Title: L1CTT Run IIb Readiness Review


1
L1CTT Run IIb Readiness Review
  • The CTT Gang

2
Physics Motivation
  • In Run IIa and RunIIb, the L1 Track Trigger
    Provides
  • CFT tracks for L1Muon Seeds
  • High pT isolated track trigger capability
  • CFT tracks CPS clusters ? embryonic electrons
  • Found tracks for STT
  • As instantaneous luminosities hit 1032, the
    rejection for L1CTT drop drastically.
  • Accomplish high eff with low fake rates using the
    full granularity of the CTT.

3
Motivation
  • Need much larger FPGA to accommodate the
    increased equation set.
  • Add extensive testability of the input and output
    information from the DFEA
  • Reduce firmware download times.
  • Limited by the slow 1553 interface
  • Old method scales up to about 12 hours/job for
    Run IIb equation file sizes
  • Concerns about reliability of the download of
    firmware 3-5x the existing size.

4
Changes
  • Remove existing DFE crates
  • Change access of cables from front to back
  • Design new DFE boards for larger FPGA.
  • Add front panel LED for status.
  • Add input/output buffer sampling on DFEA2
  • New crate controller with much faster download
    speed.

5
Questions for Committee
  • Does the CTT upgrade follow the Hippocratic Oath?
  • First, do no harm
  • Does the chances of improving performance
    outweigh any reasonable risks?
  • Are there any show stoppers for installation?
  • Have we forgotten anything?