1UNIVERSITY OF PRETORIA Systems Renewal Status
Update 9 September 2009 0800 0930
2Objectives of this presentation
- Current status and future activities
- Questions Discussions
- Announcements
31. Systems RenewalCurrent Status Future
Activities
4Financial and Supply Chain Management (FSC)Prof
Quintus Vorster
PeopleSoft
5Agenda
- General Ledger
- Asset Management
- Procurement
- Accounts payable
- Commitment control, budgets
- AR, Billing
- Student Financials
- Claims, Advances, Stores, Job cards
- Management Information
- Training
- Smart security
6General Ledger
- Integration Unikom to PS PS to Unikom (AR/BI)
working smoothly, daily recon reports - Issues
- VAT calculations on PS journals
- PS Journals do not integrate to existing donor
system
6
7Asset Management
- Setup configured in production
- Data conversion in progress
- Conversion of room locations
- Commodity codes
- Loading of test data
- Testing in progress, also training of staff
- Testing AM security design and roles
- Red flag integration with PO and AP
7
8Procurement
- Design workshops completed
- BEE configuration in progress
- Some issues
- Vendor adresses not all available
- E-procurement (test environment) not functioning
- Workflow i.r.o. PO approvals not active
8
9Accounts payable
- Design workshops completed
- Started with configuration in production
- Foreign vendors upload almost completed
- Cleanup on stores data almost completed
- PO data cleanup
- Status 4 no issues
- Status 5 no issues
- Status 6 some issues
- Status 2 some issues
- Four staff members already involved in testing
9
10Accounts payable - outstanding
- VAT setup time consuming to capture vouchers,
delay development of UPK - Identify user preferences
- VAT not setup correctly for foreign vendors
- Setup of EFT and cheque payments
10
11Commitment control and budgets
- Completed and in process define, setup and test
- Ledgers and group ledgers
- Period calendars
- Budget chart fields
- Define translation trees for budget chart fields
11
12Commitment control and budgets
- To be completed
- Further testing of commitment check on balances
of actual revenue less expenditure and
encumbrances on a cost centre, where budgets not
applicable - Design workshop and design workbook
12
13AR Billing
- Accounts receivables (General) live from 1 June
2009 - Accounts receivables live from 1 September 2009
- Student RAG
- Tuks FM
- SRC
- Perdeby
- Student culture
- Student administration
13
14Student Financials
- 26 Customisations, 5 completed
- Currently testing 5 completed
- Next 9 Planned for completion end September
- Data conversion i.r.o account balances, loans and
deposits completed, currently being tested - Waiting for student records to be converted to
start testing tuition fee calculation - Risk Customisations not completed in time
14
15Student Financials NSFAS
- NSFAS process being developed
- Waiting for student information to be converted
and equations written to test merit and other
bursary awards. - Risk Too little time for testing
15
16Claims, Advances and Stores
- CA (interim Unikom) Integration with HR no
commitment control, only fund check for interim
period - Unikom stores system
- Replenishment of stock through PS PO
- Receipt of goods in PS
- Integration to Unikom stores
- Issuing in Unikom (Unikom requisition)
- No commitment control, only funds check
- Integration to PS
16
17Jobcards investigation
- Unikom Taakkaart system
- Taakkaart PO in Unikom, commitment control
- Capture invoices in Unikom, liquidate Commitments
- Integration to PS, invoices as approved vouchers
- Payment in PS
17
18Management Reports
- 61 Reports identified
- Four categories
- Critical, before go live (19)
- Important, post go live, year end (9)
- Non-critical next year (13)
- Scrapped, vanilla (20)
- 9 of critical reports already developed, 1 in
testing
18
19Training
- Power users 14 September to 25 September 2009
- End users 28 September to 13 November 2009
- Training on the Test environment
- Classroom based training UPKs integrated in
training
19
20Smart Security
- Currently being configured
- Risk, if not completed in time
20
21Human Capital Management (HCM)Mr Paul Krige
PeopleSoft
22Human Capital Management (HCM)
- COMPLETED since previous report
- PayConnect
- Parallel runs on July salary and claims payrolls.
- Administer Workforce
- Testing on hiring, employee maintenance,
terminations and student appointments. - E-Recruitment
- Testing the recruitment process
- Leave
- Testing to leave process
- Position Budgeting and Commitment Accounting
- Some progress not completed.
- Data conversion
- Person, Job, Salary plans and grades, Position
data, PayConnect and Leave - Training
- Training schedules completed and communicated to
participants
23Human Capital Management (HCM)
- In Progress
- PayConnect
- Parallel runs on August salary and claims
payrolls. - Administer Workforce
- UAT testing on hiring, employee maintenance,
terminations and student appointments. - E-Recruitment
- UAT testing of the recruitment process
- Leave
- UAT testing of leave
- Position Management and Commitment Accounting
- Configuration
- Data conversion
- Benefits
- Training
- Development of training material
- Change Management
- Communication to all HR staff re training and
go-live - Communication to all UP staff re HR go-live
arrangements and the shutdown of GMHS.
