Design, Production, - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

Design, Production,

Description:

Design, Production, – PowerPoint PPT presentation

Number of Views:83
Avg rating:3.0/5.0
Slides: 25
Provided by: dang5
Category:
Tags: design | ftw | production

less

Transcript and Presenter's Notes

Title: Design, Production,


1
Design, Production, Shipping Status at FNAL
  • Nelson Chester
  • Fermilab
  • March 4-8, 2002
  • CERN EMU Meeting

2
Outline
  • Design Status
  • Chamber Design
  • Chamber Integration Design
  • Configuration Control
  • Procurement / Shipping Plans
  • Chamber Related
  • Integration Related
  • Cooling Plates
  • Other Parts
  • FNAL Production Activities
  • Panel production
  • Chamber Production
  • Configuration Releases
  • Other FNAL Activities

3
Design Status
  • Chambers
  • ME 234/2 CC Spr. 00
  • ME 2/1 CC Jan. 02
  • ME 1/2 CC Nov. 02
  • ME 3/1 CC Apr. 02 ?
  • ME 1/3 CC Jul. 02 ?
  • ME 4/1 CC Sep. 02 ?
  • Work started by V. Razmyslovitch mid Feb. 02.
    Funded for 6 months (until mid
    August02)
  • Probably will need longer time!!
  • Chamber Integration
  • CC Aug.00
  • CC Dec. 01
  • CC Nov. 02
  • CC Apr. 02 ?
  • CC Jul. 02 ?
  • CC Sep. 02 ?
  • Design Layout
  • Prototype
  • Design Finalization
  • CC

4
Configuration Control
  • Chamber Configuration Control
  • Needed to be able to provide PNPI/IHEP drawings
    to the machine frame parts.
  • Needed to allow PNPI/IHEP to start relative
    chamber production.
  • Cannot finalize Chamber Configuration until
    Integration Configuration is finalized.
  • Integration Configuration Control
  • Needed to allow FNAL and UW to begin parts
    procurement

http//tdserver1.fnal.gov/project/uscmsemu/Config
uration_Control_Documents/Released_Configurations/
5
Configuration Control (cont.)
  • Communication to Foreign Sites
  • Procedure in place to let foreign sites know
    about released Configuration
  • Initial released Configuration transmitted by CD.
  • Foreign site responsible to update drawings in
    their possession if/when new Configurations are
    approved.
  • Process (Travelers) Changes communication to
    Foreign Sites
  • Procedure in place to let foreign sites know
    about Assembly process changes at FNAL.
  • Initial released Configuration transmitted by CD.
  • Foreign site responsible to translate and update
    travelers in their possession for their own
    purposes.

http//tdserver1.fnal.gov/project/uscmsemu/Releas
ed_Specifications/Chamber_Specifications/
6
ME234/2 Cooling Plate Procurement
  • All cooling plates (150) manufactured by Unique
    and shipped to FNAL.
  • Half shipped to UF
  • Balance being shipped to UCR and UCLA

7
ME1/2 Cooling Plate Procurement
  • All Cooling Plates Manufactured by Unique and
    Shipped to Fermilab
  • Half Packed at
  • Unique
  • Half Packed at
  • FNAL

8
ME 2/1 Cooling Plate Procurement
  • Quotes have Closed!
  • Unique is MOST LIKELY low bid vendor.
  • Bid is 860/plate vs 710 for ME1/2 and 735 for
    ME234/2
  • Larger Copper Plate must be procurred
  • Different Furnace Vendor (Larger Furnace)
  • Lower Quantity (38 vs 74 and 140 resp.) Tooling
    and setup amortized over smaller quantity.
  • Exploring cost savings by procurring SAME Cooling
    Plates NOW for ME 3/1.
  • Limited risk to place an order for these SAME
    plates.
  • Belief is that ME 4/1 will also use SAME plate
    but will NOT procure now because of funding
    limits.

9
Cooling Plates Budget vs Actual Cost
10
Shipments Requested
  • Integration Shipments
  • At FNAL
  • ME1/2 Mechanical Parts (UW)
  • ME2/1 AFEB-ALCT Cables (CM)
  • ME1/2 CFEB (OS)
  • ME1/2 Chamber-CFEB Cables (OS)
  • ME2/1 CFEB (OS)
  • ME2/1 Chamber-CFEB Cables (OS)
  • Default approach
  • CablesMechanical parts in oversea container
    shipments.
  • i.e. ME2/1 AFEB-ALCT cables with ME3/1 Chamber
    parts shipment.
  • Electronic by air.
  • Oleg Prokofiev now tracking boxes through FNAL.

