Title: Provincial Budget Outcome of Conditional Grants and CAPEX As at 30 September 2006
1Provincial Budget Outcome of Conditional Grants
and CAPEX As at 30 September 2006
- Select Committee on Finance
- Presentation by
- Northern Cape
- Provincial Treasury
- 20 November 2006
2Objectives
- To brief the Select Committee on Finance on the
CAPEX and Conditional Grants Outcomes as at 30
September 2006 - Summary of total CAPEX
- Summary of Infrastructure Infrastructure
Reporting Model (IRM) - Conditional Grants
- Reasons for under/ over expenditure per
Department
3Broad Overview
- Total expenditure on Payments for Capital Assets
amount to R198,5 million or 42 of the allocated
budget as at 30 September 2006. - The Province projects to over-spend its CAPEX by
R83,9 million or 18 of the budget. - Total expenditure on conditional grants amount to
R338,2 million or 37 of the allocated budget as
at 30 September 2006. - The Province project to overspent CG budget by
R9,5 million.
4Summary of Capital Expenditure per Department as
at 30 September 2006
5Payments for Capital Assets(Capital Expenditure)
- Total Capital Expenditure as at 30 September 2006
amount to R198,5 million or 42 of CAPEX budget. - An improvement compared to 37 in 2005/06.
- Social Sector Capital Expenditure amount to
R228,9 million as at 30 September 2006 or 43 of
capital budget - An improvement compared to 33 in 2005/06.
- Education capital expenditure amount to R11,2
million or 44 of capital budget. - Considerable improvement compared to 28 in
2005/06. - Health capital expenditure total to R114,0
million or 42 of capital budget. - An improvement compared to 36 in 2005/06
- Social Services Population Development capital
spending amount to R4,2 million or 46 of capital
budget. - Considerable improvement compared to 27 in
2005/06. - Other sectors capital expenditure combined total
to R69,0 million or 42 of capital budget.
6Total Infrastructure (Maintenance Capital)
7Summary spending on Infrastructure
- Allocated Budget R664,7 million
- Total Infrastructure Spending as at 30 September
2006 is R235,7 or 35 of the infrastructure
budget. - The Province project to underspent its
infrastructure budget by a net amount R45,5
million at the end of the year.
8Spending on Infrastructure per Department
- Education
- Allocated Budget R26,9 million
- Spending as at 30 September 2006 is R13,3 or 50
of infrastructure the budget. - The department projects to overspend the
allocated budget by R20,459 million. - The reason, according to the department is due to
reprioritisation Capital budget of the
department has been reduced to augment
compensation of employees.
9Spending on Infrastructure per Department cont.
- Transport, Roads and Public Works,
- Allocated Budget R246 million, of which R115,4
million represent PIG. - Spending as at 30 September 2006 is R85,7 million
or 35 of the budget. - This is below average.
- The reasons for slow spending, according to the
department, is the delay on the implementation of
projects. - However, the department projects to break even at
year end
10Spending on Infrastructure per Department cont
- Health
- Allocated Budget R325,6 million, of which R12,0
million represent PIG. - Spending as at 30 September 2006 is R96,5 million
or 30 of the budget. - The reason for slow spending is as stated by the
department attributed to delays in major
projects. - The department is projecting to under-spend its
infrastructure budget by R84, 2 million.
11Spending on Infrastructure per Department cont.
- Agriculture and Land Reform
- Allocated Budget R30,7 million, of which R2,7
million represent PIG. - Spending as at 30 September 2006 is R11,5 million
or 37 of the budget. - Slow spending, according to department, is delays
in tendering processes by Public Works. - However the Department is projecting to break
even at year end. - Sport, Arts and Culture
- Allocated Budget R10 million
- Spending as at 30 September 2006 is R15,9million
or 159 of the budget - The Department is projects to overspend by R18, 3
million by the end of the financial year. - The project was initially allocated R40 million
over the four year period. - Due to slow spending during previous years
amounts were not rolled over. - The amounts had been reallocated during
adjustment estimates.
12Spending on Infrastructure per Department cont.
- Housing Local Government
- Allocated Budget R25,3 million, of which 88
represent the eradication of bucket system. - Spending as at 30 September 2006 is R11,5 million
or 50 of the budget. - Sport, Arts and Culture
- Allocated Budget R10 million
- Spending as at 30 September 2006 is R15,9million
or 159 of the budget - The Department is projects to overspend by R18, 3
million by the end of the financial year. - The project was initially allocated R40 million
over the four year period. - Due to slow spending during previous years
amounts were not rolled over. - The amounts had been reallocated during
adjustment estimates.
13Challenges Main causes of Infrastructure
Underspending
- Project lists not submitted timeously to the
Implementing Agent (IA) - IA cannot start with planning and design of next
financial years projects - Contractors will not be on site on 1 April of
each year lead to rollovers - Lack of forward planning and poor alignment of
planning and budgeting cycle. - Inadequate assessment of infrastructure plans and
budgets by departments. - Budgets for large multi year projects are
committed to one financial year. - Lack of ownership/ leadership by HODs.
- Lack of Programme Management Skills in
departments.
14Solutions
- Full implementation of Infrastructure Delivery
Improvement Programme (IDIP). - Building of Capacity in line departments.
15 16Conditional Grants by Grant Type
17CONDITIONAL GRANTS 2nd QUARTER EXPENDITURE
COMPARISON (2005/06 VS 2006/07 FINANCIAL YEAR)
18Aggregate Expenditure of CG as at 30 September
2006
- Total budget R915,6 million
- Total transfers received R401,1 million
- Expenditure to date R338,163 million
- 84 of total received funds
- 37 of budget
- A considerable decline compared to 55 in 2005/06
19Detail on Conditional Grant per Department
20Department of Agriculture
- Agriculture Grants
- Comprehensive Agriculture Support (CASP)
- Land Care Programme
- Budget Outcome 2nd Quarter
- Total National Allocation R21, 6 million
- Total transfers received R9,704 million
- Total spent as at 30 September 2006 R11, 7
million - 54 of the budget.
