Financing issues - PowerPoint PPT Presentation

1 / 41
About This Presentation
Title:

Financing issues

Description:

attractive to mobilize long term limited / non recourse financing' ... Is the amount of financing required prevent proper competition between ... – PowerPoint PPT presentation

Number of Views:125
Avg rating:3.0/5.0
Slides: 42
Provided by: WB1673
Category:
Tags: financing | issues

less

Transcript and Presenter's Notes

Title: Financing issues


1
Financing issues
  • Raymond Bourdeaux
  • The World Bank
  • St. Petersburg May 23, 2008

2
Specifics of project finance debt
3
Why investors want to raise debt?
  • Cost of equity vs. cost of debt
  • Cost of equity 18
  • Cost of debt 12
  • Where to mobilize financing? / non recourse
    financing
  • Increasing borrowing allows to reduce the cost of
    a project to the Government

4
Debt characteristics the basics
  • Maturity
  • Grace Period
  • Funding rate
  • Margin
  • Conditions Precedents
  • Covenants and debt service cover ratio
  • Event of Default
  • Consequence of Event of Default
  • Security

5
What is a bankable deal?
  • A project that Banks consider sufficiently
  • attractive to mobilize long term limited / non
    recourse financing
  • Different financing institutions have different
    requirements who is going to finance the
    project?
  • What amounts are required to finance the deal?
  • To which extent does this tally current financial
    modeling results?
  • But there is no upside to debt the only concern
    for a lender is to minimize risks

6
Debt characteristics the basics

7
Debt characteristics the basics
Additional Money Requested by Lenders to Service
Debt due to traffic uncertainty

time
Lower than expected revenues
8
Structure of Availability Payment (AP)
  • Availability Payment (AP) starts on the first
    year of operation
  • A portion of the AP will be indexed to reflect
    OM cost inflation
  • It is proposed that AP will follow 2 rules, to
    reduce the incidence of high starting level due
    to shorter maturity in ruble
  • On a nominal basis, AP can only reduce year on
    year
  • Such reduction cannot happen in the first 5
    years of operation, to ensure that Investors can
    design a project with the lower acceptable level
    of equity IRR

9
Ways of decreasing debt funding requirements
(apart from additional Government support)
  • Increase tariffs / revenues ( feasibility) ?
  • Upfront Government contribution ?
  • Decrease operation and maintenance costs
  • Allow variability of design to reduce
    construction costs ?
  • Defer some of the construction until later ?
  • Increase equity ?
  • Increase maturity and / or grace period ?
  • Ensure lower cost financing ?
  • Split the project into phases / reduce the
    project scope?
  • Making sure that the project is competitively bid
    to maximize competitive tensions between bidders
    ?

10
Challenges for finance raising
  • Finance raising is investors responsibility, why
    does it matter?
  • Deals are challenging, investors will expect
    Government to understand the challenge and to
    show has addressed it in its approach
  • Investors will expect that Government know the
    deal is bankable, because the relevant detailed
    financial studies have been done
  • Specifics of the deal
  • Size of project versus typical projects in this
    category
  • Untested market, both legally and finance raising
    wise
  • Finance raising work will take a long time once a
    bidder is selected
  • Multi Laterals Agencies cannot support
    exclusively at bidding stage
  • Is the amount of financing required prevent
    proper competition between commercial banks
    (exclusivity vs. size)?