24Human Capital Management (HCM)
- Next Steps
- PayConnect
- Parallel runs on September salary and claims
payrolls. - DIFFICULTY BALANCING DUE TO REMUNERATION BOX TAX
BALANCE ADJUSTMENTS. - DELAYS IN PROCESSING RUNS DUE TO THESE BALANCE
ADJUSTMENTS. - Administer Workforce
- Sign-off on hiring, employee maintenance,
terminations, student appointments and claims - UNSCHEDULED DEVELOPMENT ARISING FROM TESTING
- E-Recruitment
- Sign-off the recruitment process
- Leave
- Sign-off on leave
- Position Management and Commitment Accounting
- Reports
- Equity and PayConnect
- Integration
- Fleet Management, Parking, Performance
Management, ID Management. - Training
- Training schedules complete and communicated to
participants
25Campus Solutions (CS)Mr Johan Haumann
PeopleSoft
26Campus Solutions (CS)
- Modules in the CAMPUS PRODUCTION environment
- External Organizations (Schools data needed for
CRM) - Modules in CAMPUS TEST environment
- Academic Structures
- Programme and Plans
- Campus Community
- 64,000 Students person and person other
records are loaded - User Acceptance Testing completed
- Student Records
- The Scheduling of Classes from 1930 to 2009 has
been loaded. - 210 Students academic records were converted
from Legacy to PeopleSoft
27Campus Solutions (CS)
- Modules in CAMPUS Test environment (cont)
- Student Financials
- Students accounts has been converted from Legacy
to PS - User acceptance testing is under way
- Student Financial Aid
- Three customizations are ready for user
acceptance testing - Other Module Status
- Admissions
- The Registrar approved that applications for 2011
will still be done in Legacy and then from a
later date in 2010 all applications will be
handled in PeopleSoft
28Campus Solutions (CS)
- Pending
- All approved customizations are in progress
- Configuration of Self Service (Students and
Staff) - Residence Management System
- Integration
- Availability of UP Resources
29Customer Relationship Management (CRM)Ms M
Wheeler
PeopleSoft
30Customer Relationship Management (CRM)
- COMPLETED since previous report
- User acceptance testing
- Outbox visit to SA to help with support and
outstanding issues 85 resolution of issues
achieved during the week visit - Demo to interested stakeholders
- Apropos / PS CRM integration developed and tested
- UPK Know-it mode completed by CSC staff
- Tracking of scores
31Customer Relationship Management (CRM)
- In Progress
- Setup label printers (Outbox)
- Get unique numbering testing phase
- Data Loading
- Last few outstanding UAT issues (Outbox)Â
- Migration of objects / configurations to
Production environment
32Customer Relationship Management (CRM)
- Next Steps
- GO-LIVE
- Roll out to the rest of UP
33Oracle Enterprise Content Management (ECM)Mr
André Kleynhans
34Oracle Enterprise Content Management (ECM)
- Activities recently completed
- The proposed Security model design has been
successfully implemented in Dev.
35Oracle Enterprise Content Management (ECM)
- Activities currently in progress
- Testing of the security model
- Development of automatic rerouting should
gatekeeper not be available. - Investigate options regarding clustering as part
of the software architecture - Awaiting response from Oracle regarding
validation of software architecture - Reviewing the proposed meta data model
36Oracle Enterprise Content Management (ECM)
- Planned next steps (short term)
- Finalise testing of security model.
- Obtain validation feedback from Oracle regarding
software architecture. - Finalise meta data model.
- Planning for implementation of the Archive
project. - Planning for implementation of Intra Web
projects.
37Server Administration TeamMr Mike Coetzee
38Server Administration Team
- COMPLETED since previous report
- Upgrades ordered for the IBM Intel (X-Series)
Servers to cater for additional VMs implemented
on Saturday 5th September - Storage (SAN and Cartridge) upgrades approved,
and orders placed. Initial unit (27TB) to be
delivered on Tuesday 8th September, with upgrade
to 43TB expected by end of next week.
