Title: Monte Carlo Schedule Analysis
1Monte Carlo Schedule Analysis
- The Concept, Benefits and Limitations
Intaver Institute 400, 7015, Macleod Trail S.W.,
Calgary, Alberta, T2H 2K6, Canada
2What is Monte Carlo Analysis?
- Monte Carlo simulation is a mathematical method
used in risk analysis. Monte Carlo simulations
are used to approximate the distribution of
potential results based on probabilistic inputs.
3Monte Carlo Simulations
Monte Carlo simulations use distributions as
inputs, which are also the results
4Monte Carlo Schedule Analysis
Monte Carlo simulations take multiple
distributions and create histograms to depict the
results of the analysis
5Two Approaches to Estimating Probabilities
- The relative frequency approach, where
probability equals the number of occurrences of
specific outcome (or event) divided by the total
number of possible outcomes. - The subjective approach represents an experts
degree of belief that a particular outcome will
occur.
6Two of Approaches for Defining Uncertainties
- Distribution-based approach
- Event-based approach
- Monte Carlo can be used to simulate the results
of discrete risk events with probability and
impact on multiple activities
7What Distribution Should Be Used?
- Also useful for Monte Carlo simulations
- Lognornal
- Beta
8Ignoring Base-Rate Frequencies
- Historically, the probability that a particular
component will be defective is 1. - The component is tested before installation.
- The test showed that the component is defective.
- The test usually successfully identifies
defective components 80 of the time. - What is the probability that a component is
defective? - The correct answer is close to 4, however, most
people would think that answer is a little bit
lower than 80.
9Role of Emotions
Emotions can affect our judgment
10Eliciting Judgment About Probabilities of Single
Events
- Pose a direct question What is the probability
that the project will be canceled due to
budgetary problems? - Ask the experts two opposing questions (1) What
is the probability that the project will be
canceled? and (2) What is the probability the
project will be completed? The sum of these two
assessments should be 100. - Break compound events into simple events and
review them separately.
11Probability Wheel
Use of visual aids like a probability wheel can
aid in the increasing validity of estimates
12Eliciting Judgment Probability Method
13Eliciting Judgment Method of Relative Heights
Plotting possible estimates on a histogram can
help improve estimatesc
14How Many Trials Are Required?
- Huge number of trials (gt 1000) usually does not
increase accuracy of analysis - Incorporate rare events
- Use convergence monitoring
15What Is The Chance That a Project Will Be on Time
And Within Budget?
16Analysis of Monte Carlo Results
- Sensitivity and Correlations
- Critical Indices
- Crucial tasks
- Critical Risks
- Probabilistic Calendars
- Deadlines
- Conditional Branching
- Probabilistic Branching
- Chance of Task Existence
17Crucial Tasks
Crucial tasks for project duration
Monte Carlo analysis identifies task cruciality,
how often tasks are on the critical path.
18Critical Risks
19Conditional Branching
20Monte Carlo and Critical Chain
Monitoring Project Buffer
21Tracking Chance of Project Meeting a Deadline
22When Monte Carlo Is Useful
- You have reliable historical data
- You have tools to track actual data for each
phase of the project - You have a group of experts who understand the
project, have experience in similar projects, and
are trained to avoid cognitive and motivational
biases
23Additional Resources
Project Think Why Good Managers Make Poor
Project Choices
Project Decisions The Art and Science Introductio
n to Project Risk Management and Decision
Analysis
Project Risk Analysis Made Ridiculously Simple
24Questions?