Title: IRIS Standard
1IRIS Standard
- Zusatzforderung
- zur
- DIN EN ISO 9001 2000
Juli 2006
2IRIS - Zusatzforderungen
- 4.3 Knowledge management
- Best practice shall be documented and regularly
- updated.
- Note, this can include
- gt Design rules
- gt Return of experience after a project
- gt Methods / Manufacturing Engineering standards
Juli 2006
3IRIS - Zusatzforderungen
- 4.4 Management of multi site projects
- In the case that a project involves multiple
sites, an - appropriate Business Management System (e.g.
Project - Quality Plan) shall be implemented for
(operational - interfaces, communication channels, work split,
applicable - Procedures).
- Cross site process efficiency shall regularly be
assessed.
Juli 2006
4IRIS - Zusatzforderungen
- 5.3 Quality policy
- The organisation shall establish and update at
least - annually a Business Plan, with covers at a
minimum the - following topics Railway Industry activities,
company - Misson and Vision, SWOT, Market and product
strategy - including obsolescence, Make or Buy strategy,
company - capacity,developement plans of new product /
process, - business obejectives
Juli 2006
5IRIS - Zusatzforderungen
- 5.5.1 Responsability and Authority
- Roles and responsabilities for all processes
having an - impact on customer satisfaction (including RAMS
and - special processes) shall be described.
- Owernship of business processes shall be defined.
Juli 2006
6IRIS - Zusatzforderungen
- 5.5.2 Management Representative
- All shifts shall be staffed with personnel in
charge of, or - hold delegated responsabilty for ensuring product
quality
Juli 2006
7IRIS - Zusatzforderungen
- 5.5.3 Internal Communication
- The organization shall establish a communication
system - from management to ist personal, as a minimum
- policy, mission and vision, company performance,
- customer related issues
Juli 2006
8IRIS - Zusatzforderungen
- 5.5.4 Customer Relationship Management
- Top management shall appoint a member of
management - who, irrespective of other responsabilities,
shall have - responsability and authority that includes
- processes needed to customer satisfaction are
established, implemented and maintained - reporting to top management on the performance of
these processes - promotion of awareness of customer satisfaction
throughout the organisation
Juli 2006
9IRIS - Zusatzforderungen
- 5.6 Management Review
- Planned intervals shall not exceed 12 months.
- 5.6.2 Review Input
- Key issues from previous project reviews
- Analysis of actual and potential field-failures
- KPI for customer on time delivery performance
- KPI customer non conformities for the entire life
cycle
Juli 2006
10IRIS - Zusatzforderungen
- 6.2.2.1 Product design skills
- The organisation shall ensure that personnel with
the - responsability for product design have the
necessary - compentence.
- Applicable tools and techniques shall be
identified
Juli 2006
11IRIS - Zusatzforderungen
- 6.2.2.2 Training
- The organization shall establish and maintain
documented procedures for identifying and
planning training needs - Output of Knowledgemanagement activities (see
section 4.3) shall taken into consideration as an
input to training planning - Personal performing specific assigned tasks (e.g.
special processes) shall be qualified. A system
shall be in place to maintain and upgrade the
qualifications of such personal. - Appropriate rules shall apply for temporary
workers and new comers. - Critical activities affecting the product quality
and safety shall be identified - Personal whose work can affect quality and safety
shall be informed about the consequences to the
customer of nonconformity to quality and safety
requirements
Juli 2006
12IRIS - Zusatzforderungen
- 6.2.2.3 Employee motivation and empoverment
- The organization shall motivate employees to
achieve - business, quality and safety objectives.
Juli 2006
13IRIS - Zusatzforderungen
- 6.2.2.4 Performance management planning
- An appraisal system shall be established to
regularly set - individual objectives linked with business
objectives and - review the individual performance
Juli 2006
14IRIS - Zusatzforderungen
- 6.3.2 Contingency plan
- The organization shall prepare contingency
- plans for utility interruptions, labour
shortage, - key equipement failure an field returns.
Juli 2006
15IRIS - Zusatzforderungen
- 7.2.2 Review of Requirements related to the
Product - Multidisciplinary approach shall be used.
- Project Management and Design / Development must
- be appropriatly represented in all requirements
reviews. - The organisation shall ensure that the
requirements are identified, negotiated,
evaluated, understood and committed. - Deficiencies identified in the review shall be
managed. - Risks shall be identified monitored and
mitigated. - The Reviews shall cover critical product
characteristics, customer regulatory - requirements, scope, time, cost, quality,
resources, communication, risk, changes
Juli 2006
16IRIS - Zusatzforderungen
- 7.3 Tender Management
- Prior to commitment to start the quotation
process the - organisation shall
- use a multidisciplinary approach to investigate
customer regulatory requirememts, confirm and
document the feasibility of the proposed products
in the tender review and approve the offer,
including planning,resources. - ensure that the requirements are identified,
negotiated, evaluated, understood and committed
Juli 2006
17IRIS - Zusatzforderungen
- 7.4 Project Management
- The organisation shall implement a Project
management or - New Product Developement Process addressing the
- applicable areas of Project management (see
7.4.ff), - describing the roles and responsabilities,
integrating all - functions of the organization into a
multidisciplinary team.
