Project Management: Resource Factors - PowerPoint PPT Presentation

About This Presentation
Title:

Project Management: Resource Factors

Description:

Optimistic completion times. Most likely completion times ... Over Allocation of Resources. More resources loaded onto an activity than are available ... – PowerPoint PPT presentation

Number of Views:68
Avg rating:3.0/5.0
Slides: 26
Provided by: TOber
Category:

less

Transcript and Presenter's Notes

Title: Project Management: Resource Factors


1
Project ManagementResource Factors
  • November 8, 2001
  • MBA 253
  • The Pegasus Group
  • Mario Rosso
  • Phil Randolph

2
Basic Resource/Project Management Tools
  • Gantt Charts
  • Program Evaluation Review Technique
  • PERT
  • Critical Path Method
  • CPM

3
Gantt Charts
  • Developed in 1917 by Henry L. Gantt
  • Purpose to better understand and depict the
    progress of an organization in attaining certain
    objectives.
  • Primarily used to depict how time is utilized
  • Depicts start and end dates of activities as well
    as the duration of the entire project
  • Depicts how activities are interrelated

4
Gantt Charts
5
PERT
  • Requires project planners to coordinate the
    entire project in terms of activities and
    milestones
  • Each activity contains
  • Expected beginning and end dates
  • Duration of the activity (number of days)
  • Resource usage for each activity
  • Personnel requirements
  • Equipment requirements

6
PERT-Calculating Expected Times for completion
of activities
  • Requires predicting
  • Optimistic completion times
  • Most likely completion times
  • Pessimistic completion times
  • O 4M P te
  • 6
  • If O6weeks, M8weeks, and P16weeks then
  • 6 32 16 te 9 weeks
  • 6

7
PERT
  • Once estimates are created a PERT chart can be
    created depicting how the activities relate in
    terms of respective time estimates, sequence of
    execution, and relative resource consumption
  • At this point, adjustments can be made through
    CPM to ensure proper functioning of the project

8
PERT
9
CPM
  • Allows project planners to identify which path
    along either the Gantt or PERT chart determines
    the overall length or duration of the project
  • Determines which activities are critical to
    complete the project on time
  • Determines which activities can sustain reduced
    resource input and longer durations

10
CPM
  • The path containing activities with the longest
    durations is the Critical Path
  • Critical activities must be closely monitored as
    any delays will increase the duration of the
    entire project
  • Resources can be diverted from other non-critical
    activities to critical activities to ensure
    proper completion or to shorten the time of the
    project.

11
PERT and CPM
12
Resources Project Management Objectives
  • Goal of project management
  • Reduce overall duration
  • Maximize usage of resources
  • Traditional project management only considered
    time factors
  • The availability and allocation resources must be
    considered if a project manager is to gain
    control of a project and see it to its optimal
    conclusion.

13
Resource Management
  • The planning, allocating and scheduling of
    resources to tasks, generally including manpower,
    machine (plant and equipment), money, and
    materials.
  • Resource Management typically covers resource
    allocation and its impact on schedules and
    budgets, as well as resource leveling and
    smoothing.

14
Resources
  • Money
  • Manpower
  • Machine (equipment)
  • Materials

15
Categories of Resources
  • Renewable
  • Constrained on a day-to-day basis
  • Ex. Labor
  • Non-Renewable
  • Constrained to a particular project
  • Ex. Raw materials
  • Doubly Constrained
  • Limited to a single project allocated on a
    day-to-day basis
  • Ex. Cash

16
Resource Allocation
  • Assignment of people, equipment, facilities, or
    materials to a project
  • Projects cannot be completed on schedule if
    adequate resources are not provided
  • Key task for project manager
  • WBS

17
Work Breakdown Structure
  • Defines activities and resources required to
    accomplish a project
  • Planning tool
  • Helps compare actual to baseline

18
(No Transcript)
19
(No Transcript)
20
The Resource Allocation Problem
  • Determining optimal trade-offs between
  • Available resources
  • Start dates
  • Durations of project activities
  • If time and cost/resources are fixed, PM loses
    ability to make trade-offs

21
Resource Loading
  • Calculate how much each task needs of each
    resource for the activitys duration
  • PM must ensure resources are available in the
    required amounts when needed
  • Problem occurs when resources are under or over
    allocated

22
Over Allocation of Resources
  • More resources loaded onto an activity than are
    available
  • Typical in environments with multiple projects
    and/or activities drawing from same resource pool
  • Requires trade-offs be made
  • Crashing a project
  • Adding additional resources to an activity to
    expedite it

23
Resource Leveling
  • Rescheduling activities so resource requirements
    do not exceed resource limits
  • Project completion date can move out in the
    process
  • Shift activities with float to reduce variations
    in resource loads
  • Promotes a smoother distribution of resources

24
Resource-Constrained Scheduling
  • Scientific method for optimizing resource
    allocation
  • Heuristic
  • rules of thumb
  • Optimization
  • Mathematical/Linear Programming

25
Thank you for your time
Write a Comment
User Comments (0)
About PowerShow.com