Title: RF Gun Status LCLS Facility Advisory Committee Meeting October 26, 2005
1RF Gun StatusLCLS Facility Advisory Committee
MeetingOctober 26, 2005
- Mechanical design review (08/05)
- Commissioning plan
- Cathode development
- Response to FAC recommendations
2RF Gun Mechanical Design Review
- Presentation of mechanical design with RF and
thermal simulations. - Mechanical design commended by review committee.
- Concerns
- Heating at cathode/gun RF joint and coupler
irises. - Damage from high flow in cooling channels.
- Recommendations
- Improve cooling design.
- RF reflection in waveguide pumping slots
acceptable. - Make two guns with tree sets of parts.
- Start load lock development program.
- Response
- Water flow rate lowered.
- Radii on ports increased to limit pulse heating.
- Cathode plate thickened.
3Gun and Solenoid
Courtesy of E. Jongewaard
4Water Flow Velocity Reduction
Courtesy of E. Jongewaard
5Gun Commissioning Schedule
- Fabrication - 01/06
- Scheduled in SLAC Klystron department.
- Cold test - 04/06
- Characterize gun.
- Bead pull/drop measurement (use dummy cathode?).
- Cathode plate tuning with 1st cathode.
- Cathode preparation - 06/06
- Characterize 2nd cathode.
- QE measurement, H ion cleaning.
- Measure surface roughness contaminants.
- Gun Solenoid integration - 06/06
- Assemble on common girder.
- Magnetic measurement with dummy cathode.
- Install cleaned 2nd cathode and retune.
- Hot test - 08/06
- Details follow.
- Installation commissioning at S20 - 12/06
- See next presentation.
6RF Gun Preparation
- Part of injector commissioning schedule
7Gun Hot Test
- Objectives
- Vacuum bake to 10-10 Torr.
- Stable 120 MV/m operation.
- Demonstrate 130 MV/m.
- Demonstrate 120 Hz operation (3.5 kW thermal
load). - Measure thermal distribution with low high RF
power. - Measure Cell field balance at high RF power.
- Procedure
- Install assembly in Klystron department and bake.
- RF processing.
- Full characterization.
- Test temperature control?
8Gun Hot Test Setup
- Hardware from GTF
- YAG/FC
- Solenoid power supply
- Thermal management
- Cooling without temperature feedback
- Track RF frequency with gun temperature
- Controls
- LLRF
- Parameter logging
- Algorithm for automatic processing
Gun
Valve
YAG/FC
Pump
To Klystron
Wave Guide
Solenoid
Pump
9Measurements for Gun Conditioning
- Gun temperatures (RTDs)
- W/G and FC vacuum pressure
- Klystron drive power
- Gun forward/reflected power
- Half and full cell probes
- Dark current in FC
- Image of dark current (YAG)
- RF breakdowns
10Open Issues
- Hot test schedule and location
- PEP test bunker in Klystron Department
- Available 08/06
- Sector 20
- Before, during, or after 2006 downtime
(08/06-11/06) - More details in next presentation
- Cooling water for gun
- Stand alone 4 kW chiller?
- Use facility water?
11Cathode Development
- Presently no process to improve and control QE of
LCLS cathodes. - No load lock in LCLS budget.
- Need for improved cathode installation procedure.
- Operational contamination requires in-situ
cleaning. - Avoid risky gun baking and laser cleaning
Courtesy of D. Dowell
12In-Situ Cleaning Methods
- H-beam cleaning
- Use 1keV H-beam.
- Cleans 1cm diameter area.
- Requires no reconfiguration of gun system.
- Benign to cathode surface.
- H-plasma cleaning
- Produce plasma inside gun volume.
- Plasma excitation with RF
- Only cleans region of high E-field.
- Plasma excitation with DC
- Only cleans region near electrodes.
13H-Beam Cleaning Results Installation on Gun
Experimental results from SLAC Physical
Electronics Lab
See D. Dowell et al., FEL2005 Conf.
14Proposed Three Step Plan
- Compare cathode surface processing with H-beam
vs. H-plasma. - Find best procedure to clean, transfer, and
install cathodes for LCLS gun 1. - Develop in-situ cleaner for LCLS gun 2.
- Thermal emittance measurement not part of this
plan.
15Laboratory Test (Part 1)
- Goals
- Comparison of H-beam and H-plasma cleaning.
- Find optimum materials and fabrication
techniques. - Simulation of cathode transfer and installation
effects. - Compare with theory.
- Plan
- Testing of small samples in SLAC PE lab.
- Uses existing surface diagnostics equipment.
- Construct H-plasma cleaner.
- Result
- Capability for H-beam and H-plasma cleaning
measured data.
16Cathode Cleaning and GTF Test (Part 2)
- Goals
- Test robustness of cleaned cathodes for
installation procedure and improve procedure for
LCLS. - Quantify effect of gun bake on QE.
- Plan
- Characterization and H-beam cleaning of GTF
cathodes in SLAC PE lab. - Transfer and test cathodes in GTF gun.
- Compare lab QE measurement with operational QE.
- Result
- Improved procedure for installing well
characterized, clean LCLS cathodes.
17In Situ Cleaning for LCLS Gun 2 (Part 3)
- Goals
- Design and build cleaner system for LCLS Gun 2.
- Find operating parameters for H source.
- Plasma cleaning with RF, compare with bake.
- Plan
- Install and test system on existing chamber in PE
lab. - Move system to LCLS Gun 2 and test.
- Test with RF?
- Result
- Complete gun assembly with cleaner ready for
installation at Sector 20.
18Funding Status
- BCR requested for part 1.
- BCR in preparation for part 2.
- Request for part 3 when results from parts 1 and
2 available.
19Response to FAC Recommendations
- Completion of second gun encouraged.
- Fabrication of second gun scheduled with first
gun. Will be available as complete system with
solenoid as fast backup at sector 20. - Investigate gun wake field effects.
- Large energy spread in GTF gun contributed to
pi-0 mode beating. Should not occur in LCLS gun
with 15 MHz mode separation. PIC simulations
planned for next year. - Continue effort on H ion cleaning of cathode.
- Budget modified to pursue cleaning and test on
second gun. - Develop permanent facility for gun testing.
- No decision made yet, but funding for GTF
continued through FY2006.
20Summary
- Gun mechanical design completed.
- Fabrication of gun scheduled.
- Commissioning plan in progress.
- Funding for cathode development underway.