Title: Proton Plans at Fermilab Robert Zwaska Fermilab Science and Engineering at HendersonDUSEL Capstone W
1Proton Plans at Fermilab Robert Zwaska -
Fermilab Science and Engineering at
Henderson-DUSEL Capstone WorkshopStony Brook
UniversityMay 5, 2006
Outline
- Introduction to the accelerator complex
- Planned and possible upgrades
- Proton power projections
2Making Neutrino Beams
- Two operating beams at Fermilab
- Use 8 or 120 GeV protons
- Secondaries produced with solid target and
focused - A rough figure of merit proton power on target
- Average current Beam energy
- 120 GeV beam does better
- Other factors (not covered)
- Neutrino beam elements design
- Detector size design
NuMI
3(No Transcript)
4The Main Injector Today
- Provides high power, 120 GeV proton beam
- 80 kW for antiproton production
- 170 kW for neutrino production
- Takes 6 or 7 batches from the 8 GeV Booster _at_ 15
Hz - 4-5 1012 protons per Booster batch
- Total cycle time 1.467 s batches/15
Booster
NuMI
Batch 1 (PBar)
Batch 2
Batch 6
Main Injector
Batch 3
Batch 5
Batch 4
5Past-Year NuMI Running
- Average power of 165 kW in the last few months
- Maximum beam power of 270 kW down the NuMI line
(stably for ½ hour) - Peak intensity of 31013 ppp on the NuMI target
300
200
6Slip-stacking (Proton Plan)
- Merge two booster batches through RF
manipulations
K. Seiya et. al., PAC2003
- Doubles the azimuthal charge in the Main
Injector - Booster loading time is doubled
? 440 kW of protons
7SnuMI Recycler as an 8 GeV proton accumulator
D. McGinnis, Beams-doc-1782, 2138
- After the Collider program is terminated, we can
use the Recycler as a proton accumulator - Booster batches are injected at 15 Hz rep rate
- Accumulate protons from the Booster while MI is
running - save 0.4 s for each 6 Booster batches injected
- Can also slip-stack beam in the Recycler
- Up to 12 Booster batches injected (save 0.8 s)
- 5.41013 ppp every 1.467 s ? 700 kW
8SNuMI Momentum stacking in the Accumulator
D. McGinnis, Beams-doc-1782, 2138
- After the Collider program is terminated, we can
also use the Accumulator in the Anti-proton
Source as a proton accumulator - Momentum stack 4 (3) Booster in Accumulator
batches every 267 (200) ms - Limit Booster batch size to 41012 protons
- Box Car stack in the Recycler
- Load in a new Accumulator batch every 267 (200)
ms - 6 Accumulator (24 or 18 Booster) batches
- in Recycler
- Load the Main Injector in a single turn
- 9.11013 every 1.6 s ? 1.1 MW
- 7.21013 every 1.33 s ? 1.0 MW
9High Intensity Neutrino Source
- 8 GeV Superconducting Linac as replacement for
Booster - Nominal injection charge 1.51014 ppp
- Cycling every 1.4 s corresponds to a beam power
of 2 MW at 120 GeV - Requires major upgrades to Main Injector RF
- Significant MI RF and magnet upgrades could
reduce acceleration time - Maybe up to 4 MW
10Proton Power Projections
Note 1.7107 s/yr (effective, at peak power)
- Proton plan (in progress)
- Ramp to 440 kW in 2009
- Recycler/Accumulator upgrades (in design not
approved yet) - One year shutdown in 2010
- Ramp to 1.1 MW (700 kW) in 2012
- High Intensity Neutrino Source (under
consideration) - 2 MW sometime in the future
11Lowering the primary proton energy ?
- Injection dwell time 80 ms
- Flattop time 50 ms
- Maximum dp/dt 240 GeV/s
D. Wolff
- this is achievable now (conservative)
- limit injection dwell time to 30 ms ?
- faster down ramp ?
12Proton Energy Scaling
- Reducing proton beam energy does not results in
an equal reduction in cycle time - Worst for cases where Booster is heavily utilized
- Neutrino beams based on lower-energy protons will
have lower beam power
13Conclusions
- Fermilab proton complex can be upgraded to
produce a Neutrino Superbeam - 320 kW peak (250 kW ave.) available today
- 440 kW upgrades are in progress
- Proton Plan ? E. Prebys et al.
- 700 kW 1.1 MW upgrades are under study
(likely?) - SNuMI ? A. Marchionni et al.
- 2 MW beams are under consideration
- HINS ? G. Appolinari et al.
- Primary proton energy needs to be understood
- Lowering proton energy below 120 GeV always
reduces the beam power on target - Neutrino beam production needs to be considered
- There is no beamline to Henderson
- Does not need to be a conventional beam
- Neutrino Factory (A. Tollestrup et al.)
- Beta Beam (A. Jansson)