11
Overall risk allocation
12
Impact of setting the risk allocation at a
suboptimal level and having a too short timetable
  • Timetable. Size and risk allocation influence
    bidders willingness to participate
  • The less the competition, the more demanding
    investors will be
  • The best moment to ensure reasonable risk
    allocation is early on. After bid award, the
    pressure is to close the transaction, not improve
    the risk allocation

13
PPP risk allocation principle
  • PPP risks need to be allocated to the party best
    able to manage it
  • This is very different from allocating all risks
    to the private sector
  • Inadequate risk allocation leads to
  • Failure of project to reach financial close (eg
    all risks revert back to Government)
  • Failure during construction (half constructed
    motorway and liabilities attached to it))
  • Failure during operation (costs of re- tendering
    and liabilities reverting back to Government)
  • Risks magnitude vary depending on project phases
    some risks can be allocated early on in the
    bidding process and some continue to exist until
    the end of the project life. This impact the
    optimum risk allocation, typically there are
    four distinct period for projects
  • Before bid submission
  • Between bid submission and financial close
  • During construction
  • During operation

14
Typical risk allocation
15
Bank margin
16
Risk of change in bank margin and maturity the
issue
  • Margin and maturity are finalized only when the
    loan is ready to be signed
  • Lenders margin are a function of demand and
    supply, market appetite and due diligence.
    Typically it is linked to
  • Transaction size
  • How many transactions are in the market at the
    same time
  • The amount of due diligence done upfront
  • The amount of lending competition
  • Any financial disruption
  • In theory and assuming competition for funding
    exists, once a preferred bidder is selected it
    will have a better ability to negotiate down
    banks margin or extend maturities.
  • So bidders cannot fully control banks margin at
    the point of bid submission.
  • Who should take the risk of change in bank
    margins and maturities between bid submission and
    financial close?

17
Risk of change in bank margin and maturities
Typical risk allocation
  • Risk exists in any countries and is a typical
    risk associated with bidding for project
    financings.
  • only in the period between bid submission and
    financial close, margins are fixed at financial
    close (subject only to refinancing).
  • Risk normally borne by bidder
  • Might be different if narrow or volatile or
    difficult market.

18
Risk of change in bank margin
  • TYPICALLY, THE RISK IS ALLOCATED TO THE PREFERRED
    CONCESSIONAIRE, SINCE
  • The bidders have much deeper experience in
    estimating bank margins than the grantor.
  • Subject to major due diligence findings post bid
    submission, margins might be reduced post bid
    submission
  • Difficult for Grantor to control the risk and no
    interest for bidder to mitigate it if it does not
    take the risk
  • Note that
  • in theory, savings on lowering margin changing
    maturities could be shared with grantor, but it
    is unlikely that bidders would accept upside
    sharing without downside sharing

19
Interest rate
20
Risk of change in interest rate the basics
  • Loans are quoted in relation to floating rate
  • It is often better to ensure the interest rate of
    the loan is fixed for an infrastructure project
  • An interest rate swap allow a borrower to
    exchange a loan with a floating interest rate
    with a fixed interest rate

21
10 year interest rate swap, rubleevolution over
the last year
Change in swap rate over last year has been in
the region of 135-155bp points (6.4 to 7.5-8.0
between sept 06 and nov 07
22
5 years IRS ruble swap rates
23
Risk of change in interest rate the issue
  • Floating interest rate (Libor, Russian base rate
    etc..) changes with time and is not something the
    Bidder can control.
  • Usually, Governments are not prepared to
    compensate Concessionaire for change in interest
    rate during construction or operation.).
  • Entering into an interest rate swap implies a
    contractual commitment( the interest rate swap).
    Usually such contract is entered at the time of
    financial close. This is common practice.
  • When the bidder submits its bid, it has to use an
    assumption about the swap rate applicable for its
    Interest rate swap. The bidder cannot control the
    swap rate.
  • Who should take the risk related to movement in
    interest rate swap ?

24
Risk of change in interest rate Typical risk
allocation
  • This issues is true in any country and is a
    typical risk associated with bidding of project
    financing.
  • The issue arises purely between bid submission
    and financial close, assuming interest swap rate
    markets exist for maturities similar to the one
    considered for the project loans.
  • The standard treatment (UK, South Africa etc..)
    is that,the Government takes the risk of change
    in swap rates between bid submission and
    financial close.

