Title: European Space Operations Centre
1European Space Operations Centre
Space Agency Overviews- ESA/ESOC -
SpaceOps Committee at Large MeetingMiraikan,
Tokyo 17 April 2007
Manfred Warhaut ESA/ESOC (OPS-O)
2ESA Organization
DIRECTOR GENERAL J.-J. DORDAIN
Directorates
Program-
SCIENCE PROGRAMME
EARTH OBSERVATION PROGRAMME
TELECOMMUNICATION AND NAVIGATION
LAUNCHERS
HUMAN SPACEFLIGHT, MICROGRAVITY AND EXPLORATION
G. VIRIGLIO
A. FABRIZI
D. SACOTTE
D. SOUTHWOOD
V. LIEBIG
Support-
Directorates
TECHNICAL AND QUALITY MANAGEMENT
OPERATIONS AND INFRASTRUCTURE
EXTERNAL RELATIONS
RESOURCES MANAGEMENT
M. COURTOIS
G. WINTERS
R. OOSTERLINCK
H. KAPPLER
3D/OPS Organization
4(No Transcript)
5ESA Science Missions
Integral
XMM
LisaPF
Gaia
Smart-1
Soho
Cluster
ExoMars
Huygens
BepiColombo
Venus Express
Ulysses
Mars Express
Rosetta
6ESA Earth Observation Missions
- ERS
- ENVISAT
- GOCE
- SMOS
- ADM-AEOLUS
- CRYOSAT-2
- SWARM
- GMES/Sentinels
- EarthCare
7ESA ISS Mission Operations
- ISS mission operations are managed by D/OPS but
conducted from control centres hosted by National
Agencies
- DLR Oberpfaffenhofen for
- Columbus operations
- CNES Toulouse for
- ATV operations
8(No Transcript)
9ESA Tracking Station Network (ESTRACK)
10Evolution of ESTRACK
- ESTRACK facilities follow requirements of ESA
programmes, subject to constant evolution, which
now requires adjustment in both capabilities and
capacity. There is a decreasing load on existing
facilities, and at the same time the need for
adapted and/or new assets. - Evolution of ESTRACK takes into account
technological aspects, conscious risk taking,
cost efficient setting-up and operation of
assets, whilst ensuring independent access to
space. - ESA concentrates on high-end technology of
complex nature not readily available on the
commercial and institutional markets, but
acknowledges advances in commercial sector for
provision of standard tracking services available
on a contractual basis. - Necessary ESTRACK adjustments to be taken in the
near and medium term relate to TTC aspects,
which for scientific missions includes the
acquisition of science data. - Earth observation payload data acquisition
mostly achieved through dedicated terminals are
not within the scope of this document. Due to
special nature of the Galileo project the
pertinent TTC facilities are also not considered
in this context, except for the In-Orbit Test
(IOT) activities at Redu.
11ESTRACK Core Network Load (2007-2016)
Without possible mission extensions being
discussed by relevant Program Boards
12ESTRACK Evolution Summary
- ESTRACK and its operation by ESA is impacted by
the following factors over next 10 years - Utilisation will drop significantly The overall
load on the network (which at present is around
47000 hours of tracking support per year) will be
reduced to about 30 by 2011, respectively 50
in 2013. - The technical requirements of ESA programmes (in
particular Science) have evolved and will require
more complex and sophisticated space
communications technology in the X and Ka bands
as well as 35 m antennas for deep space
communication. - The standard routine TTC support services are
becoming more and more available on the
commercial markets. For certain market segments,
commercial operators can offer attractive
conditions for ESA. Consequently, ESA will
concentrate on the critical, strategic and
complex operations activities for which a
commercial market has not (yet) developed, such
as deep space and LEOP spacecraft operations. - As a consequence, ESA will have to re-structure
its station network by - Reducing capacity where it is no longer utilised
by the ESA missions - Increasing capacity in the Deep Space network to
support its future scientific and exploration
missions - Outsourcing activities that can be taken care of
by industry at better commercial conditions. - This re-structuring process will have
implications for existing ESA infrastructure in
member states and in non-member states. Such a
policy needs to be implemented on the basis of a
careful implementation plan in order to avoid
adverse effects, risks to the ESA operations, and
taking into account the interest of the member
states concerned.
13ESA/ESOC (OPS-O)Key Objectives 2007
- Mission Extension MEX and VEX (23 February 2007)
done - ROSETTA Mars fly-by (25 February 2007) done
- ESTRACK Evolution to Council, and DS3 endorsed
(14/15 March 2007) done - Signature ESA / NASA Network and Operations Cross
Support Agreement (21 March 2007) done - TerraSAR-X support (24 May 2007)
- Lisa Pathfinder confirmation (25 May 2007)
- Chang E-1 support (October 2007)
- ROSETTA 2nd Earth fly-by (November 2007)
- XMM and Integral Mission Extensions (November
2007) - SoLo approval (November 2007)
- GOCE launch (16 December 2007) possibly in
Jan/Feb 2008 - Note ATV (November 2007) and Columbus (December
2007)
14Information / Discussion on General Topics
- Space Communications Architecture
- Space Debris alert and reporting
- Network and Operations Cross-support
- Non Disclosure Agreements
- Future of RCSGSO