Closeout of IIDR Recommendations - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Closeout of IIDR Recommendations

Description:

The Board notes with satisfaction that at subsystem level very good progress has ... between PACS and SPIRE as very profitable and asks PACS to liaise with SPIRE. ... – PowerPoint PPT presentation

Number of Views:31
Avg rating:3.0/5.0
Slides: 17
Provided by: albrechtp
Category:

less

Transcript and Presenter's Notes

Title: Closeout of IIDR Recommendations


1
Close-out of IIDR Recommendations
  • A. Poglitsch

2
IIDR Board Conclusions
  • The Board notes with satisfaction that at
    subsystem level very good progress has been made
    in the design and identification of critical
    areas and congratulates the PACS team for their
    efforts.
  • The Board is confident that with the
    implementation of its recommendations PACS will
    arrive at the required status for the next
    review, which will mark the start of the
    instruments detailed design and development
    phase.
  • Although the Board does not consider the Review
    objectives formally fully met, it does not see
    the need for a delta Review.

3
Board Recommendations
  • R1 The Board fully supports PACS desire to
    review and consolidate urgently their model
    philosophy, test sequences and schedule in
    conjunction with the Prime Contractor and ESA and
    strongly asks PACS to ensure, as part of the
    consolidation, proper AIV sequence and instrument
    characterisation. The main goals will have to be
    to ensure the required delivery dates for the CQM
    and PFM, to reduce the number of items on the
    critical path and to ensure adequate schedule
    margins, while still allowing adequate time for
    properly characterising and calibrating the
    instrument on the ground.
  • This is still ongoing work it is clear, however,
    that proper characterisation and calibration on
    the ground are incompatible with original (IID-A)
    schedule. Final assessment requires consolidated
    schedule for satellite from Prime which has to be
    achieved yet.

4
Board Recommendations
  • R2 The Board asks PACS to proceed without delay
    in the resolution of the identified open issues,
    being telescope optical prescription and
    straylight, black paint and connector
    qualification and instrument product assurance.
  • Closed
  • telescope optical prescription agreed between
    instruments, ESA, and Prime
  • black paint qualification at ESTEC
  • connectors through CPP
  • PA established
  • Open telescope straylight model from Prime

5
Board Recommendations
  • R3 The Board urges PACS to carry out a failure
    analysis at system and subsystem levels and to
    provide a FMECA.
  • Closed.

6
Board Recommendations
  • R4 The Board asks PACS to review their thermal
    analysis of the FPU and the validity of the
    underlying assumptions. The Board sees an
    expertise exchange between PACS and SPIRE as very
    profitable and asks PACS to liaise with SPIRE.
    PACS must deliver a proper thermal model
    including the bolometer array.
  • Closed thermal model delivered
  • Open thermal analysis can only be done at
    system level! Results urgently needed as
    manufacture of FPU has started and changes will
    lead to delay and cost increase

7
Board Recommendations
  • R5 The Board asks PACS to optimise their FPU
    mechanical design with the aim to reduce the
    loads on the chopper.
  • Closed
  • change in FPU structural design has reduced loads
    on chopper to accepted value
  • RfW for notching pending

8
Board Recommendations
  • R6 The Board acknowledges that PACS clearly
    identified their critical areas as being the
    CREs, the grating mechanism, the SPU, and the
    bolometer arrays, and asks PACS to follow these
    closely to arrive at a mature design.
  • Progress
  • CRE performance according to specs demonstrated
    in most parameters, QM chips manufactured, small
    optimisations for FM run identified
  • SPU H/W design according to PACS requirements
    settled
  • grating drive and position readout bread-boarded
  • QM bolometer arrays manufactured, performance
    tests done so far are within specs

9
Board Recommendations
  • R7 The Board urges PACS to validate the new
    design for the BOLA with the reduced dissipation.
    Before deciding on the desirability of designing
    away the BOLA unit, the impact of mission
    lifetime must be assessed in connection with ESA.
  • Closed BOLA with reduced dissipation is
    baseline
  • Problem BOLA minimum operating temperature may
    be above CVV temperature needs clarification on
    short timescale

10
Board Recommendations
  • R8 The Board sees the interdependence of the SPU
    and REBA (LFI) requirements as unhealthy and asks
    PACS to make a detailed analysis of the SPU
    requirements and closely follow the SPU programme
    (see also R9 and R10).
  • Closed design of both units has been upgraded
    to meet PACS SPU requirements

11
Board Recommendations
  • R9 The Board sees the need to directly involve
    the SPU and DPU contractors in programmatic and
    technical discussions and asks PACS to consider
    the participation of representatives of CRISA
    (contractor for SPU) and Gavazzi (contractor for
    DPU) in the PACS team.
  • Closed for DPU regular progress meetings
    between system engineering, IFSI, and Gavazzi
  • Open for SPU interaction lacks sufficient
    support from IAC/CRISA

12
Board Recommendations
  • R10 The Board asks PACS to urgently review the
    needed on-board data processing and compression
    needs for all foreseen operating modes in the
    view of consolidating the requirements for the
    implementation of this critical subsystem.
  • Closed basic needs for all operating modes have
    been defined to the extent needed for H/W design.
  • Remark more detailed definition at the border
    between requirements and implementation is still
    necessary (ongoing work)

13
Board Recommendations
  • R11 The Board asks PACS to consolidate the data
    compression requirements with the SPU design. The
    Board urges PACS to review with IAC as a matter
    of urgency all aspects of the SPU programme, i.e.
    technical issues (e.g. processor speed, memory
    requirements), cost and schedule impacts, SPU
    model philosophy, etc.
  • Closed
  • agreed design following PACS requirements
  • schedule compatible with PACS master schedule
  • SPU AVM not form-fit-function

14
Board Recommendations
  • R12 The Board asks PACS to bring its
    documentation to the standard required for the
    start of its phase C/D. All documents should be
    at Issue 1 (or higher), properly signed and put
    under formal Configuration Control. As a matter
    of priority the following documents must be
    updated
  • DDVP
  • Product Tree
  • Work Breakdown Structure
  • Documentation Tree
  • ICDs
  • Closed with IBDR
  • Remark DDVP replaced with 2 new documents
  • general instrument AIV (without tests)
  • test plan (including AIV)

15
Board Recommendations
  • R13 The Board takes note of the increase of the
    FPU mass budget and urges PACS to trace their
    budgets and clearly identify the drivers.
  • Closed FPU mass budget
  • after FPU design review and change request new
    and final masses accepted by Project
  • Open electrical power budget
  • PACS on mode above allocated 100 W per
    instrument
  • ongoing discussion with Prime on actual total
    power budget as all 3 instruments do not need to
    be on simultaneously

16
Board Recommendations
  • R14 The Board urges PACS, together with SPIRE
    and the Science Team, to provide a schedule how
    to settle the parallel mode issue before the
    end of the year, identifying the (currently
    missing) knowledge required to make a decision.
  • Progress Evaluation Note on parallel mode byM.
    Griffin and A. Poglitsch sent to Project
    Scientist on 08 Jan 02
Write a Comment
User Comments (0)
About PowerShow.com