25
Risk of change in interest rate example of risk
allocation
  • Government provides reference source for swap
    rate before bid submission for reference for
    bidders
  • Such quote is used to calculate capital grant and
    revenue guarantee / availability payment
    requirement in the bid.
  • Around the time of financial close, the swap rate
    is quoted by banks and entered into by the
    Concessionaire. Such rate becomes the reference
    rate to re-compute( based on the financial model)
    the level of capital grant and availability
    payment that will keep the Concessionaire
    financially whole (no gain / no loss) compared to
    its bid case at bid submission.
  • Period of uncertainty for the Government is
    purely during the period from bid submission to
    financial close.

26
Risk of change in interest rate
  • Entering into a large swap might change the
    quotation for this swap Possible solutions to
    this
  • A swap for the full amount is entered into at
    financial close. Obtaining independent quote for
    such a large swap might be difficult.
  • The swap is broken down into a set of swaps
    entered into during construction, for a number of
    drawdown
  • Contractual provision preventing market collusion
    can be introduced to ensure the quote is procured
    in a manner satisfactory to grantor .

27
Inflation
28
Risk of change in inflation the issue
  • Inflation impacts project during bidding,
    construction and operation since construction and
    operating costs increase with time
  • The cumulative impact of inflation might be
    significant over the life of the project
    (bidding, construction, operation).
  • Forcing investors to take inflation risk can
    result either in (i) no bid or (ii) bids that
    include very high forecast for inflation since
    bidders have limited protection against this
    risk.
  • Governments typically allow for some form of
    protection against inflation in typical
    procurement contract. The key issue is to make
    sure that this is properly adapted to the
    specifics of a PPP transaction.

29
Example of partial inflation to revenue guarantee
  • If there is no mechanism for inflation, the
    bidder, has no choice but to assume a high
    inflation) assumption throughout the life of the
    concession resulting in a high estimate of
    operation and maintenance costs (pink line)
  • If the inflation is limited throughout the
    operation period, indexation represent a
    significant limitation of liability to the
    Government (blue versus pink line)
  • Even assuming a scenario with high inflation for
    a limited period of time (7 years yellow line)
    indexation to inflation might result in a
    reduction of liability to the concessionaire

30
Inflation risk, typical risk allocation
  • Government support ( capital grant and /or
    availability payment or revenue guarantee) is at
    least partially indexed to an inflation factor.
  • Such inflation factor is calculated from the date
    of bid submission so it covers the period of bid
    submission, construction and operation
  • The inflation factor seeks to mirror as closely
    as possible reality. The inflation applies to
    part of costs related to inflation only

31
Forex
32
The project is potentially exposed to foreign
exchange rate movement in the following ways
  • Construction and other construction related
    costs might not be fully denominated in ruble if
    imports are considered.
  • Revenues are most likely denominated in ruble
  • Debt Financing might be sourced in other
    currencies to ensure long maturities and / or
    deeper pool of financing
  • Some of the operating costs might be denominated
    in a currency other than the ruble.
  • Foreign equity holders might require returns
    calculated in a home currency.
  • Currency swaps can protect against movements in
    foreign exchange but such swaps are entered into
    at financial close.
  • Price to end users cannot always be significantly
    indexed to a foreign exchange rate (elasticity of
    price of toll tariffs vs demand).

33
Should any of the construction cost be sourced in
currency other than the rubles?
  • There appears to be significant bottleneck in
    terms of key supplies on the Russian market. This
    has lead to significant increase in prices of
    cement and steel.
  • Some of the construction related costs
    (engineering design, management staff etc.) will
    not be denominated in rubles.
  • Part of the rationale for the PPP strategy is to
    encourage sourcing of material in currencies
    other than ruble.
  • the currency risk (for construction) is limited
    to the period between bid submission and
    financial close at financial close, the
    Government liability is fixed.
  • Nothing prevents the Government limiting its
    exposure to this risk (maximum amount of cost
    denominated in Foreign Currency, or dead band for
    swap rate movement).

