Proton Plans at Fermilab Robert Zwaska Fermilab Science and Engineering at HendersonDUSEL Capstone W - PowerPoint PPT Presentation

1 / 13
About This Presentation
Title:

Proton Plans at Fermilab Robert Zwaska Fermilab Science and Engineering at HendersonDUSEL Capstone W

Description:

A rough figure of merit: proton power on target. Average current Beam energy ... Maximum dp/dt 240 GeV/s. 120 GeV, 1.34 s. 50 GeV, 0.81 s. 40 GeV, 0.73 s. 30 ... – PowerPoint PPT presentation

Number of Views:41
Avg rating:3.0/5.0
Slides: 14
Provided by: Robert1010
Category:

less

Transcript and Presenter's Notes

Title: Proton Plans at Fermilab Robert Zwaska Fermilab Science and Engineering at HendersonDUSEL Capstone W


1
Proton Plans at Fermilab Robert Zwaska -
Fermilab Science and Engineering at
Henderson-DUSEL Capstone WorkshopStony Brook
UniversityMay 5, 2006
Outline
  • Introduction to the accelerator complex
  • Planned and possible upgrades
  • Proton power projections

2
Making Neutrino Beams
  • Two operating beams at Fermilab
  • Use 8 or 120 GeV protons
  • Secondaries produced with solid target and
    focused
  • A rough figure of merit proton power on target
  • Average current Beam energy
  • 120 GeV beam does better
  • Other factors (not covered)
  • Neutrino beam elements design
  • Detector size design

NuMI
3
(No Transcript)
4
The Main Injector Today
  • Provides high power, 120 GeV proton beam
  • 80 kW for antiproton production
  • 170 kW for neutrino production
  • Takes 6 or 7 batches from the 8 GeV Booster _at_ 15
    Hz
  • 4-5 1012 protons per Booster batch
  • Total cycle time 1.467 s batches/15

Booster
NuMI
Batch 1 (PBar)
Batch 2
Batch 6
Main Injector
Batch 3
Batch 5
Batch 4
5
Past-Year NuMI Running
  • Average power of 165 kW in the last few months
  • Maximum beam power of 270 kW down the NuMI line
    (stably for ½ hour)
  • Peak intensity of 31013 ppp on the NuMI target

300
200
6
Slip-stacking (Proton Plan)
  • Merge two booster batches through RF
    manipulations

K. Seiya et. al., PAC2003
  • Doubles the azimuthal charge in the Main
    Injector
  • Booster loading time is doubled

? 440 kW of protons
7
SnuMI Recycler as an 8 GeV proton accumulator
D. McGinnis, Beams-doc-1782, 2138
  • After the Collider program is terminated, we can
    use the Recycler as a proton accumulator
  • Booster batches are injected at 15 Hz rep rate
  • Accumulate protons from the Booster while MI is
    running
  • save 0.4 s for each 6 Booster batches injected
  • Can also slip-stack beam in the Recycler
  • Up to 12 Booster batches injected (save 0.8 s)
  • 5.41013 ppp every 1.467 s ? 700 kW

8
SNuMI Momentum stacking in the Accumulator
D. McGinnis, Beams-doc-1782, 2138
  • After the Collider program is terminated, we can
    also use the Accumulator in the Anti-proton
    Source as a proton accumulator
  • Momentum stack 4 (3) Booster in Accumulator
    batches every 267 (200) ms
  • Limit Booster batch size to 41012 protons
  • Box Car stack in the Recycler
  • Load in a new Accumulator batch every 267 (200)
    ms
  • 6 Accumulator (24 or 18 Booster) batches
  • in Recycler
  • Load the Main Injector in a single turn
  • 9.11013 every 1.6 s ? 1.1 MW
  • 7.21013 every 1.33 s ? 1.0 MW

9
High Intensity Neutrino Source
  • 8 GeV Superconducting Linac as replacement for
    Booster
  • Nominal injection charge 1.51014 ppp
  • Cycling every 1.4 s corresponds to a beam power
    of 2 MW at 120 GeV
  • Requires major upgrades to Main Injector RF
  • Significant MI RF and magnet upgrades could
    reduce acceleration time
  • Maybe up to 4 MW

10
Proton Power Projections
Note 1.7107 s/yr (effective, at peak power)
  • Proton plan (in progress)
  • Ramp to 440 kW in 2009
  • Recycler/Accumulator upgrades (in design not
    approved yet)
  • One year shutdown in 2010
  • Ramp to 1.1 MW (700 kW) in 2012
  • High Intensity Neutrino Source (under
    consideration)
  • 2 MW sometime in the future

11
Lowering the primary proton energy ?
  • Injection dwell time 80 ms
  • Flattop time 50 ms
  • Maximum dp/dt 240 GeV/s

D. Wolff
  • this is achievable now (conservative)
  • limit injection dwell time to 30 ms ?
  • faster down ramp ?

12
Proton Energy Scaling
  • Reducing proton beam energy does not results in
    an equal reduction in cycle time
  • Worst for cases where Booster is heavily utilized
  • Neutrino beams based on lower-energy protons will
    have lower beam power

13
Conclusions
  • Fermilab proton complex can be upgraded to
    produce a Neutrino Superbeam
  • 320 kW peak (250 kW ave.) available today
  • 440 kW upgrades are in progress
  • Proton Plan ? E. Prebys et al.
  • 700 kW 1.1 MW upgrades are under study
    (likely?)
  • SNuMI ? A. Marchionni et al.
  • 2 MW beams are under consideration
  • HINS ? G. Appolinari et al.
  • Primary proton energy needs to be understood
  • Lowering proton energy below 120 GeV always
    reduces the beam power on target
  • Neutrino beam production needs to be considered
  • There is no beamline to Henderson
  • Does not need to be a conventional beam
  • Neutrino Factory (A. Tollestrup et al.)
  • Beta Beam (A. Jansson)
Write a Comment
User Comments (0)
About PowerShow.com