Title: Financing issues
1Financing issues
- Raymond Bourdeaux
- The World Bank
- St. Petersburg May 23, 2008
2Specifics of project finance debt
3Why investors want to raise debt?
- Cost of equity vs. cost of debt
- Cost of equity 18
- Cost of debt 12
- Where to mobilize financing? / non recourse
financing - Increasing borrowing allows to reduce the cost of
a project to the Government
4Debt characteristics the basics
- Maturity
- Grace Period
- Funding rate
- Margin
- Conditions Precedents
- Covenants and debt service cover ratio
- Event of Default
- Consequence of Event of Default
- Security
5What is a bankable deal?
- A project that Banks consider sufficiently
- attractive to mobilize long term limited / non
recourse financing - Different financing institutions have different
requirements who is going to finance the
project? - What amounts are required to finance the deal?
- To which extent does this tally current financial
modeling results? - But there is no upside to debt the only concern
for a lender is to minimize risks
6Debt characteristics the basics
7Debt characteristics the basics
Additional Money Requested by Lenders to Service
Debt due to traffic uncertainty
time
Lower than expected revenues
8Structure of Availability Payment (AP)
- Availability Payment (AP) starts on the first
year of operation - A portion of the AP will be indexed to reflect
OM cost inflation - It is proposed that AP will follow 2 rules, to
reduce the incidence of high starting level due
to shorter maturity in ruble - On a nominal basis, AP can only reduce year on
year - Such reduction cannot happen in the first 5
years of operation, to ensure that Investors can
design a project with the lower acceptable level
of equity IRR
9Ways of decreasing debt funding requirements
(apart from additional Government support)
- Increase tariffs / revenues ( feasibility) ?
- Upfront Government contribution ?
- Decrease operation and maintenance costs
- Allow variability of design to reduce
construction costs ? - Defer some of the construction until later ?
- Increase equity ?
- Increase maturity and / or grace period ?
- Ensure lower cost financing ?
- Split the project into phases / reduce the
project scope? - Making sure that the project is competitively bid
to maximize competitive tensions between bidders
?
10Challenges for finance raising
- Finance raising is investors responsibility, why
does it matter? - Deals are challenging, investors will expect
Government to understand the challenge and to
show has addressed it in its approach - Investors will expect that Government know the
deal is bankable, because the relevant detailed
financial studies have been done - Specifics of the deal
- Size of project versus typical projects in this
category - Untested market, both legally and finance raising
wise - Finance raising work will take a long time once a
bidder is selected - Multi Laterals Agencies cannot support
exclusively at bidding stage - Is the amount of financing required prevent
proper competition between commercial banks
(exclusivity vs. size)?
11Overall risk allocation
12Impact of setting the risk allocation at a
suboptimal level and having a too short timetable
- Timetable. Size and risk allocation influence
bidders willingness to participate - The less the competition, the more demanding
investors will be - The best moment to ensure reasonable risk
allocation is early on. After bid award, the
pressure is to close the transaction, not improve
the risk allocation
13PPP risk allocation principle
- PPP risks need to be allocated to the party best
able to manage it - This is very different from allocating all risks
to the private sector - Inadequate risk allocation leads to
- Failure of project to reach financial close (eg
all risks revert back to Government) - Failure during construction (half constructed
motorway and liabilities attached to it)) - Failure during operation (costs of re- tendering
and liabilities reverting back to Government) - Risks magnitude vary depending on project phases
some risks can be allocated early on in the
bidding process and some continue to exist until
the end of the project life. This impact the
optimum risk allocation, typically there are
four distinct period for projects - Before bid submission
- Between bid submission and financial close
- During construction
- During operation
14Typical risk allocation
15Bank margin
16Risk of change in bank margin and maturity the
issue
- Margin and maturity are finalized only when the
loan is ready to be signed - Lenders margin are a function of demand and
supply, market appetite and due diligence.
Typically it is linked to - Transaction size
- How many transactions are in the market at the
same time - The amount of due diligence done upfront
- The amount of lending competition
- Any financial disruption
- In theory and assuming competition for funding
exists, once a preferred bidder is selected it
will have a better ability to negotiate down
banks margin or extend maturities. - So bidders cannot fully control banks margin at
the point of bid submission. - Who should take the risk of change in bank
margins and maturities between bid submission and
financial close?
17Risk of change in bank margin and maturities
Typical risk allocation
- Risk exists in any countries and is a typical
risk associated with bidding for project
financings. - only in the period between bid submission and
financial close, margins are fixed at financial
close (subject only to refinancing). - Risk normally borne by bidder
- Might be different if narrow or volatile or
difficult market.
