Title: Flood analysis in the Var catchment
1 Flood analysis in the Var catchment
Viktoria Bondarets (Cottbus), Benoit Brugeilles
(Nice), Jocelyn Fortune (Nice), Julien Frachisse
(Nice), Iglika Gentcheva (Cottbus), Celine Noel
(Nice)
2Introduction
- Var flooding
- Hydro-europe cooperation
- Modelling software
MIKE 11 MIKE SHE ?
3Monday, 24/02/03
- General description
- life seemed to be sweet (probably thanks to
- the delicious Belgium chocolate and the
- starting optimism of the participants)
4Monday, 24/02/03
- Activities Comparison the real discharges
measured on the - var during the flooding of november 1994 with the
ones - obtained in the MikeShe simulation on a 300 m
dimension - DEM
Conclusion cell dimensions of the grid are too
big to obtain the precise results recomputation
is necessary
5Monday, 24/02/03
6Tuesday, 25/02/03
- General description
- we understood what PROBLEM meant. We
- did not like it!
7Tuesday, 25/02/03
- Activities Usage of Digital Elevation Model
(DEM) of the - Topography (MIKE SHE) to design the rivers cross
sections - according to the relief and elevation data.
- Methodology
- Identification of the relation between MIKE11 and
MIKE SHE geographical references. - In MIKE 11, quotation of the (xy) coordinates of
the cross section with the necessity of redesign - In MIKE SHE elevation model, select the (xyz)
coordinates of each pixel around the profile to
calculate its two slopes and its minimum
elevation.
8Topography DEM (300 m) from MIKE SHE
9Tuesday, 25/02/03
Cross-sections are located in the lowest
intersection point with the vertical Two average
slopes calculated for each side and applied to
the cross-sections
10Tuesday, 25/02/03
Cross-section definition in EXCEL (according to
the local topography)
11Tuesday, 25/02/03
12Wednesday, 26/02/03
- General description
- first dawn- to- dusk day.
- The team was kept busy by calculations from
- 9 a.m. till 7 p. m. (here we will not mention
- that we had a 1,5-hour break and that Team 4
- stayed much longer.Just to produce more
- dramatic effect!)
-
13Wednesday, 26/02/03
- Activities division in two different groups to
compare different - ways of cross- section derivation
- The first sub team - the upstream slope,
- The second - the downstream slope
14Wednesday, 26/02/03
Final results
15Thursday, 27/02/03
- General description
- the number of participants in our team has
- pleasantly increased. The amount of work
- needed to be done increased as well. Not very
- pleasantly...
16Thursday, 27/02/03
- Activities based on the existing network the
previously - defined cross-sections were inserted at the
places chosen as - being the most representative for the
longititudinal profile of - the network.
17Thursday, 27/02/03
- One point at each change of the slope was
selected
18Thursday, 27/02/03
- Method
- - Simulation with only 6 sections
- - Increase the number of Cross-Sections (17)
19Thursday, 27/02/03
- Simulation conditions
- - Time step dt10 s.
- - Space step dx300 m.
- - Initial Conditions
- . Qo 300 m3/s
- . Ho 0 m.
- - Simulation using SteadyParameter
- - Kinematic wave
20Thursday, 27/02/03
21Thursday, 27/02/03
Discharge results
22THANK YOU FOR YOUR ATTENTION
23(No Transcript)
24(No Transcript)
25(No Transcript)
26(No Transcript)