Title: Baltic Electricity Market Forum
1Baltic Electricity Market Forum Developing
transmission networks to serve market integration
Jan Sundell EURELECTRIC Vilnius, 29 May 2008
2EURELECTRIC Key Priorities
1. Liberalisation Process Contribute to
the creation of a pan-European energy
market through harmonisation and industry action
2. Pan-European Context Contribute to a
good business environment and to the
integration of the Electricity Industry at
international level
3. Sustainable Development Promote the
role of electricity and electrotechnologies as
part of the solution to the global
environmental problem systematically
integrate sustainable development policies
in key strategies and actions promote
market-oriented policies
3EURELECTRIC Structure
SG Regional Transmission Investment Incentives
4Shortcomings in present situation
- TSOs are seldom tasked to develop regional
markets in electricity law or company statutes
explicitly - National Regulators are considering national
benefits only, based on national legislation, in
many cases - In some countries the allowed return on
investments is too low for transmission
investments to be attractive for investors - Lines are not built because of licensing problems
- Investment in new interconnection has been very
low. A 2006 report from the European Commission
concluded that - Amounts invested in cross-border infrastructure
in Europe appear dramatically low. Only 200
million yearly is invested in electricity grids
with as main driver the increase of cross-border
transmission capacity.
5Challenges
- The consideration of existing and forecasted
generation and consumption location in network
planning, whereby the renewable wind off-shore
generation will in particular not be located
close to the centres of demand! - The complexity of authorisation procedures for
building new grids, and - the additional costs for underground cables
- The importance of ensuring that TSOs and National
Regulators act with a regional mindset when
determining their investment programmes.
6Is Ownership Unbundling the answer?
7EU initiatives so far
- Cross-border regulation 1228/2003
- use the congestion rents
- to guarantee allocated capacities
- and to fund increases in available cross-border
capacity, - however it is also allowed to use the congestion
income for reducing national network tariffs. - merchant interconnectors can be exempted from
regulation of both access requirements and
tariffs. - There was also a political commitment statement
to requiring that each Member State should have a
minimum level of interconnection equal to 10 of
installed generation capacity - The Commission adopted a priority
interconnection plan, providing some (small)
funding for certain interconnections - The Commission appointed 4 experts together with
mechanisms intended to lessen political and
bureaucratic obstacles for a small set of to
facilitate 4 key strategic projects (whom 3 in
power).
8Evolution congestion income and social welfare
due to a XB investment (simplified example)
9Case study the Nordic Region (1)
- The Nordic TSOs have a close cooperation in
Nordel where they have created a grid code
including system planning, however the grid code
is non-binding, and includes an explicit
recognition that it must be subordinate to the
national rules in the various Nordic countries - Nordel has a permanent committee, the Nordic
Planning Committee, responsible for producing and
updating a top-down analysis of the overall
needs of the Nordic region, the Nordic Grid
Master Plan. - Nordel makes recommendations for specific
investments on the basis of the Master Plan.
These recommendations are non-binding, and the
process itself is relatively informal, because
all co-operation between the Nordic TSOs is on a
voluntary basis. Nordel undertakes costbenefit
analyses to assess potential investments, but
these are not published. - National TSOs then make their own transmission
plans. The plans reflect a mix of national and
Nordic criteria - The Nordel process is also now evolving to allow
for multi-regional planning, to include links
with the Baltics and Central Europe.
10Case study the Nordic Region (2)
- The inter-TSO coordination occurs on an entirely
voluntary basis, and with limited ability for
TSOs to be financially compensated for
investments that provide benefits outside their
own area. - A number of factors make the regional planning
system more likely to succeed in the Nordic
region than elsewhere - There is a strong political will to create and
sustain an integrated Nordic market and there is
a strong history of Nordic co-operation in many
areas - The diversity of generation, and in particular
the prevalence of hydro in some countries and
thermal generation in others - There is an ongoing discussion on how efficient
the voluntary arrangement is and market
participants want a more transparent process - Preliminary Conclusions Other Regions should
follow similar approach but more stakeholders
involvement and transparency is needed
11Inter TSO compensation
- The inter TSO Compensation (ITC) is not giving
significant incentives for cross-border
transmission investments due to - The current ITC mechanism is still based on a
voluntary and year-by-year interim agreement
between TSOs rather than a long-term decision by
the Commission or ERGEG. - ITC is looking at historical investments and not
at giving incentives to new cross-border
investments
12Proposed model for Regional Transmission
Investments (1)
- Transmission investments with positive socio
economic gain on a regional basis should be
built. - There has to be a socio economic welfare gain for
each country that exceeds the national costs of
that particular investment. - In order to secure investments that have positive
socio-economic benefit for a regional as a whole
but not for one or several nations, some sort of
additional mechanism must be put in place.
13Proposed model for Regional Transmission
Investments (2)
- Existing models account only for some of the
costs and benefits - A model calculating the overall socio-economic
benefits is needed - The model must be common for the region and
ideally for the whole of Europe - Investments bring socio-economic welfare value
if - ? COSTS lt ? BENEFITS
- Where
- CHANGE OF COSTS includes (capital,
environmentally related, operational and
maintenance) - CHANGE OF BENEFITS includes
- (congestion rents, producer and consumer
surplus, system losses, security of supply,
supply quality, cost of system operation, cost
of congestion management, environmental
improvement)
14Proposed model for Regional Transmission
Investments (3)
- We urge regulators and TSOs to come up with
simplified and transparent models that give a
fair indication of the socio-economic benefits
from different investment scenarios and give also
a fair indication on the burden sharing between
markets of the investments. - Gradually, such a model can be refined and
improved - Much more important is the common approval from
all (regional and inter-regional) involved
regulators and a common use of all involved TSOs.
- EURELECTRIC believes here that the regional
overview should be in hands of the Agency (as
proposed under the third package) - Market stakeholder involvement is of the utmost
importance scenarios should be driven by their
indications