- CASP National Allocation R15, 8 million
- Total transfers received R7,1 million
- Total spent as at 30 September 2006 R9, 1
million - 58 of the budget
- Considerable improvement compared to 29 in
2005/06.
21Department of Agriculture cont.
- Budget Outcome
- Land Care Programme National Allocation R5, 8
million - Total transfers received R2,6 million
- Expenditure as at 30 September 2006 R2, 6
million - 100 of the total received.
- 46 of the Budget.
22Department of Education
- Education Grants
- Further Education and Training College Sector
Recap - HIV and Aids (Life skills Education)
- National School Nutrition Programme
- Budget Outcome 2nd Quarter
- National Allocation R42,1 million
- Total transfers received R21,0 million
- Spending as at 30 September 2006 R22, 8 million
- 108 of total transfers received
- 54 of National Allocation.
- An improvement compared to 50 in 2005/06.
- FET National Allocation R10, 0 million
- Total transfers received R5,0 million
- Total spent as at 30 September 2006 R0, 0
million - Nothing was spent to date
23Department of Education cont.
- HIV AIDS National Allocation R2,4 million
- Total transfer received R1,2 million
- Total spent as at 30 September 2006 R0, 584
million - 48 of total transfers received
- 24 of the Budget
- A declined compared to 36 2005/06.
- National School Nutrition Programme National
Allocation R29, 6 million - Total transfers received R14,8 million
- Total spent as at 30 September 2006 R22, 2
million - 150 of total transfers received
- 75 of the Budget.
- A considerable increase compared to 50 2005/06
24Department of Education cont.
- Reasons for below average spending as indicated
by the department - HIV AIDS
- The slow spending, according to the department
is attributed to change in the business plan. (No
indication on detail of changes) - FET
- Transfers to FET institutions were transacted to
suspense account, hence no expenditure reported. - The discrepancy has since been corrected.
25Department of Health
- Health Grants
- Comprehensive HIV AIDS
- Forensic Pathology Services
- Health Professions Training and Development
- Hospital Revitalisation
- National Tertiary Services
26Department of Health cont.
- Budget Outcome 2nd Quarter
- National Allocation R539, 2 million
- Spending as at 30 September 2006 R191, 4
million - Total transfers received R269,6 million
- 71 of total transfers received
- 36 of Budget, a decline compared to 46 in
September 2005 - Comprehensive HIV AIDS National Allocation
R68,6 million - Total transfers received R34,3 million
- Expenditure as at 30 September 2006 R28, 9
million - 84 of total transfers received
- 42 of the Budget.
- an improvement compared to 27 in 2005/06.
27Department of Health Cont.
- Forensic Pathology Service National Allocation
R23, 6 million - Total transfers received R11,8 million
- Expenditure as at 30 September 2006 R2,2
million - 18 of total transfers received
- 9 of the Budget
- Health Professions Training Development
National Allocation R41,1 million - Total transfers received R20,5 million
- Expenditure as at 30 September 2006 R20,5
million - 50 of the Budget, which is the same as in
2005/06.
28Department of Health Cont.
- Hospital Revitilisation National Allocation
R313,6 million - Total transfers received R156,8 million
- Expenditure as at 30 September 2006 R93, 7
million - 60 of total transfers received
- 30 of the Budget,
- A considerable decline compared to 52 in 2005/06
- National Tertiary Services National Allocation
R92,3 million - Total transfers received R46,1 million
- Expenditure as at 30 September 2006 R46,1
million - 100 of total transfers received
- 50 of the Budget which is the same as in
2005/06.
29Department of Health Cont.
- Reasons for slow spending
- Comprehensive HIV AIDS
- According to the department the reason for the
slow spending is attributed to - Delay in the start of ARV clinic renovations
- Challenges in the recruitment of professionals.
30Department of Health Cont.
- Forensic Pathology Services Grant
- Slower spending, according to the department, is
attributed to - Personnel costs journalized late to the grant.
- Delivery of equipment mortuary vehicles.
- Delays in appointment of contractors for
renovations in existing mortuaries.
31Department of Health Cont.
- Hospital Revitilisation
- Slow spending, according to the department is
attributed to - The delay in the appointment of contractors due
to delayed procurement processes, - The capacity to deliver by some of the
contractors appointed on the job, - The shortage of skills because of the current
demand in the construction sector, and - The shortage of materials particularly breaks and
cement.
32Department of Housing Local Government
- Housing LG Grants
- Integrated Housing and Human Settlement
Development - Budget Outcome 2nd Quarter
- National Allocation R104,7 million
- Total transfers received R46,1 million
- Spending as at 30 September 2006 R41,5 million
- 62 of total transfers received
- 40 of the Budget.
- A considerable decline compared to 79 in 2005/06
33Department of Housing Local Government
- Reasons for slow spending
- Integrated Housing and Human Settlement
Development - The slow spending, according to the department,
is attributed to non-performance by a number of
contractors. - Legal process to terminate contracts of the
affected contractors.
34Department of Sport, Arts and Culture
- Budget Outcome 2nd Quarter
- Mass Sport and Recreation Participation
Programme National Allocation R6,2 million - Total transfers received R3,5 million
- Expenditure as at 30 September 2006 R1, 8
million - 52 of total transfers received
- 30 of the Budget,
- A decline compared to 43 in 2005/06
- the low spending, according to the department, is
attributed to the delay on the appointment of
coordinators.
35THANK YOU