Title: Load Management System with Intermittent Power on the Grid
1Load Management System with Intermittent Power on
the Grid
Econnect Ventures Ltd
Ruth Kemsley CEng MIMechE MIEE ruth.kemsley_at_econne
ct.com
2Project background
- Econnects long experience with demand-side
management - distributed load control devices
- providing system (frequency) control on small
islanded networks with intermittent and limited
generation sources - Desire to develop these devices and associated
system design techniques to assist grid
integration of renewables using DSM - Need to evaluate potential markets and target
technology development accordingly
3Project objectives
- Identify contractual requirements and commercial
benefits of different load management systems - under the Renewables Obligation and electricity
trading arrangements - Model economic benefits of load management to
customers with intermittent generation on site - Develop low cost load management system
- incorporating communication technologies and
switching devices - to maximise renewable energy use on a
demonstration site - Identify associated social and psychological
aspects
4Project tasks
- Identified and evaluated four potential control
strategies for a load management system on the
distribution network - A solution to voltage rise problems caused by
distributed generation - Ensuring zero export from a site with renewable
generation - Avoiding load demand discrepancies
- Creating an additional market for renewable
energy - Selected one strategy suitable for application at
the test site - Demonstrated technical aspects of load management
equipment - Investigated the social aspects of the load
management strategy
5Project partners
- Econnect
- analysed potential DSM strategies
- carried out computer modelling work
- designed, developed, installed and tested load
management equipment - Findhorn Foundation Community
- provided a test site and assisted with
implementation - De Montfort University
- carried out social impact studies
6Conclusions from preliminary evaluation
- Mitigating voltage rise from embedded generation
- technically achievable
- benefits of avoiding voltage-related constraints
4 x implementation cost in case study - Maximising on-site usage of renewables on a site
with embedded generation and loads - technically possible to ensure close to zero
power export to the grid - quick payback of implementation cost possible
- Avoiding demand discrepancies between actual and
contractual volumes of load - possible only to reduce, rather than avoid,
demand discrepancies - savings 5 x installation cost over 20 years in
case study - Creation of additional demand for renewable
energy - complex system with high capital cost of
duplicated heating equipment - possible to reduce energy bills and increase
generation / supply companies revenues - benefits less marked
7Minimising energy export from embedded generation
- Technique selected for demonstration at Findhorn
Foundation Community - 75kW wind turbine with plans for 600kW more wind
capacity (at time of project inception) - Extensive low voltage distribution network,
administered by FFC - Power export from site rare, but will increase
significantly when new wind turbines added - Installation aimed to demonstrate load management
technology
8System tasks
DECIDE WHETHER TO INCREASE SITE LOAD
MEASURE POWER EXPORT
SEND SIGNAL TO LOAD CONTROLLERS
SWITCH LOAD ON OR OFF
SWITCH LOAD ON OR OFF
SWITCH LOAD ON OR OFF
9System components
IMMERSION HEATER
LOAD CONTROLLERS AND CONTROLLABLE LOADS (SMALL
PERCENTAGE OF TOTAL SITE LOAD)
FINDHORN DISTRIBUTION NETWORK
LC
GRID SUPPLY POWER IMPORT OR EXPORT
SPACE HEATER
LC
CURRENT AND VOLTAGE MEASUREMENT
4
LC
POWER MEASUREMENT UNIT
LC
1
SPACE HEATER
SEND ON OR OFF SIGNAL
COMMUNICATIONS UNIT
POWER IMPORT OR EXPORT, kW
TRAFFIC LIGHT
3
CONTROL UNIT
2
ADD LOAD OR REMOVE LOAD
10Engineering challenges
- Measurement of imported / exported power
- Signal communications needs to be robust
- powerline carrier demonstrated here via overhead
line and underground cable - low power radio
- communications cables
- internet
- Control algorithm for deciding when to switch
devices - need to avoid increasing import from grid!
- need to avoid switching large blocks of load
simultaneously
11Social challenges
- Selecting suitable loads for automatic management
- Identifying and communicating benefits to
consumers of surrendering control over their
loads - traffic light idea popular with the community
voluntary load switching - test loads were mostly in central community
buildings - Ensuring no loss of quality or reliability of
supply - Integrating system with tariff structure to
incentivise take-up
12System designPrototype equipment
POWER MEASUREMENT UNIT
LOAD CONTROLLER
GRID SUPPLY POWER IMPORT OR EXPORT
COMMUNICATIONS UNIT
LOAD CONTROLLER
SUBSTATION CENTRAL CONTROLLER
LOAD CONTROLLER / TRAFFIC LIGHT
13Simulation results
- Key to developing control algorithms and
identifying benefits - Example results
- assume 72kWh per day provided by 40kW of
deferrable load - without control timeswitch controls 40kW just
before midnight - with control 40kW switched on and off
throughout the day depending on wind availability - saving in this instance 19kWh depends on wind
profile and switching speed
14Test results
- Demonstrated
- low-cost power measurement system
- simple PIC-based control algorithm
- powerline carrier communications over three phase
low voltage network around test site (including
cable and overhead lines)
15Conclusions
- Identified several beneficial applications of
load management in context of renewable energy - Extended application of Econnects load
controllers from off-grid systems to
grid-connected operation - Developed a load management system for
implementation - Demonstrated successful technical operation of
component parts - Identified issues which will make a system
practicable and successful