Title: Design, Production,
1Design, Production, Shipping Status at FNAL
- Nelson Chester
- Fermilab
- March 4-8, 2002
- CERN EMU Meeting
2Outline
- Design Status
- Chamber Design
- Chamber Integration Design
- Configuration Control
- Procurement / Shipping Plans
- Chamber Related
- Integration Related
- Cooling Plates
- Other Parts
- FNAL Production Activities
- Panel production
- Chamber Production
- Configuration Releases
- Other FNAL Activities
3Design Status
- Chambers
- ME 234/2 CC Spr. 00
- ME 2/1 CC Jan. 02
- ME 1/2 CC Nov. 02
- ME 3/1 CC Apr. 02 ?
- ME 1/3 CC Jul. 02 ?
- ME 4/1 CC Sep. 02 ?
- Work started by V. Razmyslovitch mid Feb. 02.
Funded for 6 months (until mid
August02) - Probably will need longer time!!
- Chamber Integration
- CC Aug.00
- CC Dec. 01
- CC Nov. 02
- CC Apr. 02 ?
- CC Jul. 02 ?
- CC Sep. 02 ?
- Design Layout
- Prototype
- Design Finalization
- CC
4Configuration Control
- Chamber Configuration Control
- Needed to be able to provide PNPI/IHEP drawings
to the machine frame parts. - Needed to allow PNPI/IHEP to start relative
chamber production. - Cannot finalize Chamber Configuration until
Integration Configuration is finalized. - Integration Configuration Control
- Needed to allow FNAL and UW to begin parts
procurement
http//tdserver1.fnal.gov/project/uscmsemu/Config
uration_Control_Documents/Released_Configurations/
5Configuration Control (cont.)
- Communication to Foreign Sites
- Procedure in place to let foreign sites know
about released Configuration - Initial released Configuration transmitted by CD.
- Foreign site responsible to update drawings in
their possession if/when new Configurations are
approved. - Process (Travelers) Changes communication to
Foreign Sites - Procedure in place to let foreign sites know
about Assembly process changes at FNAL. - Initial released Configuration transmitted by CD.
- Foreign site responsible to translate and update
travelers in their possession for their own
purposes.
http//tdserver1.fnal.gov/project/uscmsemu/Releas
ed_Specifications/Chamber_Specifications/
6ME234/2 Cooling Plate Procurement
- All cooling plates (150) manufactured by Unique
and shipped to FNAL. - Half shipped to UF
- Balance being shipped to UCR and UCLA
7ME1/2 Cooling Plate Procurement
- All Cooling Plates Manufactured by Unique and
Shipped to Fermilab - Half Packed at
- Unique
- Half Packed at
- FNAL
8ME 2/1 Cooling Plate Procurement
- Quotes have Closed!
- Unique is MOST LIKELY low bid vendor.
- Bid is 860/plate vs 710 for ME1/2 and 735 for
ME234/2 - Larger Copper Plate must be procurred
- Different Furnace Vendor (Larger Furnace)
- Lower Quantity (38 vs 74 and 140 resp.) Tooling
and setup amortized over smaller quantity. - Exploring cost savings by procurring SAME Cooling
Plates NOW for ME 3/1. - Limited risk to place an order for these SAME
plates. - Belief is that ME 4/1 will also use SAME plate
but will NOT procure now because of funding
limits.
9Cooling Plates Budget vs Actual Cost
10Shipments Requested
- At FNAL
- ME1/2 Mechanical Parts (UW)
- ME2/1 AFEB-ALCT Cables (CM)
- ME1/2 CFEB (OS)
- ME1/2 Chamber-CFEB Cables (OS)
- ME2/1 CFEB (OS)
- ME2/1 Chamber-CFEB Cables (OS)
- Default approach
- CablesMechanical parts in oversea container
shipments. - i.e. ME2/1 AFEB-ALCT cables with ME3/1 Chamber
parts shipment. - Electronic by air.
- Oleg Prokofiev now tracking boxes through FNAL.
11PNPI Shipping Plans
- 2nd Shipment Last Week Feb. 02
- ME 3/1 Panels and Unique Parts
- ME 4/1 Unique Parts
- Remaining Tooling Test Equipment
- Production Aids
- HV Distribution Parts
- ME 2/1 Integration Cables
- ME 3/1 Integration Cables
- Integration Hardware
12PNPI Shipping Plans
- 3rd. Shipment May June 02
- ME4/1 Panels, Unique Parts
- ME2/1 Cooling Plates (possibly ME3/1 4/1 as
well) - Integration Parts and Hardware
- 4th. Shipment- June, 03
- Spare Chamber Parts
- ME3/1 (4/1) Cooling Plates (if not shipped
before) - Integration Parts and Hardware
13IHEP Shipping Plans
- 2nd. Shipment May - June, 02
- ME1/2 Cooling Plates
- ME1/2 Integration Parts and Hardware
- 3rd. Shipment Nov., 02
- ME1/3 Cooling Plates
- ME1/3 Integration Parts and Hardware
- 4th. Shipment June, - 03
- All remaining Parts and Hardware
14Shipping Instructions
- Instructions published for parts shipped to
Foreign Sites through FNAL, to be enforced by L3
Manager (A.K. obtained collaborator agreements). - Major points
- Pre-packed boxes not opened at FNAL.
