Load Management System with Intermittent Power on the Grid - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Load Management System with Intermittent Power on the Grid

Description:

powerline carrier demonstrated here via overhead line and underground cable ... powerline carrier communications over three phase low voltage network around ... – PowerPoint PPT presentation

Number of Views:881
Avg rating:3.0/5.0
Slides: 16
Provided by: ruthke9
Category:

less

Transcript and Presenter's Notes

Title: Load Management System with Intermittent Power on the Grid


1
Load Management System with Intermittent Power on
the Grid
Econnect Ventures Ltd
Ruth Kemsley CEng MIMechE MIEE ruth.kemsley_at_econne
ct.com
2
Project background
  • Econnects long experience with demand-side
    management
  • distributed load control devices
  • providing system (frequency) control on small
    islanded networks with intermittent and limited
    generation sources
  • Desire to develop these devices and associated
    system design techniques to assist grid
    integration of renewables using DSM
  • Need to evaluate potential markets and target
    technology development accordingly

3
Project objectives
  • Identify contractual requirements and commercial
    benefits of different load management systems
  • under the Renewables Obligation and electricity
    trading arrangements
  • Model economic benefits of load management to
    customers with intermittent generation on site
  • Develop low cost load management system
  • incorporating communication technologies and
    switching devices
  • to maximise renewable energy use on a
    demonstration site
  • Identify associated social and psychological
    aspects

4
Project tasks
  • Identified and evaluated four potential control
    strategies for a load management system on the
    distribution network
  • A solution to voltage rise problems caused by
    distributed generation
  • Ensuring zero export from a site with renewable
    generation
  • Avoiding load demand discrepancies
  • Creating an additional market for renewable
    energy
  • Selected one strategy suitable for application at
    the test site
  • Demonstrated technical aspects of load management
    equipment
  • Investigated the social aspects of the load
    management strategy

5
Project partners
  • Econnect
  • analysed potential DSM strategies
  • carried out computer modelling work
  • designed, developed, installed and tested load
    management equipment
  • Findhorn Foundation Community
  • provided a test site and assisted with
    implementation
  • De Montfort University
  • carried out social impact studies

6
Conclusions from preliminary evaluation
  • Mitigating voltage rise from embedded generation
  • technically achievable
  • benefits of avoiding voltage-related constraints
    4 x implementation cost in case study
  • Maximising on-site usage of renewables on a site
    with embedded generation and loads
  • technically possible to ensure close to zero
    power export to the grid
  • quick payback of implementation cost possible
  • Avoiding demand discrepancies between actual and
    contractual volumes of load
  • possible only to reduce, rather than avoid,
    demand discrepancies
  • savings 5 x installation cost over 20 years in
    case study
  • Creation of additional demand for renewable
    energy
  • complex system with high capital cost of
    duplicated heating equipment
  • possible to reduce energy bills and increase
    generation / supply companies revenues
  • benefits less marked

7
Minimising energy export from embedded generation
  • Technique selected for demonstration at Findhorn
    Foundation Community
  • 75kW wind turbine with plans for 600kW more wind
    capacity (at time of project inception)
  • Extensive low voltage distribution network,
    administered by FFC
  • Power export from site rare, but will increase
    significantly when new wind turbines added
  • Installation aimed to demonstrate load management
    technology

8
System tasks
DECIDE WHETHER TO INCREASE SITE LOAD
MEASURE POWER EXPORT
SEND SIGNAL TO LOAD CONTROLLERS
SWITCH LOAD ON OR OFF
SWITCH LOAD ON OR OFF
SWITCH LOAD ON OR OFF
9
System components
IMMERSION HEATER
LOAD CONTROLLERS AND CONTROLLABLE LOADS (SMALL
PERCENTAGE OF TOTAL SITE LOAD)
FINDHORN DISTRIBUTION NETWORK
LC
GRID SUPPLY POWER IMPORT OR EXPORT
SPACE HEATER
LC
CURRENT AND VOLTAGE MEASUREMENT
4
LC
POWER MEASUREMENT UNIT
LC
1
SPACE HEATER
SEND ON OR OFF SIGNAL
COMMUNICATIONS UNIT
POWER IMPORT OR EXPORT, kW
TRAFFIC LIGHT
3
CONTROL UNIT
2
ADD LOAD OR REMOVE LOAD
10
Engineering challenges
  • Measurement of imported / exported power
  • Signal communications needs to be robust
  • powerline carrier demonstrated here via overhead
    line and underground cable
  • low power radio
  • communications cables
  • internet
  • Control algorithm for deciding when to switch
    devices
  • need to avoid increasing import from grid!
  • need to avoid switching large blocks of load
    simultaneously

11
Social challenges
  • Selecting suitable loads for automatic management
  • Identifying and communicating benefits to
    consumers of surrendering control over their
    loads
  • traffic light idea popular with the community
    voluntary load switching
  • test loads were mostly in central community
    buildings
  • Ensuring no loss of quality or reliability of
    supply
  • Integrating system with tariff structure to
    incentivise take-up

12
System designPrototype equipment
POWER MEASUREMENT UNIT
LOAD CONTROLLER
GRID SUPPLY POWER IMPORT OR EXPORT
COMMUNICATIONS UNIT
LOAD CONTROLLER
SUBSTATION CENTRAL CONTROLLER
LOAD CONTROLLER / TRAFFIC LIGHT
13
Simulation results
  • Key to developing control algorithms and
    identifying benefits
  • Example results
  • assume 72kWh per day provided by 40kW of
    deferrable load
  • without control timeswitch controls 40kW just
    before midnight
  • with control 40kW switched on and off
    throughout the day depending on wind availability
  • saving in this instance 19kWh depends on wind
    profile and switching speed

14
Test results
  • Demonstrated
  • low-cost power measurement system
  • simple PIC-based control algorithm
  • powerline carrier communications over three phase
    low voltage network around test site (including
    cable and overhead lines)

15
Conclusions
  • Identified several beneficial applications of
    load management in context of renewable energy
  • Extended application of Econnects load
    controllers from off-grid systems to
    grid-connected operation
  • Developed a load management system for
    implementation
  • Demonstrated successful technical operation of
    component parts
  • Identified issues which will make a system
    practicable and successful
Write a Comment
User Comments (0)
About PowerShow.com