Juli 2006
18IRIS - Zusatzforderungen
- 7.4.1 Integration Management
- An integrated project plan shall be developed
reflecting the - specific rules to follow whilst executing a
project (e.g. multi - site project, consortium) throughout the entire
product life - cycle, including project plan change control.
Juli 2006
19IRIS - Zusatzforderungen
- 7.4.2 Scope Management
- The organization shall ensure that the entire
scope of work - is identified, subdivided in work packages,
controlled and - verified.
- Scope change shall be controlled and consistency
- guaranteed troughout the project and reflected in
the - project plan.
Juli 2006
20IRIS - Zusatzforderungen
- 7.4.3 Time Management
- The organization shall ensure timely completion
of the - project through the identification of
- Specific activities
- Interactivity dependencies of the work package
- Activity sequences, resource requirements and
duration - Critical path
- These activities shall be regularly reviewed,
controlled and recorded - In case of imminent deviation the organization
shall identify and implement - appropriate counter measures to avoid impact on
the customer. A change of - the delivery schedule must be authorized by the
customer. - Project plan shall be regularly reviewed and
updated -
Juli 2006
21IRIS - Zusatzforderungen
- 7.4.4 Cost Management
- The organization shall ensure the project is
completed - within the budget approved at the tender stage.
- A process shall be in place to regularly follow
the cost - progress on each work package and on each item of
the - total cost breakdown, including also the
identification of - estimate to completion.
Juli 2006
22IRIS - Zusatzforderungen
- 7.4.5 Quality Management
- The organization shall ensure a process is in
place to - manage project deliverables (e.g. customer
deliverables, - milestones, product characteristics, etc. )
- As a mimimum the following tasks shall be
managed - identification, clarification, fulfilment and
control - Validation and delivery on time
- Approval by the customer (where required)
- Open issues shall be controlled
- Documented project reviews shall take place at
regular intervals - troughout the entire project life.
- Phase Reviews shall take place at predefined
project phases / - milestones
Juli 2006
23IRIS - Zusatzforderungen
- 7.4.6 Human Resources Management
- Requirements in section 6 of this standard shall
be - deployed at the project team level. It shall
cover as a - minimum
- Identification, documentation and assignment of
project - roles, responsabilities and reporting
relationships - Acquisition of appropriate resources assigned to
and - working until project completion
- Developement of individual and group competencies
to - enhance project performance
Juli 2006
24IRIS - Zusatzforderungen
- 7.4.7 Communication Management
- The organization shall ensure that the project
team - determines and communicates needs of the
stakeholders. - This information, including performance
information, shall - be made available to project stakeholders in
timely manner.
Juli 2006
25IRIS - Zusatzforderungen
- 7.4.8 Risk and Opportunity Management
- The organization shall ensure a systematic
process is in - place to identify, analyse and when necessary
decide - upon the risk response.
- The risk response or opportunity enhancement
shall be - recorded and reported to all stakeholders as
appropriate. - The effectiveness of the response plan shall be
assessed - on regular basis
- Output of the risk assessment shall be regularly
reviewed - and updated troughout the project execution
Juli 2006
26IRIS - Zusatzforderungen
- 7.4.9 Change Management
- 7.4.9.1 General
- The organization shall have a process to control
and react to changes - that impact product realization.
- The effects of any change, including those
changes caused by any - supplier, shall be assessed and verification,
validation and approval - activities shall be defined, to ensure compliance
with customer - requirements before implementation.
- For proprietary designs, impact on form, fit and
function shall be - reviewed with the customer so that all effects
can be propery - evaluated.
Juli 2006
27IRIS - Zusatzforderungen
- 7.4.9.1 General
- When required by the customer, additional
verification / - identification requirements, such as those
required for new product introduction, shall be
met. - 7.4.9.2 Obsolescence Management
- The organization shall establish a process to
ensure, for - the defined and agreed product life cycle, the
availability of - the supplied products and spare parts.
Juli 2006
28IRIS - Zusatzforderungen
- 7.5.1 Design and Development Planning
- The organization shall determine task sequence,
- mandatory steps, significant stages and method of
- configuration control
-
Juli 2006
29IRIS - Zusatzforderungen
- 7.5.2 Design and Development Inputs
- The organization shall ensure new technologies /
- new products are valid before introduction into a
- customer project.