18Risk of change in bank margin
- TYPICALLY, THE RISK IS ALLOCATED TO THE PREFERRED
CONCESSIONAIRE, SINCE - The bidders have much deeper experience in
estimating bank margins than the grantor. - Subject to major due diligence findings post bid
submission, margins might be reduced post bid
submission - Difficult for Grantor to control the risk and no
interest for bidder to mitigate it if it does not
take the risk - Note that
- in theory, savings on lowering margin changing
maturities could be shared with grantor, but it
is unlikely that bidders would accept upside
sharing without downside sharing
19Interest rate
20Risk of change in interest rate the basics
- Loans are quoted in relation to floating rate
- It is often better to ensure the interest rate of
the loan is fixed for an infrastructure project - An interest rate swap allow a borrower to
exchange a loan with a floating interest rate
with a fixed interest rate
2110 year interest rate swap, rubleevolution over
the last year
Change in swap rate over last year has been in
the region of 135-155bp points (6.4 to 7.5-8.0
between sept 06 and nov 07
225 years IRS ruble swap rates
23Risk of change in interest rate the issue
- Floating interest rate (Libor, Russian base rate
etc..) changes with time and is not something the
Bidder can control. - Usually, Governments are not prepared to
compensate Concessionaire for change in interest
rate during construction or operation.). - Entering into an interest rate swap implies a
contractual commitment( the interest rate swap).
Usually such contract is entered at the time of
financial close. This is common practice. - When the bidder submits its bid, it has to use an
assumption about the swap rate applicable for its
Interest rate swap. The bidder cannot control the
swap rate. - Who should take the risk related to movement in
interest rate swap ?
24Risk of change in interest rate Typical risk
allocation
- This issues is true in any country and is a
typical risk associated with bidding of project
financing. - The issue arises purely between bid submission
and financial close, assuming interest swap rate
markets exist for maturities similar to the one
considered for the project loans. - The standard treatment (UK, South Africa etc..)
is that,the Government takes the risk of change
in swap rates between bid submission and
financial close.
25Risk of change in interest rate example of risk
allocation
- Government provides reference source for swap
rate before bid submission for reference for
bidders - Such quote is used to calculate capital grant and
revenue guarantee / availability payment
requirement in the bid. - Around the time of financial close, the swap rate
is quoted by banks and entered into by the
Concessionaire. Such rate becomes the reference
rate to re-compute( based on the financial model)
the level of capital grant and availability
payment that will keep the Concessionaire
financially whole (no gain / no loss) compared to
its bid case at bid submission. - Period of uncertainty for the Government is
purely during the period from bid submission to
financial close.
26Risk of change in interest rate
- Entering into a large swap might change the
quotation for this swap Possible solutions to
this - A swap for the full amount is entered into at
financial close. Obtaining independent quote for
such a large swap might be difficult. - The swap is broken down into a set of swaps
entered into during construction, for a number of
drawdown - Contractual provision preventing market collusion
can be introduced to ensure the quote is procured
in a manner satisfactory to grantor .
27Inflation
28Risk of change in inflation the issue
- Inflation impacts project during bidding,
construction and operation since construction and
operating costs increase with time - The cumulative impact of inflation might be
significant over the life of the project
(bidding, construction, operation). - Forcing investors to take inflation risk can
result either in (i) no bid or (ii) bids that
include very high forecast for inflation since
bidders have limited protection against this
risk. - Governments typically allow for some form of
protection against inflation in typical
procurement contract. The key issue is to make
sure that this is properly adapted to the
specifics of a PPP transaction.
29Example of partial inflation to revenue guarantee
- If there is no mechanism for inflation, the
bidder, has no choice but to assume a high
inflation) assumption throughout the life of the
concession resulting in a high estimate of
operation and maintenance costs (pink line) - If the inflation is limited throughout the
operation period, indexation represent a
significant limitation of liability to the
Government (blue versus pink line) - Even assuming a scenario with high inflation for
a limited period of time (7 years yellow line)
indexation to inflation might result in a
reduction of liability to the concessionaire
30Inflation risk, typical risk allocation
- Government support ( capital grant and /or
availability payment or revenue guarantee) is at
least partially indexed to an inflation factor. - Such inflation factor is calculated from the date
of bid submission so it covers the period of bid
submission, construction and operation - The inflation factor seeks to mirror as closely
as possible reality. The inflation applies to
part of costs related to inflation only
31Forex
32The project is potentially exposed to foreign
exchange rate movement in the following ways
- Construction and other construction related
costs might not be fully denominated in ruble if
imports are considered. - Revenues are most likely denominated in ruble
- Debt Financing might be sourced in other
currencies to ensure long maturities and / or
deeper pool of financing - Some of the operating costs might be denominated
in a currency other than the ruble. - Foreign equity holders might require returns
calculated in a home currency. - Currency swaps can protect against movements in
foreign exchange but such swaps are entered into
at financial close. - Price to end users cannot always be significantly
indexed to a foreign exchange rate (elasticity of
price of toll tariffs vs demand).