11
PNPI Shipping Plans
  • 2nd Shipment Last Week Feb. 02
  • ME 3/1 Panels and Unique Parts
  • ME 4/1 Unique Parts
  • Remaining Tooling Test Equipment
  • Production Aids
  • HV Distribution Parts
  • ME 2/1 Integration Cables
  • ME 3/1 Integration Cables
  • Integration Hardware

12
PNPI Shipping Plans
  • 3rd. Shipment May June 02
  • ME4/1 Panels, Unique Parts
  • ME2/1 Cooling Plates (possibly ME3/1 4/1 as
    well)
  • Integration Parts and Hardware
  • 4th. Shipment- June, 03
  • Spare Chamber Parts
  • ME3/1 (4/1) Cooling Plates (if not shipped
    before)
  • Integration Parts and Hardware

13
IHEP Shipping Plans
  • 2nd. Shipment May - June, 02
  • ME1/2 Cooling Plates
  • ME1/2 Integration Parts and Hardware
  • 3rd. Shipment Nov., 02
  • ME1/3 Cooling Plates
  • ME1/3 Integration Parts and Hardware
  • 4th. Shipment June, - 03
  • All remaining Parts and Hardware

14
Shipping Instructions
  • Instructions published for parts shipped to
    Foreign Sites through FNAL, to be enforced by L3
    Manager (A.K. obtained collaborator agreements).
  • Major points
  • Pre-packed boxes not opened at FNAL.
  • Full List of Parts attached on multiple sides of
    the box.
  • Unit Value Weight on Outside
  • Description of where the parts are to be shipped
    with reference to which chamber it is going to
    be used.
  • Etc.

http//tdserver1.fnal.gov/project/uscmsemu/Release
d_Specifications/Chamber_Specifications/
15
Lab 8 Situation
  • End of Jan. 2002 Panel Machining Snapshot
  • (In units of Chambers) PLANNED
    MACHINED
  • Ramp up (FY99) ME234/2 22 22
  • ME234/2 126 122
  • ME2/1 39 (?38) 36
  • Production ME3/1 39 (?38) 36
  • (FY00-01-02) ME1/2 74 72
  • ME1/3 74 -
  • (Re-Scoped) ME4/1 . 38
    . 36 .
  • All Production Total 372 / 410
    324 / 324
  • Labor Charged totaled 413k of a budget of 478 k
    or 86.4 spent.
  • Produced panels for 324 of a planned 372
    chambers or 87.1.

16
Lab 8 Factory Status
  • Panel Machining in full-speed production as of
    Jan 00
  • Completed machining of ME234/2 panels (FNAL
    Production)
  • Completed machining of ME2/1, ME3/1 ME4/1
    panels (98 ofPNPI Production)
  • Completed machining of ME1/2 panels ( 50 of IHEP
    Production)
  • Started machining ME1/3 panels (completion
    expected by July 02)
  • Spares To Follow

17
Lab 8 Situation (cont.)
  • LAB 8 PRODUCTION MEETS BUDGET ESTIMATES
  • LAB 8 PRODUCTION MEETS TECHNICAL EXPECTATIONS
  • LAB 8 PRODUCTION EXCEEDS SCHEDULE EXPECTATIONS
  • Remaining Effort to Complete Panel Production
  • ME 1/3 Panels 74 Chambers
  • Spares (410-324-74) 12 Chambers
  • Total Remaining 86 Chambers
  • Cost to Complete Remaining Chambers
  • 413K/324 1275/Chamber x 86 110K
  • Remaining Funds
  • 478K - 413K 65K 50K (addl upscope
    approval) 115K
  • ESTIMATE COMPLETING WORK AHEAD OF SCHEDULE,
    MEETING TECH. SPECS., AND WITHIN APPROVED BUDGET.

18
MP9 Production Plans
  • Production Requirements
  • Per L2,L3 complete production by end of March
    03.
  • Methodology
  • Increase production rate to 5.6 chambers/month.
  • 190 WFTE hours/chamber, need 8.4 FTE between Nov.
    02 and Mar. 03 to complete project.on or before
    March 03.
  • Increase Production Workforce
  • Will use the available visitor funding to pay for
    increase in trained MP9 assembly personnel from 7
    to 8 technicians.
  • Additional funding to cover 0.4 FTE in overtime
    distributed over the remaining 15 months of
    production.

19
FNAL MP-9 Chamber Team
50 of ME234/2 Chambers Completed!
20
ME 234/2 Production at MP-9
  • 75 Production Chambers assembled (52)
  • One chamber to be re-built (006)
  • Production Rates
  • 3.25 Chamber/ month in FY01
  • 5.0 Chambers / month Oct, Nov, 02
  • 6.0 Chambers / month Dec. Feb. 02

21
Chamber Production Experience
  • New Lessons
  • Chamber cannot be sealed during transportation
  • Old Lessons
  • One case of bad wire
  • Way wire is wound on spool affects wire tension.
  • Dye added to 2-part RTV to insure good mix.
  • Discrepancy Report at average level of
    3-4/chamber
  • Most DR ME234/2-006 with 11 DRs
  • Least DR Many Chambers with 0 DRs
  • Most Consistent Cause Wire position/Wire Tension
  • Most Dramatic/Scary Problem RTV mixing/Flaking
    Wire

22
FNAL FY01 Milestones
Canceled
23
FNAL FY01 Milestones (2)
24
Conclusion
  • Chamber Integration Configuration Control
  • Plan to Complete for ME 3/1, 4/1 and 1/3 before
    End FY 02.
  • FNAL Factories
  • Activities proceeding according to plans.
  • Panel Production ahead of plan To finish by
    July, 02.
  • Chamber Production rate increased to finish by
    April, 03.
  • FNAL Shipment Activities
  • Chamber Un-machined Frame Parts Shipments
    proceeding according to the new plans.
  • 60 of PNPI/IHEP Shipments at destination
  • FAST Sites Part Flow
  • FNAL starting to receive boxes from Universities
    to be forwarded to IHEP/PNPI.
  • Cooling Plate procurement proceeding slightly
    behind plan.
Write a Comment
User Comments (0)
About PowerShow.com