Potential Water Supply to Morupule B - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Potential Water Supply to Morupule B

Description:

... the recommendations of the National Water Master Plan (NWMP) of 1992 is in two parts ... This was the biggest water supply scheme ever embarked on in Botswana ... – PowerPoint PPT presentation

Number of Views:69
Avg rating:3.0/5.0
Slides: 16
Provided by: btshe
Category:

less

Transcript and Presenter's Notes

Title: Potential Water Supply to Morupule B


1
Potential Water Supply to Morupule B
  • PHAKALANE GOLF ESTATE
  • 04 DECEMBER 2008
  • PRESENTED BY
  • NGINANI MBAYI
  • TECHNICAL SERVICES DIRECTOR
  • WATER UTILITIES CORPORATION

2
Introduction
  • The North South Carrier Water Supply Scheme (NSC)
    which is a direct result of the recommendations
    of the National Water Master Plan (NWMP) of 1992
    is in two parts
  • Phase I which is currently in operation
  • Phase II which is at conceptual design stage
  • The objective of the scheme is to transfer water
    from the available water resources in the north
    to the bigger demand centers in the south of the
    country

3
Major Dam Sites
4
POTENTIAL DEMANDS ON NSC SOURCES
5
NSC I
  • This was the biggest water supply scheme ever
    embarked on in Botswana
  • It comprises of Letsibogo Dam (100MCM capacity),
    360km pipeline, 3 pumping stations, 3 break
    pressure tanks and 3 treatment plants.
  • The treatment plants are at Palapye, Mahalapye
    and Mmamashia
  • The scheme has the potential to transfer 120Ml/d
    or 44MCM per annum of water from the north
  • However the sustainable yield of Letsibogo Dam at
    70 Ml/d is a limiting factor
  • The scheme, implemented at a cost of P1.5 billion
    at the time, was commissioned in August 2000
  • NSC I was primarily earmarked to supply water to
    the Greater Gaborone area (76 of the total
    demand in 2035) with supply to demand centres of
    Palapye and Mahalapye along the route.

6
(No Transcript)
7
NSC I Operational Challenges
  • After completion, the scheme experienced
    intermittent outages
  • Two pipeline materials were adopted, Glass
    Reinforced Polyester (GRP) (220 km) and welded
    Steel (140 km)
  • Problems were experienced largely on the GRP
    section in couplings and rocker pipes adjacent to
    chambers
  • Outages are fairly frequent lasting up to 5 days
    before repairs
  • While the scheme was primarily earmarked to
    supply water to the greater Gaborone Area which
    includes Gaborone, Lobatse, Tlokweng
    Mogoditshane, Ramotswa, Mochudi as well as the
    villages of Palapye and Mahalapye, additional
    demand centres of Serowe, Kanye and Molepolole
    will be included in due course due to severe
    water shortages there.

8
Morupule Water Demand Node
  • Water demand projections from NSC is based on a
    50 conjunctive use with other sources such as
    groundwater.
  • The demand projections cater for both Morupule
    Colliery and Power Station.
  • The demand projections are estimated at a maximum
    of 2.75 Mm³/annum.
  • The drawoff will initially start off with
    construction of water, which is relatively small,
    and picking up during production from 2.42
    Mm³/annum in 2014 until it reaches the maximum of
    2.75 Mm³/annum in 2020 and continues at this
    level.

9
  • Discussions with Morupule Colliery and BPC have
    been held with regard to their respective water
    demands.
  • It appears the allocated 2.75 Mm³/annum will meet
    their requirements.

10
NSC PIPELINE PROFILE AND FAILURE POINTS2000-2008
11
NSC I Maintenance Issues
  • A 15 year maintenance guarantee was adopted to
    allow for extended support largely to the new GRP
    pipe material.
  • This arrangement has not been completely
    beneficial to WUC
  • The scheme was shutdown for major maintenance in
    June 2006 and several couplings were replaced
  • The scheme was subsequently used to circumvent
    the severe drought of 2005/2006 when the level of
    Gaborone reached its record lowest of 16
  • Another shutdown was done in June 2007 primarily
    to install additional line valves so as to
    minimize water losses during pipe repairs
  • NSC I availability has been estimated to be 70
    excluding the periods of planned shutdowns.
  • Maintenance of NSC I has todate cost P12 million

12
NSC II
  • The NWMP projected water demands up to 2035 are
    due to exceed the current supply capacity of NSC
    I in the short to medium term
  • The north eastern dams are the only source with
    sufficient capacity to meet additional demand
  • Government decided that the transfer capacity of
    NSC II should be 45MCM per annum independent of
    design horizon
  • It has been demonstrated that the transfer of
    45MCM per annum under NSC II over and above that
    of NSC I is adequate to meet forecast demand to
    the year 2035
  • The conceptual design of NSC II allows for the
    injection of ground water from Khurutshe(Masama)
    and Palla Road well fields. These are planned as
    standby resources.

13
NSC II Continued
  • NSC II sources will include Shashe dam, Letsibogo
    dam and the future Dikgatlhong dam which is
    scheduled for completion in 2012.
  • NSC II will generally follow the same route as
    NSC I but will be operated independently.
  • Due to the NSC I experiences, it was decided that
    Steel or Ductile Iron will be the preferred
    pipeline materials
  • The estimated construction cost of NSC II is P3.6
    billion
  • Completion of the scheme is anticipated to be end
    of 2012

14
Conclusion
  • Based on the availability of both NSC I and II,
    water supply to Morupule B can be met

15
  • I thank you for your attention
Write a Comment
User Comments (0)
About PowerShow.com