Baltic Electricity Market Forum - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Baltic Electricity Market Forum

Description:

Investment in new interconnection has been very low. ... Nordel undertakes cost benefit analyses to assess potential investments, but ... – PowerPoint PPT presentation

Number of Views:77
Avg rating:3.0/5.0
Slides: 15
Provided by: eho59
Category:

less

Transcript and Presenter's Notes

Title: Baltic Electricity Market Forum


1
Baltic Electricity Market Forum Developing
transmission networks to serve market integration
Jan Sundell EURELECTRIC Vilnius, 29 May 2008
2
EURELECTRIC Key Priorities
1. Liberalisation Process Contribute to
the creation of a pan-European energy
market through harmonisation and industry action


2. Pan-European Context Contribute to a
good business environment and to the
integration of the Electricity Industry at
international level

3. Sustainable Development Promote the
role of electricity and electrotechnologies as
part of the solution to the global
environmental problem systematically
integrate sustainable development policies
in key strategies and actions promote
market-oriented policies
3
EURELECTRIC Structure
SG Regional Transmission Investment Incentives
4
Shortcomings in present situation
  • TSOs are seldom tasked to develop regional
    markets in electricity law or company statutes
    explicitly
  • National Regulators are considering national
    benefits only, based on national legislation, in
    many cases
  • In some countries the allowed return on
    investments is too low for transmission
    investments to be attractive for investors
  • Lines are not built because of licensing problems
  • Investment in new interconnection has been very
    low. A 2006 report from the European Commission
    concluded that
  • Amounts invested in cross-border infrastructure
    in Europe appear dramatically low. Only 200
    million yearly is invested in electricity grids
    with as main driver the increase of cross-border
    transmission capacity.

5
Challenges
  • The consideration of existing and forecasted
    generation and consumption location in network
    planning, whereby the renewable wind off-shore
    generation will in particular not be located
    close to the centres of demand!
  • The complexity of authorisation procedures for
    building new grids, and
  • the additional costs for underground cables
  • The importance of ensuring that TSOs and National
    Regulators act with a regional mindset when
    determining their investment programmes.

6
Is Ownership Unbundling the answer?
7
EU initiatives so far
  • Cross-border regulation 1228/2003
  • use the congestion rents
  • to guarantee allocated capacities
  • and to fund increases in available cross-border
    capacity,
  • however it is also allowed to use the congestion
    income for reducing national network tariffs.
  • merchant interconnectors can be exempted from
    regulation of both access requirements and
    tariffs.
  • There was also a political commitment statement
    to requiring that each Member State should have a
    minimum level of interconnection equal to 10 of
    installed generation capacity
  • The Commission adopted a priority
    interconnection plan, providing some (small)
    funding for certain interconnections
  • The Commission appointed 4 experts together with
    mechanisms intended to lessen political and
    bureaucratic obstacles for a small set of to
    facilitate 4 key strategic projects (whom 3 in
    power).

8
Evolution congestion income and social welfare
due to a XB investment (simplified example)
9
Case study the Nordic Region (1)
  • The Nordic TSOs have a close cooperation in
    Nordel where they have created a grid code
    including system planning, however the grid code
    is non-binding, and includes an explicit
    recognition that it must be subordinate to the
    national rules in the various Nordic countries
  • Nordel has a permanent committee, the Nordic
    Planning Committee, responsible for producing and
    updating a top-down analysis of the overall
    needs of the Nordic region, the Nordic Grid
    Master Plan.
  • Nordel makes recommendations for specific
    investments on the basis of the Master Plan.
    These recommendations are non-binding, and the
    process itself is relatively informal, because
    all co-operation between the Nordic TSOs is on a
    voluntary basis. Nordel undertakes costbenefit
    analyses to assess potential investments, but
    these are not published.
  • National TSOs then make their own transmission
    plans. The plans reflect a mix of national and
    Nordic criteria
  • The Nordel process is also now evolving to allow
    for multi-regional planning, to include links
    with the Baltics and Central Europe.

10
Case study the Nordic Region (2)
  • The inter-TSO coordination occurs on an entirely
    voluntary basis, and with limited ability for
    TSOs to be financially compensated for
    investments that provide benefits outside their
    own area.
  • A number of factors make the regional planning
    system more likely to succeed in the Nordic
    region than elsewhere
  • There is a strong political will to create and
    sustain an integrated Nordic market and there is
    a strong history of Nordic co-operation in many
    areas
  • The diversity of generation, and in particular
    the prevalence of hydro in some countries and
    thermal generation in others
  • There is an ongoing discussion on how efficient
    the voluntary arrangement is and market
    participants want a more transparent process
  • Preliminary Conclusions Other Regions should
    follow similar approach but more stakeholders
    involvement and transparency is needed

11
Inter TSO compensation
  • The inter TSO Compensation (ITC) is not giving
    significant incentives for cross-border
    transmission investments due to
  • The current ITC mechanism is still based on a
    voluntary and year-by-year interim agreement
    between TSOs rather than a long-term decision by
    the Commission or ERGEG.
  • ITC is looking at historical investments and not
    at giving incentives to new cross-border
    investments

12
Proposed model for Regional Transmission
Investments (1)
  • Transmission investments with positive socio
    economic gain on a regional basis should be
    built.
  • There has to be a socio economic welfare gain for
    each country that exceeds the national costs of
    that particular investment.
  • In order to secure investments that have positive
    socio-economic benefit for a regional as a whole
    but not for one or several nations, some sort of
    additional mechanism must be put in place.

13
Proposed model for Regional Transmission
Investments (2)
  • Existing models account only for some of the
    costs and benefits
  • A model calculating the overall socio-economic
    benefits is needed
  • The model must be common for the region and
    ideally for the whole of Europe
  • Investments bring socio-economic welfare value
    if
  • ? COSTS lt ? BENEFITS
  • Where
  • CHANGE OF COSTS includes (capital,
    environmentally related, operational and
    maintenance)
  • CHANGE OF BENEFITS includes
  • (congestion rents, producer and consumer
    surplus, system losses, security of supply,
    supply quality, cost of system operation, cost
    of congestion management, environmental
    improvement)

14
Proposed model for Regional Transmission
Investments (3)
  • We urge regulators and TSOs to come up with
    simplified and transparent models that give a
    fair indication of the socio-economic benefits
    from different investment scenarios and give also
    a fair indication on the burden sharing between
    markets of the investments.
  • Gradually, such a model can be refined and
    improved
  • Much more important is the common approval from
    all (regional and inter-regional) involved
    regulators and a common use of all involved TSOs.
  • EURELECTRIC believes here that the regional
    overview should be in hands of the Agency (as
    proposed under the third package)
  • Market stakeholder involvement is of the utmost
    importance scenarios should be driven by their
    indications
Write a Comment
User Comments (0)
About PowerShow.com