- This new technology / new product development
- shall apply the design and development
- requirements described in section 7.5.2
- RAMS and LCC shall be taken into account
Juli 2006
30IRIS - Zusatzforderungen
- 7.5.3 Design and Development Outputs
- The production process input (design output)
shall include - Specifications and drawings
- Information on materials
- Production process flow chart
- P FMEAs
- Control plan
- Work instructions
- Process and product acceptance criteria
- Data for quality, measurement, reliability,
maintainability, etc. - Results of error proofing activities
- Methods of rapid detection and feedback of
product and process NCs
Juli 2006
31IRIS - Zusatzforderungen
- 7.5.4 Design and Development Review
- At suitable stages, systematic reviews of design
and - developement shall be performed in accordance
with the - planned arrangements
Juli 2006
32IRIS - Zusatzforderungen
- 7.5.6 Design and Development Validation
- Design and development validation shall be
demonstrated - for all identified operatinal conditions.
- Where tests are necessary for verification and
validation, these tests - shall be planned, controlled, reviewed and
documented to ensure and - prove the following
- test plans
- Test procedures
- correct configuration
- Requirements of test plan
- Acceptance criterias
-
Juli 2006
33IRIS - Zusatzforderungen
- 7.5.8 First Article Inspection (FAI)
- The organization shall provide a documented
procedure - defining the inspection, verification, and
documentation of a - representative item from the first production run
of a new - part, or following any subsequent change that
invalidates - the previous first article inspection result.
- FAI shall be performed subsequently to the
verification of - the production process.
- This FAI procedure shall also be applied to
suppliers
Juli 2006
34IRIS - Zusatzforderungen
- 7.6 Configuration Management
- The organization shall establish, document and
- maintain a configuration management process
- appropriate to the product, this shall include
- Define a list of products including their parts,
the - configuration of which must be managed. This
list shall be approved be the customer - Adress configuration management within change
- management process
- Maintain traceability during production and
operations
Juli 2006
35IRIS - Zusatzforderungen
- 7.7 Purchasing
- 7.7.1 Purchasing Process
- The organization shall
- Maintain a register of approved suppliers with
includes the scope of - their approval.
- Ensure that all suppliers use customer approved
special processes. - Ensure that the function for supplier quality
systems has the authority to - reject the use of sources
Juli 2006
36IRIS - Zusatzforderungen
- 7.7.1 Purchasing Process
- The organization shall
- Develop suppliers with the goal of improving
supplier operational - performance.
- suppliers shall be third party registered to ISO
9001 2000 by an accredited third party
certification body (otherwise specified by the
customer) - The organization shall implement a system to
ensure the quality of all - products purchased from suppliers.
- .
Juli 2006
37IRIS - Zusatzforderungen
- 7.7.2 Purchasing Information
- The organization shall
- Ensure that the suppliers offer is selected only
after thorough prior negotiation. The negotiation
shall take into account - level of compliance with the purchasing
information - the total cost requirements (incl. LCC)
- previous product quality, costs and delivery
performance - Purchasing information shall also include p.e.
name of specifications, requirements for design
and test, approval process, This informations
(where applicable) shall be documented seperately
in the contract / purchase order.
Juli 2006
38IRIS - Zusatzforderungen
- 7.7.3 Supply chain management
- Supplier deliveries shall be scheduled in order
to meet the purchasing requirements. - Ordering shall be supported by an information
system covering the whole supply chain. - The organization shall communicate a forecast to
ist suppliers. - Suppliers shortages shall be identified and
communicated to the organization. Actions shall
be established to recover the delivery schedule.
Juli 2006
39IRIS - Zusatzforderungen
- 7.7.4 Verification of purchased product
- Verification activities shall include
- Obtaining objective evidence of the quality of
the product from the suppliers. - Inspection and audit at the suppliers premises
- Review of the required documentation
- Inspection of products upon receipt
- Delegation of verification to the supplier
Juli 2006
40IRIS - Zusatzforderungen
7.7.4 Verification of purchased product The
purchased product shall not be used or processed
until it has been verified as conforming to the
specified requirements. The organization shall
periodically verify test reports for raw
material. In case of delegation of verification
activities the requirements for delegation shall
be defined.
Juli 2006
41IRIS - Zusatzforderungen
7.8 Production and service provision 7.8.1 Prod
uction scheduling Production (including test
equipement) shall be scheduled (short-, mid- and
long term) in order to meet the purchase
requirements. The organization shall use custome
forecast and orders to plan capacity and
resources. Bottlenecks in the production shall
be identified an improvement action plan
established.