34
Possible mitigation mechanisms
  • Bidder is encouraged to finance using ruble
    financing
  • Government help to mobilize local banks?
  • Bidding criteria to reward local currency
    financing?
  • Tariff formula takes into account impact of
    foreign exchange
  • Bidder bid fixed amount allowed to fluctuate
    against forex
  • If required, maximum amount can be set as a
    ceiling to cap grantor risk.
  • Bidder takes risk on make up of financing plan
  • Risk for Government
  • Sudden devaluation of the ruble (if amounts is
    not capped)
  • If Ruble appreciate, not a risk, reward to
    grantor
  • Size of potential liability will be linked to
    debt amounts in foreign currency which will not
    be finalized at bid submission date.
  • Bidder compensated in direct relation to a
    proportion of the actual foreign denominated
    debt repayment schedule
  • If required, maximum amount can be set as a
    ceiling to cap grantor risk
  • Bidder not exposed to make up of financing plan
  • Difficult to evaluate bidders proposals

35
Risk associated with foreign exchange Proposed
mechanism for capital cost
  • Government allows for a certain portion of the
    capital cost to be denominated in foreign
    currency and protected for exchange rate risk via
    swaps
  • At bid submission, Government provide reference
    for currency swap rates for the construction
    period
  • At financial close, the swaps rate are quoted by
    the concessionaire banks and the difference leads
    to an increase (or decrease) in the capital
    grant.

36
Risk of change in foreign exchange rate
examplefor capital costs
  • Impact of local sourcing (with price increase
    pass through) versus importing and Government
    absorbing fx risk

37
Should any of the debt be denominated in
currencies other than ruble?
  • Can the project raise debt financing without
    foreign denominated debt?
  • How much will Veshneconombank commit?
  • How much is available in the commercial debt
    market?
  • How much will IFI prepare to commit?
  • If the project has some construction costs not
    denominated in ruble, does it make sense to
    borrow only in rubles?
  • If such amounts are available, what is the
    maturity that will be attached to it?
  • Will all the debt have a maturity longer than
    17years?
  • Is it likely that for these amounts, the debt
    tranches will have several maturities, including
    shorter maturities of say 12 years
  • Is constraining maturities increasing revenue
    guarantee to a higher level than otherwise
    required with foreign debt denomination
  • Impact on margin?
  • How will a bidder benefit from competition
    between banks (and margin reduction) if no
    competition is possible

38
Euro denominated debt
  • Euro denominated debt is different from rubles
    denominated debt
  • Longer maturity available (20 years and above)
  • Long term swap exists and are liquid for the long
    maturities
  • Long term swapped rate is lower than the ruble
    swap available (4.7 for 20 year versus 8 for
    10-12 years)
  • Depth of the euro market for Project finance loans

39
Risk associated with foreign exchange Example of
mechanism for debt denominated in euros
  • Before bid submission, Government defines the
    maximum amount of debt that can be denominated
    in Euro and benefit for fx protection (eg
    concessionaire can source additional debt
    denominated in Euro but without forex
    compensation mechanism from the grantor).
  • The Government reserves its right to reject any
    repayment profile / maturities that it does not
    consider appropriate for foreign denominated debt
    at financial close.
  • The Government introduces in the CA a maximum
    amount of ruble exposure it is prepared to take
    in relation to this foreign denominated debt
  • During the life of the loan, credit / debt are
    registered and payment made / received by grantor
    in relation to the debt

40
Conclusions
  • Debt raising is a key element of structuring a
    project financing
  • Project finance lenders have specific
    requirements that need to be taken into account
  • Some of the financing risks tend to be dealt with
    in a similar fashion, and the proposed risk
    allocation ought to reflect international
    standards to ensure the right competition

41
Financing Issues
THANK YOU !!! Raymond Bourdeaux The World
Bank Rbourdeaux_at_worldbank.org
Write a Comment
User Comments (0)
About PowerShow.com