Title: The Building Code Compliance Office
1The Building Code Compliance Office
- Lightweight Insulating
- Concrete
- Instructor
- Michael L. Goolsby, RRC
2FBC definition
- Material produced with or without aggregate
additions to portland cement, water and air to
form a hardened material possessing insulating
qualities, which, when oven dried shall have a
unit weight no greater than 50 pcf (801 kg/m3).
(1917.1)
3Types of lightweight insulating concrete
mentioned in the FBC
- Aggregate Minimum compressive strength 125
psi - Cellular Minimum compressive strength 160
psi - Cellular/aggregate (Hybrid)
- Minimum compressive strength 200 psi (250
psi for adhered membrane systems)
4Cellular LWIC
- A foaming agent is added to the LWIC.
- The foam keeps the cement particles in suspension
around the cells until the LWIC hardens into a
honeycomb matrix.
5Advantages of LWIC
- Slope to drain
- Thermal value
- Thermal mass
- Keep weight off
- Surface irregularities
- Fire resistivity
- Nailable base
- Avoid tear off
6What is the minimum thickness of LWIC that must
be poured?
- 1917.4.2 Minimum thickness of lightweight
insulating concrete fill shall be 2 inches over
the top plane of the substrate unless otherwise
specified in the Product Control Approval. In
all cases, lightweight insulating concrete shall
be of sufficient thickness to receive the
specific base ply fastener throughout the roof
deck.
7What is the R Value of LWIC
- FBC 13-404.2.AB.1 Data input per Appendix B.
- Shall obtain from 1997 ASHRAE Handbook of
Fundamentals. - R Values per ASHRAE for Cellular
- Density
- 60 pcf R 0.48
- 40 pcf R 0.71
- 20 pcf R 1.25
- When not available here
- Use manufacturers info based on lab or field
testing. Four ASTM tests specified. - EPS is used to enhance R value.
8EPS Board
- 1917.4.12 Insulation board with lightweight
insulating concrete fill shall conform to Type I
expanded polystyrene insulation as defined in
ASTM C 578. 1. - Check LWIC NOA for approved insulation.
- Insulation panels shall be provided with holes
and/or slots for keying and/or slots for venting. - Sometimes the holes do not extend through the
board. In this case the board should not be used.
9What is holey board?
- EPS is required to have holes to allow for
monolithic bonding of the slurry coat and top
pour. - Hence the name. Holey board is used as a brand
name by at least one manufacturer. - Size and density of the holes is established by
the insulation manufacturer. - 8-2 1/2 holes or 6-3 holes or 6- 2 7/8 holes
for a 2 x4 EPS board. - Minimum EPS density 1 pcf, 1 thick min., 2 x4
min. dimensions. (Per NOA)
10EPS (Holey Board) stacked on the roof.
11EPS (Holey Board) stacked on the roof.
12How is EPS installed
- Thickness of EPS depends on R value required
and slope required. - EPS is placed in a 1/8 slurry coat of LWIC,
while the material is still plastic. - A minimum 2 topcoat of LWIC is then installed.
- Some manufacturers require that 24 hours elapse
between placement of the EPS and installation of
the top coat. Some allow both the same day. - NOA typically requires the 24 hour delay for
installations on structural steel. -
13Slurry coat being installed. EPS will be set in
the slurry coat.
14EPS is being installed in the slurry coat.
15EPS (cont.)
- When installing EPS boards, dont drag the boards
over the flutes, slurry coat will be displaced. - EPS boards cannot be stacked, only one layer is
acceptable. - Solvent based adhesives may migrate through
cracks in the LWIC and damage the EPS boards.
16What is a floater?
- When an EPS board does not stay secured to the
substrate, the board will sometimes rise to the
surface of the top pour.
17Fasteners that bottom out.
- Insufficient depth of top pour. (1917.4.2)
- The legs of the fastener hit the EPS board and
the fastener bounces up. - Resulting in a fastener that has no holding power.
18Over what substrates may LWIC be poured?
- Structural steel (as thin as 26 gauge)
- (2222.4.3)
- Structural concrete also twin tees and pre-cast
units - Existing roof systems, i.e. gravel, smooth or
granule surfaced BUR.
19Moisture content of LWIC
- 267-350 lbs of water used to batch one cubic yard
of 200-249 psi LWIC. - How much is left after hydration?
- Can you tell if the deck is dry based on the
color of the LWIC? - What is the EMC? Moisture affects R value. Air
has a k value of .17 /water k 4. - What happens if rain occurs prior to installation
of the roof cover on a deck without underside
venting/with underside venting? - Is there a way to remove excess water?
