Title: Agenda
1UPPER SLIDE RAVINE WORKSHOP City of Grass
Valley September 29, 2009
2Agenda
Upper Slide Ravine Infrastructure Study Workshop
- Welcome Introductions
- II. Review of State Grant and What It Can
Do - Results of Preliminary Engineering Study
- Question and Comment Period
3Upper Slide Ravine Infrastructure Study
Workshop Introductions
City Staff Tony Clarabut, Fire Chief Joe C.
Heckel, Community Development Director Tim
Kiser, Public Works Director/City Engineer Tom
Last, Planning Director Jeri Amendola,
Housing/Econ Development Specialist TLA
Consultant Team Terry Lowell, President, TLA
Engineering Planning Keone Kauo, P.E., TLA
Engineering Planning
4(No Transcript)
5Upper Slide Ravine Infrastructure Study Workshop
II. Review of State Grant and What It Can
Do a. Why a Grant for this Area? -Obtained
funds based on needs of area and desire for City
services by residents b. Amount and Time Frame
of Grant Funds -Approx. 400,000 for const.
Start by June 2010 c. Review of Study Area and
Priorities -Identify priorities and base
infrastructure d. Review Work Effort by TLA
(with focus on improving public
safety) -Identify and engineer baseline
improvements
6List of Immediate Priorities and Challenges
- Priorities
- Water / Fire Protection. Upgrade water system
to improve fire flow and add hydrants - Storm Drainage. Extend storm drainage system to
minimize street drainage problems and flooding - Wastewater. Extend sewer service to unserved
area. - Road Improvements. Improve for emergency access
- Challenges
- Funding limits what can be accomplished in
short-term - Road repair required with underground utilities
- Need to improve emergency access into area
Involves discussion with adjacent neighborhoods
7(No Transcript)
8Upper Slide Ravine Infrastructure Study Workshop
- Results of Preliminary Engineering
- a. Existing Conditions Future Challenges
- b. Findings of Engineering Study
- c. Immediate and Future Priorities
- d. Recommended Alternative
9Existing Sanitary Sewer Facilities
- Twelve (12) properties served by septic tank /
leach fields in area - Existing sewer main in Carol Drive and upper
Doris Drive have adequate capacity to serve this
area
10Existing Storm Drainage Facilities
- Area has minimal underground storm drainage
system - Area mostly drains by surface flow north to south
- Centerville flume installed will serve as
connection for future storm drainage
11Existing Water Facilities
12Existing Street Conditions
- Primary access route, Doris and Carol Drives via
N. Church Street - Approximately 2900 unpaved road surface 1300
of paved surface - Road widths vary between 10 to 22 feet
13Existing Street Conditions (cont.)
Bernice Drive
Doris Drive
June Drive
Hazel Lane
Helen Lane
Carol Drive
14Proposed Phased Infrastructure Plan
- Install new water main down Doris Drive to
provide greater fire flow through area and add
fire hydrants - Install an underground storm drainage system
along with a water quality device to alleviate
current flooding problems and street
deterioration in the area. - Extend existing City sanitary sewer system to
properties currently served by septic
tank/leachfield systems on the southerly portion
of the project site. - Repair existing street system following
installation of underground utilities.
15Proposed Water Facilities On Site
- Installation of new water main down Doris Drive
to provide greater fire flow through the project
area and add fire hydrants.
16Proposed Storm Drainage Facilities
- Installation of an underground storm drainage
system and storm water treatment facility to
alleviate current flooding problems and street
deterioration.
17Proposed Sanitary Sewer Facilities
- Extension of existing City sanitary sewer system
to properties currently served by septic
tank/leachfield systems in the southerly section.
18Proposed Street Restoration
- Repair and stabilize roadway sections where
underground utilities are to be installed.
19(No Transcript)
20Emergency Evacuation/Access Route
- Street system does not provide for adequate
evacuation of residents and simultaneous access
by emergency services - Limited funding precludes addressing in current
phase - Route shown is conceptual alignment of a primary
evacuation corridor
21- ACCESS AND CIRCULATION
- ISSUES - HOW TO ADDRESS?
- Access into out of Study Area is a safety
concern - Potential to create added cut-through traffic
- Other adjacent neighborhoods will need to be
involved - Need to determine road widths and obtain ROW
- Not sufficient funding available to fix road
system - FUTURE STEPS
- Wish to separate discussion on emergency access
options at separate workshop with other
neighborhood - Consultant is retained to facilitate workshop on
alternative access options within 45 days - Access options to be tied to infrastructure plan
for USR - City will pursue funding to phase in access impts
22Upper Slide Ravine Infrastructure Study Workshop
- Questions and Comment Period
- Questions/Comments
- Next Steps
- -Finalize Infrastructure Plan
- -Present to City Council - November 2009
- -Conduct community meeting on access
- -Prepare engineering plans bid process
- -Need contract executed by June 2010
23Upper Slide Ravine Infrastructure Study Workshop
Thank you for your participation! Questions on
this program can be directed to Jeri Amendola,
Housing/Economic Specialist 530-274-4714
24UPPER SLIDE RAVINE WORKSHOP City of Grass
Valley September 29, 2009