Title: Communication Forum
1Communication Forum 23rd September 2004 Paul
Quinn SRD Henry Gun-Why Estates Management DL
2Estates Management Operations
- Estates Management
- Site Operations security
- User Liaison
- Stores
- Period of Management Change and consolidation
3Estates Management Operations
- Daresbury Laboratory Operations Group DLOG,
will continue , terms of reference and membership
to be reviewed. Reporting into SMT. - Estates infrastructure.
- Health and Safety Committee will continue.
- Amenity Area and Fitness Centre will be
formalised and report into DLOG. - Next SMT 30th September 2004
4Keckwick Lane Nearly there
- Stage 3 Tuesday 13th September 2004 Audit,
Cheshire Police, Halton Borough Council, White
Young Green and Daresbury Laboratory - Matters arising - Signage , speed, lighting ,
names, road markings, roundabouts, barriers,
temporary dollies and cones .
5Keckwick Lane
6(No Transcript)
7(No Transcript)
8(No Transcript)
9(No Transcript)
10(No Transcript)
11(No Transcript)
12(No Transcript)
13(No Transcript)
14(No Transcript)
15(No Transcript)
16(No Transcript)
17(No Transcript)
18(No Transcript)
19(No Transcript)
20(No Transcript)
21(No Transcript)
22(No Transcript)
23(No Transcript)
24(No Transcript)
25(No Transcript)
26(No Transcript)
27(No Transcript)
28SITE ROAD STRAIGHTENING PEDESTRIAN ACCESS
29(No Transcript)
30(No Transcript)
31(No Transcript)
32(No Transcript)
33(No Transcript)
34(No Transcript)
35COMMISSIONING A NEW TRANSFORMER
36(No Transcript)
37(No Transcript)
38(No Transcript)
39(No Transcript)
40(No Transcript)
41(No Transcript)
42(No Transcript)
43(No Transcript)
44August was a bit wet
45Estates Management Activity Update and Issues
Raised
- Proposed Decentralisation of heating system ,
commencement May 2004, completion September
2004. - The 14 No Boiler Houses have been completed ,
awaiting Gas to be commissioned. - The Infrastructure Pipe work for Gas and Water
has been installed. - Problem, whilst there is Gas in Keckwick Lane,
the meter and housing installation delivery is
to be confirmed ? - No plan B -
46BOILER ISOLATION
47(No Transcript)
48(No Transcript)
49(No Transcript)
50(No Transcript)
51(No Transcript)
52(No Transcript)
53(No Transcript)
54(No Transcript)
55Dog Drives Dump Digger for DL
56(No Transcript)
57(No Transcript)
58(No Transcript)
59(No Transcript)
60(No Transcript)
61(No Transcript)
62(No Transcript)
63(No Transcript)
64(No Transcript)
65(No Transcript)
66(No Transcript)
67(No Transcript)
68(No Transcript)
69(No Transcript)
70Estates Strategy - OST proposed funded projects-
2004-2005
- Replacement Site Water Main
- Asbestos removal within Tower Building
- Tower Ventilation system replacement
- Replacement of Roofs
- Replacement of CBlock Elevations
- New Entrance for B Block from Car Park - DDA
- Upgrade entrance to A and B Blocks- DDA
- Upgrade Main corridors A and B Blocks
- Upgrade Road surfaces, replace security barriers
and replace wooden kerbs. - Electrical Testing of Buildings
71THESE ARE NOT MOTORCYCLES
Would cyclists please refrain from using the bays
reserved for motorcycles, when these pictures
were taken there was space available in the cycle
racks and the motor cyclists are worried about
possible damage to their very valuable machines.
72(No Transcript)
73Emergency Plan Muster Point
74Estates Management Activity Update and Issues
Raised
- Decentralisation of Site Heating Gas Supply
Hobb Lane, A56 Chester Road, down Keckwick Lane
by July 2004. - HSE Fire Precautions Phase 1 - work has commenced
in the SR and Tower completion September 2004
Fire Panels replacement - Fire System Replacement - Tower, Stores , E
Block and A Block Summer 2004
75Reception Building Update
- Principal Contractor Whites Building Services
- Start on site Monday 22nd September 2003
- Demolition w/c 6th October 2003
- Completed 27th August 2004
- Cost 1.83 m including VAT and fees
- Ground Floor Security, User Liaison and Site
Operations - 1st Floor Directorate , BITD Information Lounge
and others to be confirmed. - Furniture installed, occupancy with next 14
days. - Security - when the CCTV has been re-engineered
76(No Transcript)
77(No Transcript)
78(No Transcript)
79(No Transcript)
80(No Transcript)
81(No Transcript)
82(No Transcript)
83(No Transcript)
84AMAZING REFLECTIVE QUALITIES OF THE RECEPTION
BUILDING FRONT PANELS
85Thanks for your Co-operation
- Staff
- Users
- Site Operations and Security
- Estates Management
86Reception Centre Visit
- Today, commencing after this presentation led
by Colin Gelson Jackson, conducted by Site
Operations and User Liaison