33Should any of the construction cost be sourced in
currency other than the rubles?
- There appears to be significant bottleneck in
terms of key supplies on the Russian market. This
has lead to significant increase in prices of
cement and steel. - Some of the construction related costs
(engineering design, management staff etc.) will
not be denominated in rubles. - Part of the rationale for the PPP strategy is to
encourage sourcing of material in currencies
other than ruble. - the currency risk (for construction) is limited
to the period between bid submission and
financial close at financial close, the
Government liability is fixed. - Nothing prevents the Government limiting its
exposure to this risk (maximum amount of cost
denominated in Foreign Currency, or dead band for
swap rate movement).
34Possible mitigation mechanisms
- Bidder is encouraged to finance using ruble
financing - Government help to mobilize local banks?
- Bidding criteria to reward local currency
financing? - Tariff formula takes into account impact of
foreign exchange - Bidder bid fixed amount allowed to fluctuate
against forex - If required, maximum amount can be set as a
ceiling to cap grantor risk. - Bidder takes risk on make up of financing plan
- Risk for Government
- Sudden devaluation of the ruble (if amounts is
not capped) - If Ruble appreciate, not a risk, reward to
grantor - Size of potential liability will be linked to
debt amounts in foreign currency which will not
be finalized at bid submission date. - Bidder compensated in direct relation to a
proportion of the actual foreign denominated
debt repayment schedule - If required, maximum amount can be set as a
ceiling to cap grantor risk - Bidder not exposed to make up of financing plan
- Difficult to evaluate bidders proposals
35Risk associated with foreign exchange Proposed
mechanism for capital cost
- Government allows for a certain portion of the
capital cost to be denominated in foreign
currency and protected for exchange rate risk via
swaps - At bid submission, Government provide reference
for currency swap rates for the construction
period - At financial close, the swaps rate are quoted by
the concessionaire banks and the difference leads
to an increase (or decrease) in the capital
grant.
36Risk of change in foreign exchange rate
examplefor capital costs
- Impact of local sourcing (with price increase
pass through) versus importing and Government
absorbing fx risk
37Should any of the debt be denominated in
currencies other than ruble?
- Can the project raise debt financing without
foreign denominated debt? - How much will Veshneconombank commit?
- How much is available in the commercial debt
market? - How much will IFI prepare to commit?
- If the project has some construction costs not
denominated in ruble, does it make sense to
borrow only in rubles? - If such amounts are available, what is the
maturity that will be attached to it? - Will all the debt have a maturity longer than
17years? - Is it likely that for these amounts, the debt
tranches will have several maturities, including
shorter maturities of say 12 years - Is constraining maturities increasing revenue
guarantee to a higher level than otherwise
required with foreign debt denomination - Impact on margin?
- How will a bidder benefit from competition
between banks (and margin reduction) if no
competition is possible
38Euro denominated debt
- Euro denominated debt is different from rubles
denominated debt - Longer maturity available (20 years and above)
- Long term swap exists and are liquid for the long
maturities - Long term swapped rate is lower than the ruble
swap available (4.7 for 20 year versus 8 for
10-12 years) - Depth of the euro market for Project finance loans
39Risk associated with foreign exchange Example of
mechanism for debt denominated in euros
- Before bid submission, Government defines the
maximum amount of debt that can be denominated
in Euro and benefit for fx protection (eg
concessionaire can source additional debt
denominated in Euro but without forex
compensation mechanism from the grantor). - The Government reserves its right to reject any
repayment profile / maturities that it does not
consider appropriate for foreign denominated debt
at financial close. - The Government introduces in the CA a maximum
amount of ruble exposure it is prepared to take
in relation to this foreign denominated debt - During the life of the loan, credit / debt are
registered and payment made / received by grantor
in relation to the debt
40Conclusions
- Debt raising is a key element of structuring a
project financing - Project finance lenders have specific
requirements that need to be taken into account - Some of the financing risks tend to be dealt with
in a similar fashion, and the proposed risk
allocation ought to reflect international
standards to ensure the right competition
41Financing Issues
THANK YOU !!! Raymond Bourdeaux The World
Bank Rbourdeaux_at_worldbank.org