Title: Power System Restoration


1
Power System Restoration
  • Kevin Schneider, Chen-Ching Liu
  • University of Washington
  • Department of Electrical Engineering

2
Overview
3
Restoration Constraints
  • Main power converter startup time
  • Communications start up time
  • Maximum dv/dt
  • Node voltage limits

4
Main Power Converter Startup Time
  • 10-15 second startup delay from when power is
    applied to the backbone
  • During this time
  • Startup supply capacitor charges to 48V
  • SCRs begin to fire at 45V
  • Startup power supply energized
  • Main power converter control circuits energized

5
Communications Startup Time
  • Approximately ½ to 1 minute for the
    communications system to power up

6
Maximum DV/DT
  • PN junctions in solid state components are
    sensitive to high values of DV/DT
  • DI/DT will not be a concern for the NEPTUNE
    systems backbone solid state components

7
Node Voltage Limits
  • If node voltage drops below 5600V the control
    circuit will drop out and the converter will turn
    off
  • Voltage cannot exceed certain levels or there
    could be arc over
  • There will be an acceptable band of operation
    that must be adhered to

8
Security Analysis
9
Security Analysis Cont.
  • Switching Action- For a restorative action there
    may be several possible ways to restore the
    system.
  • Feasibility- A portion of these actions will
    place the system in insecure configuration for
    some period of time. Only switch actions which
    do not violate any constraint can be allowed.

Note a system may meet all 4 constrains but be
operating in an insecure condition
10
Contingency Selection
  • Before a switching action is performed the effect
    of the following must be considered for the new
    topology
  • Loss of shore station
  • Loss of shallow water links or deep water links
  • Significant load increase
  • Node failures
  • Others

11
Black Start Example
  • Only the shore stations have power
  • After a node is fully energized, 4 kW of
    scientific load is applied to that node

12
System Start-up From Black Start Ensuring Voltage
Limits
Victoria
18V
72V
185V
Nedonna Beach
942
13
Summary
  • Before every switching action
  • Ensure all 4 constraints are meet
  • Ensure transition is to a secure situation