produce
each of the work packages, creating a WBS of
tasks, identify resources for each task, estimate
how long it will take to complete each task,
estimate cost of each task using an average
hourly rate for each resource.
907. Create baseline management plans. Once the
scope, schedule, and cost baselines have been
established, you can create the steps the team
will take to manage variances to these plans.
All these management plans usually include a
review and approval process for modifying the
baselines. 8. Develop the
staffing plan. The staffing plan is a chart that
shows the time periods, usually month, quarter,
year, that each resource will come onto and leave
the project. It is similar to other project
management charts, like a Gantt chart, but does
not show tasks, estimates, begin and end dates,
or the critical path.
91- Analyze project quality and risks.
- - project quality
- - project risks
-
- 10. Communicate.
- Once the project plan is complete, it is
important not just to communicate the importance
of the project plan to the sponsor, but also to
communicate its contents once its created.
92Developing a Project Network
- Project Network is a tool used for planning,
scheduling and monitoring project progress. - It is a graphical flow chart of the project job
plan. - Critical path should be identified.
- It is used to take decision concerning project
time, cost and performance. - The network depicts the project activities that
must be completed, logical sequences and their
inter dependencies.
93From Work Packages to Network
- An activity include one or more work packages.
- These activities are placed in a sequence that
provides for orderly completion of the project. - Network are built using nodes and arrows.
- Nodes Activity
- Arrow Project flow
- This network depicts the actual project flow.
94Difficulties in Network Process
- Integrating work packages and the network
represents a point where the management often
fails. - 1. Different groups are used to define work
packages. - 2. WBS is poorly constructed.
95Constructing a Project Network
- 1. Activity An activity is an element of the
project. It usually represents one or more tasks
from a work package. - Merge Activity An activity that has more than
one activity immediately preceding it. - 3. Parallel Activity Activities that can take
place at the same time -
96- Burst Activity An Activity that has more one
activity immediately following it - Path Sequence of connected, dependent
activities. - Critical Path Longest path through the network.
- Event It is a point in time when an activity is
started or completed.
97Activity-On-Node (AON)
- In activity-on-node (AON) network, the node
depicts an activity of a project. - The AON network can be computed using
- 1. Forward Pass - earliest time
- 2. Backward Pass - latest time
A
C
B
98Activity-On-Node (AON)
- 1. Forward Pass
- It starts with the first project activity, trace
through all the activities and end with the last
project activity. - Backward Pass
- It starts with the last project activity, trace
backward on each path to find late start and late
finish of each activity.
99Activity-On-Arrow (AOA)
- In AOA network, the arrow depicts the activity of
the project and which is connected by start event
node and end event node.
A -
- Here dummy activities are introduced in case of
activities that are parallel and have same start
and end node.
-
X
D -
C -
- A
-
B
1
2
3
5
1
2
4
100Difference in PERT CPM
- PERT is appropriate where time estimate arte
uncertain in the duration of activities as
measured by optimistic time, most likely time,
and pessimistic time, where as CPM is good when
time estimates are found with certainty. CPM
assumes that he duration of every is constant and
therefore every activity is critical or not. - PERT is concerned with events, which are the
beginning or ending points of operation while CPM
is concerned with activities.
101- PERT is suitable for non-repetitive projects
while CPM is designed for repetitive projects. - PERT can be analyzed statistically whereas CPM
not. - PERT is not concerned with the relationship
between time and cost, whereas CPM established a
relationship between time and cost is
proportionate to time.
102Resource Allocation Leveling through Network
Resources allocation means how much resources be
diverted to the project concerned day after day
as the project progresses.
103Days B C D E F G H I Total Labour Needs
1 3 3
2 3 3
3 3 3
4 3 3
5 3 3
6 3 3
7 3 3
8 3 3
9 5 2 7 5 19
10 5 7 5 17
11 3 7 5 15
12 2 5 4 11
13 5 4 9
14 3 3
15 3 2 5
Total Labour days activity 24 10 2 3 21 8 25 10 103
104Project Control Process
Control is the process of comparing actual
performance against plan to identify deviations,
evaluate possible alternative course of actions,
and take appropriate corrective action.
105Steps in Project Control Process
- Setting a baseline plan
- Measuring Progress and Performance
- Comparing plan against actual
- Taking action
106Project Audit
Professional management of project needs a
methodology to carry out a regular check as to
whether the project is progressing as scheduled,
in scope and in time. In other words, a good
system of project audit will go a long way in
facilitating prompt and effective project
implementation. Project audit as a formal and
systematic examination of the performance of an
ongoing project as compared to its requirements.
It involves measurement against predefined and
relevant standards.
107Objectives of Project Audit
- Creating awareness among the project staff of
the types and magnitude of the problems that are
likely to be encountered in completing the
project and producing quality products, in
planned volume and at competitive costs. - Providing a clean picture, from time to time,
of the actual status of the project. - Prompt identification of the factors that
might cause product quality problems or lead to
time and/or cost overruns. - Timely spotting of a variety of generic
problems that are associated with execution of
projects.
