Title: Enbridge SCC Management Program


1
Enbridge SCC Management Program
  • SCC Workshop
  • Houston - December 2, 2003
  • Walter Kresic
  • Enbridge Pipelines Inc.

2
System Map
Pipeline System
Norman Wells
540 Miles
591 Miles
Athabasca
Line 1
1098 Miles
Line 2
800 Miles
Line 3
1098 Miles
Line 4
1098 Miles
Line 5
645 Miles
Line 9
Line 9
Line 6
759 Miles
Line 7
153 Miles
Line 8
130 Miles
Line 9
524 Miles
Line 10
91 Miles
Line 11
47 Miles
Line 13
909 Miles
Line 14
461 Miles
Line 17
88 Miles
Vector
348 Miles
3
Condition Monitoring
CEPA Framework
Plan Implement Mitigation
Document Learn
4
Condition Monitoring
  • Pipeline segment susceptibility inventory
  • coating type / disbondment observations
  • field examinations whenever pipe exposed
  • crack ILI data
  • hydrotest results when available

5
Plan and Implement Mitigation
  • Mitigation of discrete pipe joint
  • addresses isolated SCC colonies
  • grinding, sleeving, recoating
  • Mitigation of entire pipe segment
  • ILI-based repair project for widespread colonies
  • hydrotest is an option
  • pressure spectrum modification? (PRCI)

6
Document and Learn
  • Annual update of technical process
  • databasing significant volume of information
  • on-going trend process
  • share with industry

7
SCC Detected by ILI
8
Documented Process
  • Roles and responsibilities
  • Annual plans and budgets
  • Technical procedures
  • Field NDT
  • Pressure restriction during field work
  • Grinding / Sleeving / Coating Specifications
  • Gathering samples and field observations
  • Annual trending techniques

9
Enbridge SCC Observations
  • No failures have occurred
  • Near neutral pH SCC
  • Associated with disbonded P.E. tape
  • Pressure cycling a potential contributor
  • Crack detection ILI is effective

10
Improvements
  • Field NDT process (i.e. reporting styles)
  • NDT depth sizing
  • Fitness-for-purpose equations
  • Crack tool defect sizing precision
  • Crack initiation and growth lifecycle
    understanding

11
Summary
  • Enbridge SCC Management Program is a component of
    a broader crack program applied to all pipe
  • Techniques and technologies exist but greater
    precision desirable

12
Enbridge SCC Management Program
  • SCC Workshop
  • Houston - December 2, 2003
  • Walter Kresic
  • Enbridge Pipelines Inc.