20Venting of LWIC
- 1917.4.1 Lightweight insulating concrete fill
shall be poured over bottom slotted galvanized
(G-90) steel decking as follows cellular, 0.5
percent open hybrid, 0.75 percent open,
aggregate 1.5 percent open. No lightweight
insulating concrete shall be poured over a
painted or non-galvanized steel deck. - 1. Lightweight insulating concrete fill over
structural concrete slabs, twin tees, precast
units or other non venting substrates shall be
vented, to allow the escape of excess moisture
21Roof system venting
- 1519.5.3 Lightweight insulating concrete. All
lightweight insulated concrete shall be vented
per roofing system manufacturer recommendations. - It seems a conflict exists between 1519.5.3 and
1917.4.1. - The more restrictive applies per 101.4.1.
- How can venting be accomplished?
22Must the LWIC have an NOA?
- 1917.2.1 Product Control Approval shall be
required for all lightweight insulating concrete
fill systems.
23Must LWIC installation comply with wind load
requirements?
- Yes. Maximum design pressures are listed in the
NOA for various substrates. - These pressures must meet or exceed the design
pressures of the building for all pressure zones. - What is the effective area for LWIC?
- Effective area for a mechanically fastened roof
system is the area attributed to one fastener.
24LWIC strength, bar joist spacing and maximum
design pressures
- Spacing has a direct impact on the uplift
resistance developed between the steel deck and
the LWIC. - Deflection of the steel deck causes the LWIC to
fail in tension. - Typically the closer the bar joists the higher
the maximum design pressure of the LWIC. - Are compressive strength, bar joist spacing and
maximum design pressures being cross referenced
against the LWIC NOA and roof system NOA at the
processing stage? - Section 104.2.1.1 drawings and specifications.
25Maximum Design Pressures
26Polyester fibers improve tensile and shear
performance.
27Is testing of new LWIC required?
- 1917.3 Testing. The building official may require
tests of the lightweight insulating concrete fill
to confirm the - fastener withdrawal resistance
- compressive strength
- drainage ability.
28How can the physical properties of LWIC be
determined and quality control be maintained?
- By establishing
- Wet density (cast density)
- Fastener pull out resistance
- Compressive strength
- Dry density
- Walkability
29Wet density (cast density)
- Determined during installation.
- Is an indication of correct batch mix.
- NOA gives an acceptable range in pcf.
- To establish, fill a container of a known volume
and weigh. - Foam densities for cellular LWIC can also be
established. - Which weighs more, 1 ft.3 of water or 1 ft.3 of
LWIC?
30NRDCA procedures for establishing cast densities.
- Weigh an empty cast density container of known
volume. Knowing volume is critical. - Container must not distort when filled, or
volume of container will be altered. Galvanized
container is recommended. - Fill the container directly from the hose.
- Scrape the top with a straight edge.
- Wipe outside of container clean.
- Weigh the full container and subtract the empty
weight of the container.
31NOA requirements.
- Cast density container must a minimum of 5
quarts. (NRDCA 10 quart) - To weigh use a calibrated scale accurate from
1-50 lbs. - Scale must display in ΒΌ lb. increments.
- Scale must be accurately calibrated to 1/16 lb.
- Cast densities must be taken hourly and entered
in the job log. (NRDCA 30 min.) - NOA shows required cast densities in PCF.
32Cast density measurement about to taken. A 5
quart plastic container is to be used.
33Calibrating cast density container.
- Using a 10 Qt. galvanized container.
- Empty weight 2.00 pounds
- Weight filled w/water 23.50 pounds
- Net weight of water 21.50 pounds (23.5
2) - Calibration factor 2.9 pails per ft.3
(62.4/21.5) - By volume 21.5/62.4 0.34 ft.3
-
34Cast density example. Using info from previous
slide.
- 14.6 2(empty weight) 12.6 lbs
- 12.6 x 2.9 (calibration factor) 36.54
- Cast Density 36.54 PCF.
- Compare this figure to the cast density range
shown in the NOA. NOA must be in the job log. - If the measurement falls within the range then
cast density is acceptable.
35Table is found in the LWIC Notice of Acceptance
36.54 pcf From Previous Slide
36Further cast density information per NRDCA.
- Container calibration should be checked monthly.
Volume could be changed by dents in container or
accumulation of dried LWIC in the container. - If calibration factor changes by more than 3,
replace the container.
37Fastener withdrawal resistance
- 1917.4.10 requires that new pours achieve a
fastener pull of 40 lbf at the time of roofing or
60 lbf after 28 days. - Pull out values are assumed to increase over
time. - Fastener pullout test is required for existing
LWIC decks. - Test per TAS 105. TAS 105-8.3 The number of test
samples required shall be increased by an
additional 25 for LWIC decks.
38Compressive strength requirements
- Minimum after 28 days for cellular is 160 psi for
nailed system and 250 psi for adhered systems.
(1917.4.3) - 300 psi LWIC is typically required for fully
adhered roof systems per NOA. - How is enhancing the strength of LWIC
accomplished? - Is this requirement identified at the plans
processing stage?