Installation and configuration still to be
planned and completed. - Further RAM and CPU upgrades ordered for the P570
servers to cater for Application and Database
LPAR requirements - Further IBM Intel servers ordered to cater for
additional VM requirements across the various
System Renewal Application environments - Trevor and Stefan completed the second course in
the IBM AIX series of training courses
39Server Administration Team
- In Progress
- Ongoing work on input to the DR (Disaster
Recovery) planning for the System Renewal
environment - Continuation of fine tuning performance measuring
and monitoring of the server environments - Updating of operational documentation (Standards,
Procedures, etc,) relating to the implemented
hardware / software - Review of current Oracle VM implementation and
existing VMs, and prioritization of creation of
remaining required VMs - Planning for Storage upgrades and new storage
solution
40Server Administration Team
- Next Steps
- Implementation of P-Series server upgrades
- Allocation of additional RAM to PeopleSoft DEV
and TST application and database LPARs on the
first P570 server - Allocation of additional CPU/RAM to the PRD
database LPARs on the second P570 server - Finalization of Oracle VM implementation and
configuration of upgraded and additional X-Series
servers - Implementation of required additional VMs
- Finalization of planning for Storage upgrades and
new storage solution - Continuation of requisite AIX and associated
training
41Database and Integration SupportMs Estie Steyl
42Database and Integration Support
- COMPLETED since previous report
- Compilation of Production components to be
monitored through Grid Control - Data Refreshes
- PSHCM from Production to Training
- EPM Training and Production, from Development
- PS Campus from Test to Development
- Implementation of database links for UPK
Production reporting from Financials - Assisting with EPM setup and connectivity
- Recreating Web Content Management Development
database
43Database and Integration Support
- COMPLETED since previous report (continued)
- Split of the Production EPM environment from the
normal PeopleSoft Production environment - Investigation and follow-up on dormant Java
processes on Test environment - Supplied database disk space growth statistics
44Application Support (PeopleSoft)
- COMPLETED since previous report
- Installations and Upgrades
- Re-installed EPM Test with MP 6
- Upgrade of Campus Demo and Training with MP 6 and
7 and Bundles 12 and 13 (had to fix Integration
configuration problems on Campus Training before
upgrade could be done) - Ascentials on DEV and Training AIX servers
- Moved the EPM Test environment to Dev
- Campus Prod went live
- Configured CRM Prod to use LDAP
45Application Support (PeopleSoft)
- COMPLETED since previous report (continued)
- Re-configured CRM Test and Prod after the copy of
CRM DEV to these environments - Configured All CRM environments to load
attachments to the designated ftp area on the AIX
servers - Usage Tracking configured and 5000 plus userids
loaded into Usage Tracking with unique passwords - Configured HCM Training after HCM prod was copied
to HCM Training - Re-configured Campus Training after Campus Test
was copied to Campus Training
46Database and Integration Support
- In Progress
- Ongoing actions with regard to monitoring and
alerts (via SMS/email) on all Production
components - Investigation into backup tape cycles and offsite
storage procedures - Split of the Development and Test EPM
environments from the normal PeopleSoft
Development and Test environments - Ongoing assistance to Auditors with regard to
additional system information required - Ongoing support to Integration team with regard
to problems, new services etc
47Application Support (PeopleSoft)
- In Progress
- Prepare CRM for go live
- Assistance with info needed for EPM/Ascentials
setup - Installation of Ascentials and Datastage on AIX
Production servers - Complete EPM Training configuration
- Investigations
- PS setup to use label printers at CSC, Dispatch
for PS CRM - Performance issues on PS applications
48Application Support (PeopleSoft)
- In Progress (continued)
- Re-create indexes on all PS applications
- Ongoing tasks
- Publishing new UPK content
- Move of projects into Campus Prod and Financials
Prod - Daily clean up of traces/log files on request
- Running and distributing DDDAUDIT and SYSAUDIT
reports to ensure system stability and
availability
49Application Support (PeopleSoft)
- In Progress (continued)
- Ongoing tasks
- Assist Developers with investigations when
development processes experience problems in PS
applications - Assist Developers with bouncing PS Appservers,
Web servers and Process Schedulers and clearing
application specific cache on request - Assist new developers with access problems on
servers
50Database, Integration and Application Support
- Next Steps
- Monthly reporting on all Production databases
- Creation of additional database environments on
request - Decide on next Campus Environment to be upgraded
and configure that for Change Assistant - Investigate Financials upgrade requirements
- Complete printer setup for all CRM environments
- Obtain handover knowledge from Scott regarding
EPM setup - Investigate fax-server setup for Procurement for
Pos - More ongoing support for problems, new
initiatives, etc.. -
51MiddlewareMs Mariette Nordier
52System Integration Project
- Opening remarks
- The focus for integration work was
- Consolidate person records, assigning a Unique
Person Number - Align above initiative with integration required
for PS CRM -
53 System Integration Consolidate person records,
assigning a Unique Person Number
54 System Integration PS CRM integration
55 System Integration
- In Progress
- - PS CS student biographical and student academic
data to ClickUP and VCA. This data will also be
used for displaying navigation links for student
sign-on to ClickUP - Next
- Central GetPerson record Service
- Parking system queries PS Campus and PS HCM
- PS FIN Stores
- SMS systemss personnel record requirement
56Identity Management Project
- Completed
- Agreement on Directory Strategy future vision
to plan towards. - In progress
- Interim planning for addressing user
requirements - Extented user authentication requirement (ECM,
WebCenter, PeopleSoft) on authentication - Central person record source for addressing
service of GetPersonRecord - Integration for adding and update person records
- Next
- Implement what is planned Jan 2010
57WebCenter project
- In progress
- - WebCenter install on DEV server.
- - Investigation on WebCenter Spaces functionality
- - WebCenter portal development Personnel Portal
Student Portal
58 WebCenter project Portal
59 WebCenter project Personnel Portal
60 WebCenter project Student Portal
61WebCenter project
- Single user point of entry.
- Portlets for various Application (PS, Java, ext),
Intranet, Mail, ext - Next
- Install WebCenter Test and Production
environments - Performance testing
622. Questions Discussion
633. Announcements