Juli 2006
42IRIS - Zusatzforderungen
- 7.8.1 Control of production and service provision
- Controlled conditions shall include
- Accountability for all products during
manufacturing (e.g. parts, quantities, spilt
orders, nonconforming product) - Evidence that all manufacturing and inspection
operations have been completed as planned
Juli 2006
43IRIS - Zusatzforderungen
- 7.8.2.1 Production documentation
- Production operations shall be carried out in
accordance with approved datas like - drawings, parts lists, process flow charts,
- tooling lis and numerical control (NC) machine
programs,
Juli 2006
44IRIS - Zusatzforderungen
- 7.8.2.2 Control of production process change
- The organization shall
- Establish, document and maintain a process to
control production process changes. - Responsabilities to approve changes shall be
identified. - The organization shall identify and obtain
acceptance of changes that require customer and /
or regulatory authority approval. - Changes affecting processes, production
equipement, tools and programs shall be
documented.
Juli 2006
45IRIS - Zusatzforderungen
- 7.8.2.3 Maintenance of equipement and tools
- Production equipement, tools and programs shall
be validated prior to use and maintainted an
inspected periodically according to documented
procedures. - Storage requirements, including periodic
preservation / condition checks, shall be
established for production equipement or tooling
storage. - Validation prior to production use shall include
also verification of first article.
Juli 2006
46IRIS - Zusatzforderungen
- 7.8.2.3 Validation of processes for production
- and service provision
- Special processes shall be managed according to
contractual and / or internal requirements. - A process shall be established for the control of
this special processes including qualification
and approval of the process prior to use.
Juli 2006
47IRIS - Zusatzforderungen
- 7.8.6 Preservation of product
- The organization shall ensure that the product
documentation required by the contract / order
is present at delivery and is protected against
loss and deterioration.
Juli 2006
48IRIS - Zusatzforderungen
- 7.9 Commissioning / customer service
- Where field service is a specified requirement,
- processes shall provide for
- Actions to be taken where problems are
identified after delivery, - including investigation, reporting activities
and actions on service - informations
- The control and updating of technical
documentation - The Approval, control and use of repair
schemes - The organization shall demonstrate the adequate
customer support during commissioning and
warranty until complete product validation and
final customer acceptance - Suitable resoucre shall be available
- Maintenenance contracts shall be managed
Juli 2006
49IRIS - Zusatzforderungen
- 7.10 RAMS / LCC
- The organization shall have
- Documented procedure to cover all aspects of RAMS
- Process in place to manage LCC
- Resource shall be in place to address the RAMS
and LCC requirements - RAMS / LCC data collection and analysis shall be
supported by return of experience from operation
and after warranty period
Juli 2006
50IRIS - Zusatzforderungen
- 7.11 Control of monitoring and measuring
- devices
- The organization shall
- Maintain a register of these monitoring and
measuring devices and define the process employed
for their calibration including details of
equipement type, unique identification, location,
frequency of checks, check method and acceptance
criteria. - Ensure ambient conditions are suitable for the
carrying out of the calibration, inspection,
measurement and testing.
Juli 2006
51IRIS - Zusatzforderungen
- 8.2.2 Internal Audit
- The organization shall audit all processes of ist
management system to verify compliance with all
requirements. - The auditprogramm shall cover all production
shifts.
Juli 2006
52IRIS - Zusatzforderungen
- 8.2.3 Monitoring and measurement of processes
- Each process identified as such in these
requirements shall be supported be key
performance indicator (KPI)
Juli 2006
53IRIS - Zusatzforderungen
- 8.2.4 Monitoring and measurement of product
- Measurement requirements for product or service
acceptance shall be documented and include - criteria for acceptance and / or rejection
- where in the sequence measurement and testing
operations are - performed
- a record of the measurement results
- Type of measurement instruments
- Test records shall show actual test results data
when required by specification or acceptance
plan.
Juli 2006
54IRIS - Zusatzforderungen
- 8.3.2 Customer waiver
- Whenever the product or production process differ
from that which is currently approved, the
organization shall obtain a customer concession
or deviation permit prior to further processing. - Records of the expiration date of such
concessions shall be maintained. - Material shipped under concession conditions
shall be clearly and appropriate identified.
These aplies also to purchased products.
Juli 2006
55IRIS - Zusatzforderungen
- 8.4 Control of nonconforming processes
- A process shall be in place to
- identify, record the non conformity and take
appropriate - action to correct the non conforming process
- evaluate whether the process non conformity has
- resulted in product non conformity
-
Juli 2006
56IRIS - Zusatzforderungen
- 8.6.3 Corrective Action
- The procedure shall define requirements to
document the effectiveness and close out of
corrective action.
Juli 2006