39Compressive strength
- Methods for determining strength
- ASTM C 495 Standard test method for compressive
strength of LWIC. (1917) - ASTM C 796 (1917)
- ASTM C 513 Obtaining and testing specimens of
hardened LWIC for compressive strength may be
used for existing LWIC installations.
40Table is found in the LWIC Notice of Acceptance
41Container for collecting compressive strength
cylinders.
42Dry density
- Dry density ranges are found in the NOA.
- Samples of new pour are allowed to cure 28 days.
- Samples are oven dried.
- Divide volume by weight to establish dry density
43Table is found in the LWIC Notice of Acceptance
44Walkability test
- 1917.1.4 Walkability. A term defining the ability
of lightweight insulating fill to withstand
anticipated construction traffic during the roof
membrane application without significant
indentations in the lightweight insulating
concrete fill surface. - 1917.2.4 Building Official is to have clear
access and path to perform this test 24 hours
after the pour.
45What happens if a test fails?
- If walkability fails NOA- Ask for additional
testing to establish fastener spacing. - NOA- If fasteners fail to hold 40 lbf after
curing 5 days, such areas of the deck shall be
removed and recast. - Wet and dry density and compressive strength must
meet NOA and code requirements.
46Is a permit required for the installation of LWIC?
- Section 104.1.1 requires a permit.
- Permits are being required by various
municipalities. - Licensure requirements.
- 1917.2.1 Application of all lightweight
insulating concrete fill roof decks shall be by
applicators approved by the lightweight
insulating concrete deck manufacturer. - Who is the permit holder?
47Is an inspection of the LWIC installation
required?
- Permit Holder must notify the Building Official
48 hours before pouring. - Permit Holder must make available the job log.
- Inspection criteria is given in 1917.2.2, (3) and
(4).
48Job log
- 1917.2.3 The permit holder shall make available
to the Building Official a job log with the
following minimum items. - 1. Cast density recordings/hour
- 2. Product evaluation for application
- 3. Date and job locations identified
- 4. Results of any field test conducted.
49When LWIC is poured over an existing roof
assembly.
- 1519.5.3.1 Lightweight concrete shall not be
applied over an existing roof deck unless the
supporting structure has been approved as
adequate to sustain the added weight.
Calculations verifying the adequacy of the
existing structure to sustain the added weight
shall be prepared, signed, sealed and dated by a
Florida-registered architect or engineer,which
architect or engineer is proficient in structural
design, and submitted with the Uniform Roofing
Permit Application.
50When LWIC is poured over an existing roof
assembly. (Cont.)
- 1917.3.1 Existing roof assemblies to receive
lightweight insulating concrete fill other than
galvanized G-90 steel deck or structural concrete
deck shall be tested for uplift for adhesion to
the substrate to confirm compliance with design
pressure. - Testing per TAS 124 to meet design pressures and
TAS 126 for moisture in the existing roof system.
(1521.10 and 12)
51When LWIC is poured over an existing roof
assembly. (Cont.)
- Preparation steps, per NRDCA.
- Remove dirt, algae, loose gravel, and any other
loose material. - Repair blisters.
- Remove any large deposits of oil, grease, acid or
other contaminants.
52Reroofing LWIC deck. Fasteners remain and are
flattened
53Can roof systems be adhered directly to LWIC?
- In some cases. Check the roof system NOA,
however - 117-6.2 Rigid roof insulation panels shall not be
applied directly over lightweight concrete decks. - 109-15.4 Spray applied polyurethane foam shall
not be applied to lightweight insulating
concrete.
54Expansion Joints
- 1917.4.11 Lightweight insulating concrete fill
system expansion joint shall be provided at the
following locations - 1. Where expansion or contraction joints are
provided in the structural assembly - 2. Where steel framing, structural steel, or
decking change direction - 3. Where separate wings of "L", "U", "T" or
similar configurations exist - 4. Where the type of decking changes (for
example, where a precast concrete deck and a
steel deck abut) - 5. Whenever additions are connected to existing
buildings - 6. At junctions where interior heating conditions
change - 7. Wherever differential movement between
vertical walls and the roof deck may occur.
55Woodblocking Attachment
- 2330.1.3 Wood blocking attachment for lightweight
insulating concrete, gypsum concrete,
cementitious wood fiber and cellular concrete
decks shall be designed by a Registered Architect
or Professional Engineer. The deck itself shall
not be used as a wood blocking attachment
substrate.
56Woodblocking (Cont.)
- 111-3.8.2 Lightweight decks should not be used as
a woodblocking attachment substrate unless - The selected woodblocking anchor is fastened to
the underside of the deck or attached directly to
a structural member. - The selected woodblocking anchor can achieve an
average withdrawal resistance of not less than
450 lbf tested in compliance with TAS 105.