108- Enabling the creation of a good information
base for a proper estimation and costing of the
project. - Assisting in the establishment of appropriate
standards and system and recommending suitable
work techniques - Identifying the specific training needs with
references to the project tasks
109Process of Project Audit
1. Initiation and Staffing 2. Data Collection
and Analysis 3. Reporting a. Classification
of project b. Analysis of information
gathered c. Recommendations d. Lessons
Learned e. Appendix f. Summary Booklet 4.
Project Closure 5. Closure Decision
110Project Closure
The project manager is kept extremely busy near a
projects end, monitoring its progress and
preparing for shutdown. When walking about and
visiting the workstations, he or she must
re-emphasize the need for good communication
among task leaders encourage the give and take
that supports the internal customer principle be
attentive to the project timetable actively help
task leaders get their tasks started and
completed on time monitor the Gantt chart and
ass some original estimates overrun , alert
downstream task leaders to the scheduling changes.
111Steps in Closing a Project
- Getting client acceptance of deliverables
- Ensuring that all deliverables are installed
- Ensuring that the documentation is in place
- Getting client sign-off on final report
- Conducting the post-implementation audit
- Celebrating the success
112Project Team
The project team comprises of section heads of
production, electrical and mechanical who are
looking after the activities of their respective
wings. The project team is like cricket team
where we could find players adept in bowling,
batting and fielding with the result all the
players would put their accomplishing the
objective of the team. For any project, success
could be attributed to the able support of all
the players and the project manager would done
the role of a captain of the cricket team or of a
captain of ship.
113Promoting Teamwork Through Planning
A Primary rule of planning is that those
individuals who must implement the plan should
participate in preparing it. Yet leaders often
plan projects by themselves, then wonder why
their team members seem to have no commitment to
the plans. All planning requires some estimating
for example, how long a task will take, given
certain resources.
114Team Issues
- Clarifying the Teams Mission, Goals and
Objectives - Defining roles and responsibilities
- Working out procedures
- Managing interpersonal relationships
115Project Evaluation
Project Evaluation appraises the progress and
performance of a job and compares it to what was
originally planned. That evaluation provides the
basis for management decisions on how to proceed
with the project. The evaluation must be
credible in the eyes of everyone affected or
decisions based on it will not be considered
valid.
116Project Management UNIT 5
117- Unit 5
- Managing versus leading a project - managing
project stakeholders social network building
(Including management by wandering around)
qualities of an effective project manager
managing project teams Five Stage Team
Development Model Situational factors affecting
team development project team pitfalls.
118MANAGING VS LEADING PROJECT
- HOW TO MANAGE A LEADING PROJECT
- 1. Define the scope.
- What is it you are supposed to accomplish by
managing this project.
- What is the project objective.
- 2. Determine available resources.
- what people, equipment, and money will de
available to you to achieve the project objective.
119- 3. Check the timeline.
- When does the project have to be completed. If
you decide to use overtime hours to meet the
schedule, you must weight that against the
limitations of your budget. - 4. Assemble your project team.
- Get the people on your team together and start a
dialog. They are the technical experts.
120- 5. List the big steps.
- What are the major pieces of the project. If you
dont know, start by asking your team. - 6. List the smaller steps.
- List the smaller steps in each of the larger
steps.
Again, it usually helps you
remember all the steps if you list them in
chronological order.
121- 7. Develop a Preliminary Plan.
- Assemble all your steps into a plan.
- 8. Create your baseline plan.
- Get feedback on your preliminary plan from your
team and from any other stakeholders. Make
any necessary adjustment to the preliminary plan
to produce a baseline plan.
122- 9. Document Everything.
- Every time you change from your baseline plan,
write down what the change was and why it was
necessary. Every time a new requirement is added
to the project write down.
- 10. Keep everyone inform.
- Keep all the project stakeholders inform of
progress all along. Let them know of your success
as you complete each milestone, but also inform
of problem as soon as they come up. If also keep
you team informed.
123PROJECT MANAGEMENT STAKEHOLDER
- A stakeholder (in Project Management terms) is
anyone who's affected and who can affect, in one
way or another, the project. - Stakeholder (corporate), a person, group,
organization, or system who affects or can be
affected by an organization's actions - A person, group or organization that has interest
or concern in an organization. - Some example of key stakeholder are creditors,
directors, employees, government (and its
agencies),owner (shareholders), suppliers, unions
and the community from which the business draws
its resources.
124Managing Stakeholders 6 Steps to Success
- - Identify
- - Nominate
- - Feel
- - Observe
- - Review
- - Manage
125- Identify
- A stakeholder is anyone who has a vested interest
in the project someone who wants it to succeed
but equally someone who doesnt. You cant start
managing stakeholders until you know who they
are. Who are the main groups or departments
affected by your project? Stakeholders can also
be external to your organisation like the
government and third party providers as well.
The identification exercise shouldnt be done in
a vacuum you wont be able to complete the list
yourself, so get your project team involved too.