- Full List of Parts attached on multiple sides of
the box. - Unit Value Weight on Outside
- Description of where the parts are to be shipped
with reference to which chamber it is going to
be used. - Etc.
http//tdserver1.fnal.gov/project/uscmsemu/Release
d_Specifications/Chamber_Specifications/
15Lab 8 Situation
- End of Jan. 2002 Panel Machining Snapshot
- (In units of Chambers) PLANNED
MACHINED - Ramp up (FY99) ME234/2 22 22
- ME234/2 126 122
- ME2/1 39 (?38) 36
- Production ME3/1 39 (?38) 36
- (FY00-01-02) ME1/2 74 72
- ME1/3 74 -
- (Re-Scoped) ME4/1 . 38
. 36 . - All Production Total 372 / 410
324 / 324 -
- Labor Charged totaled 413k of a budget of 478 k
or 86.4 spent. - Produced panels for 324 of a planned 372
chambers or 87.1.
16Lab 8 Factory Status
- Panel Machining in full-speed production as of
Jan 00 - Completed machining of ME234/2 panels (FNAL
Production) - Completed machining of ME2/1, ME3/1 ME4/1
panels (98 ofPNPI Production) - Completed machining of ME1/2 panels ( 50 of IHEP
Production) - Started machining ME1/3 panels (completion
expected by July 02) - Spares To Follow
-
17Lab 8 Situation (cont.)
- LAB 8 PRODUCTION MEETS BUDGET ESTIMATES
- LAB 8 PRODUCTION MEETS TECHNICAL EXPECTATIONS
- LAB 8 PRODUCTION EXCEEDS SCHEDULE EXPECTATIONS
- Remaining Effort to Complete Panel Production
- ME 1/3 Panels 74 Chambers
- Spares (410-324-74) 12 Chambers
- Total Remaining 86 Chambers
- Cost to Complete Remaining Chambers
- 413K/324 1275/Chamber x 86 110K
- Remaining Funds
- 478K - 413K 65K 50K (addl upscope
approval) 115K - ESTIMATE COMPLETING WORK AHEAD OF SCHEDULE,
MEETING TECH. SPECS., AND WITHIN APPROVED BUDGET.
18MP9 Production Plans
- Production Requirements
- Per L2,L3 complete production by end of March
03. - Methodology
- Increase production rate to 5.6 chambers/month.
- 190 WFTE hours/chamber, need 8.4 FTE between Nov.
02 and Mar. 03 to complete project.on or before
March 03. - Increase Production Workforce
- Will use the available visitor funding to pay for
increase in trained MP9 assembly personnel from 7
to 8 technicians. - Additional funding to cover 0.4 FTE in overtime
distributed over the remaining 15 months of
production.
19FNAL MP-9 Chamber Team
50 of ME234/2 Chambers Completed!
20ME 234/2 Production at MP-9
- 75 Production Chambers assembled (52)
- One chamber to be re-built (006)
- Production Rates
- 3.25 Chamber/ month in FY01
- 5.0 Chambers / month Oct, Nov, 02
- 6.0 Chambers / month Dec. Feb. 02
21Chamber Production Experience
- New Lessons
- Chamber cannot be sealed during transportation
- Old Lessons
- One case of bad wire
- Way wire is wound on spool affects wire tension.
- Dye added to 2-part RTV to insure good mix.
- Discrepancy Report at average level of
3-4/chamber - Most DR ME234/2-006 with 11 DRs
- Least DR Many Chambers with 0 DRs
- Most Consistent Cause Wire position/Wire Tension
- Most Dramatic/Scary Problem RTV mixing/Flaking
Wire
22FNAL FY01 Milestones
Canceled
23FNAL FY01 Milestones (2)
24Conclusion
- Chamber Integration Configuration Control
- Plan to Complete for ME 3/1, 4/1 and 1/3 before
End FY 02. - FNAL Factories
- Activities proceeding according to plans.
- Panel Production ahead of plan To finish by
July, 02. - Chamber Production rate increased to finish by
April, 03. - FNAL Shipment Activities
- Chamber Un-machined Frame Parts Shipments
proceeding according to the new plans. - 60 of PNPI/IHEP Shipments at destination
- FAST Sites Part Flow
- FNAL starting to receive boxes from Universities
to be forwarded to IHEP/PNPI. - Cooling Plate procurement proceeding slightly
behind plan.