Title: Accelerator Operations Department Readiness Part 2


1
Accelerator Operations Department Readiness(Part
2)
  • Mike Stanek
  • Accelerator Systems Division, Deputy Operations
    Department head
  • 14-Mar-2007

2
Operations is ready for LCLS Injector
Commissioning
  • Operations Documentation and Training systems are
    mature, established, and proven.
  • Required LCLS documention and training have been
    identified.
  • Development of new required documents is complete
    (and continues to evolve.)
  • For LCLS Injector Commissioning, we have
    integrated new documents into an existing system.
  • Same approach was used for commissioning PEPII

3
  • Roles and Responsibilities of Ops personnel are
    established.
  • Ops manpower is committed to support LCLS
    Injector Commissioning plan.

4
Documentation
  • Operations Dept owns the required documents.
  • Developed with input from LCLS system designers
    and engineers
  • Approvals Ops managers and Accelerator Division
    Safety Officer (also co-author for some
    documents)

5
Status of Required Documents
  • LCLS Required Documents List has been generated
    by OPS, AD Safety Officer.
  • Completed, verified, and released

6
Example
  • LCLS Search Procedure

7
Operator Training to the LCLS Documents
  • Safety systems Training must be in place prior
    to operation! (as with any SLAC PPS)
  • PPS Certification Workbooks
  • 1. Reading the Applicable Documents
  • 2. Operating the PPS Controls
  • 3. Searching the PPS Zone
  • 4. Performing a Safety Inspection
  • 5. Checking the PPS Interlocks
  • 6. Trainer Supervisor signoff
  • Incident and Alarm response
  • Beam Containment System Procedures

8
Example
  • LCLS PPS Certification Workbook

9
Specific Operations Dept. Training
  • Administrative
  • Operations Directives revised for LCLS
    Required Reading sheet (complete).
  • Technical system operation
  • Primarily On-the-Job, will be learning along
    with the commissioning physicists.
  • Accelerator systems that do NOT impact personnel
    safety are incorporated into the Ops training
    workbooks over time with less formal treatment.

10
Training Record for PPS Operation
11
Operations Support of the Commissioning Plan
  • Roles and Responsibilities are defined in AD
    Operations Directives
  • Engineering Operator in Charge
  • Responsible for safe execution of the scheduled
    program (PEPII and LCLS)
  • Supervises and directs Operators on shift
  • Operators (3-4 per shift)
  • One per shift assigned to assist LCLS
    Commissioning
  • Safety responsibilities (Search, PPS Operation,
    alarm response, etc.)
  • Technical support (pre-run checkout, assist
    Commissioning team with measurements, tuning)
  • Accelerator Dept Safety Officer

12
Beam Authorization Sheet
  • Establishes Radiation protection conditions
    required to allow beam operation for each part of
    the accelerator.
  • Includes Pre-run checks, Running conditions,
    Initial checkout (surveys and calibration)
  • Radiation Physicist and AD Safety Office are
    co-authors
  • EOIC is responsible for insuring conditions are
    met.
  • Review and sign every shift
  • LCLS Injector will have a BAS for commissioning
  • Draft under review. It will be released to the
    EOIC when approval signatures are obtained from
    Radiation Physics, ADSO, and Head of Operations.

13
BAS - DRAFT
14
Work Control and Authorization
  • Configuration control of required safety envelope
    devices.
  • Work authorization is by Area Manager
  • Reports to Accelerator Division management.
  • Supports EOIC in controlling maintenance and
    repair work.
  • Initiates Work Control forms, which triggers
    safety review, mitigation requirements, approvals
  • eg. Radiation Safety Work Control Form (ADSO, Rad
    Physics)

15
Work Control (cont)
  • Maintenance and repair work is tracked through a
    computer-based system (ARTEMIS).
  • This system has built in work control, ISMS,
    and approval features.
  • It has been modified for LCLS Injector system
    problem entries.
  • Work on all SLAC Accelerator systems is subject
    to these controls. LCLS Injector fits in to the
    existing systems.

16
Questions?