Commissioning TileCal with Cosmic Ray Muons - PowerPoint PPT Presentation

About This Presentation
Title:

Commissioning TileCal with Cosmic Ray Muons

Description:

Cable from barrel drawer delivers 9 tower signals and 7 muon signals ... Needs ROD crate and ROD Crate Controller. Might log data from RCC over Ethernet ... – PowerPoint PPT presentation

Number of Views:54
Avg rating:3.0/5.0
Slides: 23
Provided by: jamesp59
Learn more at: http://hep.uchicago.edu
Category:

less

Transcript and Presenter's Notes

Title: Commissioning TileCal with Cosmic Ray Muons


1
Commissioning TileCal with Cosmic Ray Muons
J. Pilcher University of Chicago
2
TileCal Assembly Schedule
  • Surface preassembly of barrel
  • Complete preassembly December 03
  • Start disassembly late February 04
  • 2 months possible for commissioning studies
  • Cs studies over full height of barrel
  • Cosmic ray muons through full readout system
  • Underground assembly of barrel
  • Begin 11 May 04
  • Module assembly complete 10 Sept. 04
  • Services complete 26 Nov. 04
  • Tests and commissioning 29 Nov. 04 - 27 Dec. 04
  • Short time (4 weeks)
  • Unpopular time for working
  • We must be efficient and well prepared

3
Commissioning Preassembly
  • Goals
  • System tests with more modules
  • Largest system run to date is 6 superdrawers
  • In test beam
  • Full barrel contains 128 superdrawers
  • Intermediate step is essential
  • System tests with hardware not yet used
  • LV power supply sets in fingers
  • Bulk LV power source 80m away
  • LVL1 trigger hardware interfacing to TileCal
  • Patch panels to remap tower and muon signals
  • Receiver boards
  • Hardware RODs

4
Commissioning in Pit
  • Check that all systems are alive in Dec. 04
  • Cs and CIS runs
  • Thorough check-out with physics signals will
    take longer
  • Attractive to run system on cosmics periodically
    from Dec. 04 - Dec. 06
  • Monitor stability
  • Get all bugs ironed out
  • Provide trigger to other parts of ATLAS
  • Likely very little access to pit during this time
  • Most work in USA15

5
Estimate Trigger Rates
  • Consider rate in back-to-back trigger towers (16
    16 equipped modules)

6
Estimate Trigger Rates
  • These triggers are the most useful
  • Muon fully traverses single towers
  • Could also select these muons with bottom section
    of cal. and scintillator in beam region
  • Rate is lower than trigger using larger towers
    (eg. 0.4 x 0.4)
  • Return to this case later
  • Do simple calculation with Excel

7
Cosmic Ray Flux
  • Use numbers from Particle Data Group
  • Tabulate in Excel

8
Cosmic Ray Flux
  • Integrate over muon energy above a threshold
  • Must impose range cut-off, depending on ? (or ?)
  • Set up table for linear interpolation
  • Gives muons / sec / m2 / steradian

9
Cosmic Ray Flux
  • Range information
  • Use PDG, Sec. 26, Ref. 1 for range-energy dE/dx
  • Article by D.E. Groom et al., Nucl. Data Tables
    78, for muons in iron
  • Set up table for linear interpolation
  • Use module geometry from CDD drawings
  • Solid steel at inner and outer radii (including
    girder, etc.)
  • Steel and scintillator mixture between

10
Rate Calculation
  • Consider back-to-back cells
  • Area from plane mid-way through A-cell on bottom
  • Solid angle from corresponding plane on top
  • Scale rate by cos2? (zenith angle)
  • Integrate over wedges in ?

11
Rate Variation with ? and ?
  • Plot fraction of total rate versus ? and ?
  • Easy to scale rate to smaller configurations

12
Rate Estimate in UX15 Pit
13
Rate Estimate in UX15 Pit
  • Overburden corresponds to 55 m of rock with
    density 2.4 gm/cm3
  • Range cut-off now 34 GeV instead of 4 GeV
  • Based on CERN Yellow Report 71-18
  • SPS study of range-energy and dE/dx of high
    energy muons
  • Expected rate reduction is factor of 22
  • Zenith angle dependence of overburden not
    included
  • Would give 10 reduction
  • Vertical access shafts not included
  • Would increase rates for certain ? and ?
  • Expected rate 90/hr
  • Rob McPherson has been asked for a more detailed
    GEANT-based estimate

14
Rate with Alternative Trigger
  • Consider trigger on towers of (0.4 x 0.4)
  • Same area as before but solid angle increased by
    16
  • Rate increased by 16
  • 32K events/hr on surface (was 1.9K/hr)
  • 1.5K events/hr in pit (was 0.09K/hr)
  • Energy spread over several towers
  • Trigger less clean
  • Events less useful for calorimeter diagnostics
  • Much less trigger hardware needed
  • Could filter events at LVL2

15
Comments on Rates
  • There is a very useful trigger rate both on the
    surface and in the pit
  • Actual rate on surface next winter will depend on
    how much electronics is available

16
Hardware Needed
  • Electronics drawers (64) - probably OK
  • LV power in fingers
  • Bulk LV power (200V for USA15)
  • Cabling and fibers
  • TTC hardware
  • LVL1 trigger interface hardware
  • Patch panels to separate tower and muon signals
  • Receiver boards (64 towers each)
  • Trigger logic for cosmic ray running
  • LVL2 hardware
  • ROD modules
  • ROD crate and controller
  • Output hardware from ROD crate (Ethernet?)

17
LV System
18
LV System
  • Need full scale prototype for 2 fingers with 200V
    bulk supply, cables, splitter boxes
  • This summer?
  • Need preproduction units
  • Use in preassembly commissioning next winter
  • 64 of 256 fingers?
  • 32 of 256? ? looks reasonable
  • Feasibility????

19
LVL1 Interface Hardware
  • Cable from barrel drawer delivers 9 tower signals
    and 7 muon signals
  • Splitter box needed to collect tower and muon
    signals on separate cables
  • Group tower signals as needed for LVL1 receiver
    boards
  • Whose responsibility???
  • Drawing shows required organization for 1616
    drawers

20
LVL1 Interface Hardware
  • Receiver boards produced a single-ended,
    conditioned, analog signal for each tower
  • Will go to flash ADC boards in ATLAS
  • Could be used for cosmic trigger instead
  • Trigger on towers of 0.4 x 0.4 for 88 modules
    requires the following
  • add analog signals in groups of 16 towers
    (0.1x0.1 to 0.4x0.4)
  • Require energy threshold on sum (discriminate)
  • Take 8 2-fold coincidences between back-to-back
    towers
  • Take OR of the 8 coincidence outputs

21
LVL2 Hardware
  • Data from drawer goes to ROD modules
  • 1 module handles 8 drawers
  • 88 modules ? 32 drawers or 4 RODs
  • Needs ROD crate and ROD Crate Controller
  • Might log data from RCC over Ethernet
  • Done for other systems in test beam
  • ROD schedule?
  • 2 prototype modules planned for September
  • Can we get 4?
  • Production not until next spring

22
Conclusions
  • Commissioning with muons is attractive and
    necessary
  • The trigger rates look fine
  • Try this week to agree on target configuration
    for next winter
  • Confirm responsibilities and explore timetable
    with TDAQ groups
  • Over next few weeks make more precise list of
    items needed and identify items requiring more
    help
  • People willing to help might meet in July to
    agree on division of tasks (phone video
    face-to-face)
Write a Comment
User Comments (0)
About PowerShow.com