126- Nominate
- In each groups you have identified pick someone
to be the key individual. Choose carefully! You
may find that key people nominate themselves,
which makes your role easier it is better to
work with people who want to be involved than
those who you have to drag into the project.
Your key, nominated stakeholders should ideally
be people who are directly affected, with enough
authority to make decisions about things that
touch their departments. They are the person who
you will use to channel communication back to
their group.
127- Feel
- Begin to analyse the attitudes of the people who
have been identified as your key stakeholders
those named individuals who represent each
stakeholder group. Contact them and explain
about the project. Get them onboard and coming
to project meetings if necessary. All this will
help you understand how they feel about the work
you are doing. Do they support the project? Or
would they rather it was stopped now? Are they
ambivalent? This group can often be the hardest
to manage effectively. Your initial stakeholder
analysis is now complete.
128- Observe
- Having established where your key stakeholders
sit in relation to the project you can start to
influence their attitudes. The aim is to watch
people over time, and help them move towards a
positive way of thinking a way that will help
you achieve your aims. Keep a close eye on
people as their opinions will swing between
positive and negative over the life of a
project. A one-off analysis exercise is never
enough you have to continually monitor how
people are reacting and manage accordingly.
129- Review
- People and job roles change. So do projects.
The person who put themselves forward to
represent the marketing team six months ago may
not be the right person today. If you notice
that their influence is slipping away, or they
are less inclined to come to meetings or respond
to emails, then ask them if they still want to be
involved. If they say no, they could suggest
someone else who would be a relevant addition to
the team. Make sure you brief any new
stakeholder representative on their roles and
responsibilities, decisions in the pipeline and
what decisions you will expect of them in future.
130- Manage
- The last step is to monitor and manage your
stakeholders and their expectations as the
project progresses not just at the outset and
when you need something from them. Put a note in
your diary to give your key stakeholder
representatives a quick call every now and then
just to keep them up to date. This will help
promote the project and also ensure the
stakeholder concerned is mindful of the work
being done. It can also help build your
reputation as an excellent project manager! At
the end of the project, thank them and manage
them out of the team.
131Social Network Building
- Social network is to provide a way for people to
communicate and share information with others
based on different types of networks. The
networks are typically centered on some sort of
relationship type. LinkedIn, for example,
focuses on building a professional network of
colleagues, former co-workers, and other
work-related relationships. Face book, on the
other hand, is more open and allows for a variety
of networks, such as families, schools,
businesses, causes, groups, cities, or some other
- category of relationship.
132How does Social Network have to do with project
management?
- Well, to start with, projects require project
teams and teams are a form of relationship. - In the same way that Face book organizes
networks on a common cause, a project organizes a
team on a common cause e.g. to complete the
project on time and under budget. - The same people that use Face book or Twitter
at home are the same team members that come to
work every day, want the same thing that a social
networking site provides. - They want to be recognized for their
accomplishments, feel like their contributing to
the cause, and be able to collaborate with their
work buddies.
133How social network helps to manageprojects
- Networks could be organized around projects and
status updates and photos could be related to the
project. - Time could be easily entered, project status
quickly reported, and everything automatically
submitted to update the project schedule,
executive reports, and account for the resources
needed to complete the project. - Project and team collaboration would be simpler
and would focus on the completing the tasks at
hand. - Conversational information would provide
additional insight into the true status of the
project and team members would be recognized by
their peers for a job well done.
134LIMITATIONS
- Face book, LinkedIn, Twitter, and other social
networking sites, as great as they are, dont
provide the tools needed to effectively manage
projects. - Executives cant use Face book to organize
multiple projects, identify potential risks, and
manage resources. - Project managers cant simply post an update or
send out a Friend Request to keep projects on
time and under budget. - Managers need a robust tool that allows them to
plan projects, identify tasks, monitor schedules,
allocate resources, manage documents, improve
processes, collaborate with co-workers, and
manage the thousands of other little tasks needed
to successfully complete a project.
135Project quality management
- Project quality management includes the process
required to ensure that the project satisfies the
needs for which it is undertaken. - PQM includes all the activities of the overall
management function that determine the quality
policy, objectives, and responsibilities and
implement them within the quality system.
136Means of Implementation of PQM
- Quality Planning
- Quality Assurance
- Quality Control
- These processes interact with each other as
well as with the processes of other knowledge
areas - Each process involves an effort of one or more
individual or group of individuals based on the
need of the project. - Each process occurs at least once in every
project phase during the project life cycle.
137- Quality Planning
- Quality Planning is identifying which quality
standards are relevant to the project and
determining how to satisfy them. - Quality Assurance
- Quality assurance is evaluating the overall
project performance on a regular basis to provide
a confidence that the project will satisfy the
relevant quality standards.
138- Quality Control
- Quality Control is the monitoring of specific
project results to determine if they comply with
the relevant quality standards and identifying
ways to eliminate causes of unsatisfactory
performance.
139 - 1- INPUTS
- -work results
- -quality management plan
- Operational definitions
- checklists
- 2- TOOLS AND TECH.
- inspection
- Control charts
- Pareto diagrams
- Statistical sampling