Title: WP4 Activity Plan Romanian Education Network RoEduNet
1WP4 Activity PlanRomanian Education Network -
RoEduNet
- Eduard Andrei - eandrei_at_roedu.net
- Dan Nae - dann_at_roedu.net
- Octavian RUSU - octavian_at_iasi.roedu.net
2Description of Work
- Project objectives
- To implement the regional networking
infrastructure that will connect to the
pan-European network the regional NRENs - To maintain the infrastructure in stable
operation - Total allocated men-months 4.43
- Project duration 10 months
3Work Package Participants
- RoEduNet - Lead Contractor - 1.14 men-months
- HUNGARNET - 0.84 men-months
- GRNET - 2.45 men-months
4WP4 Deliverables and Milestones
- Deliverables
- D12 - Implementation and acceptance tests
- D14 - SEEREN configuration and performance
- Milestones
- M12 - Operation of the regional networking
infrastructure offering to all NRENs GEANT
visibility - M13 - Stable network operation
5WP4 Activity List
- 4.1 Define acceptance tests
- 4.2 Deliver equipment and connections
- 4.3 Adjust equipment configuration
- 4.4 Technical support in stable operation
6WP4 Detailed Activity Plan
- Acceptance tests for links and equipment
- Equipment configuration and deployment
- Initial test period
- Transition to production state
- Performance monitoring
- Additional services
- Technical support and problem solving
7Acceptance tests for links and equipment
- Deployment of links from the contracted service
provider - Delivery of equipment from the contracted
supplier - Initial carrier tests on BER and link
availability to pass minimum requirements (99
availability and 10e-12 BER) - Initial equipment testing to detect
software/hardware problems, as well as
software/hardware compatibility with the network
design. - Activity duration 1 month
8Equipment configuration and deployment
- The configuration should provide the minimum
requirement all NREN connectivity to GEANT
(including any future connected NRENs e.g. RENAM) - The equipment configuration should allow for
various extended services multicasting, QoS,
IPv6 - The initial configuration and deployment of the
equipment may require some travelling for on-site
installation - Training of all NRENs personnel on the
configuration and operation of equipment (online
or face-to-face) as well as documents on the
implementation available online - Activity duration 3 months
9Equipment configuration and deployment (contd)
- GEANT connectivity should be provided to all
NRENs - As stated in the DoW document (Annex 1) the
additional traffic should not cause problems to
the existing GEANT connections (an estimated
total of 17 Mbps, which can be supported by any
of the existing GEANT links) - Redundant links (if any) should be taken into
account for load balancing and rerouting traffic
in case of a link failure - If the regional NRENs (the ones already connected
to GEANT) have direct links connecting them,
routing policies should be configured to insure
redundant connectivity to GEANT for all NRENs
10Equipment configuration and deployment (contd)
- The EGP routing policies should be similar to
GEANT routing policies (communities,
import/export policies, etc) - Additional EGP policies should be considered and
accepted by all NRENs - The IGP of choice should be configured on all
routers (OSPF, IS-IS) to allow for load sharing
and redundant links.
11Equipment configuration and deployment (contd)
- Additional services should be delivered to all
NRENs - Multicast should be enabled on all routers
- QoS required for sensitive applications and
congested links. All routers should have at least
a common DSCP marking policy, and a traffic
shaping policy to reserve bandwidth for specific
applications - VoIP - as telephone costs are very high in SEE,
VoIP should be provisioned on all routers, for
basic troubleshooting calls, voice meetings, etc. - IPv6 for testing
12Initial test period
- After the deployment of the equipment, a short
test period will ensure the proper operation of
all links and equipment - During the test period additional tests will be
run to verify the operation of links and
equipment (ping tests, simulated traffic loads,
simulated link failures) - This is an extension of the acceptance tests
- Reports on the test results will be made
available on-line - Eventual equipment configuration changes will be
made - Necessary phase prior to going into production
state - Management and monitoring tools should be in
place by now - Activity duration 4 months
13Transition to production state
- Going from test phase into production state
shouldnt pose any problems but - Connectivity should be verified for all NRENs
(internally and to GEANT) - Traffic load on all links should be checked
(congestion gt upgrades?)
14Additional services
- Additional services (DNS, mail relay, ftp, web,
LDAP, etc) can be offered by any/all of the
participating NRENs - The task of administering the .seeren.org domain,
along with its public services can be distributed
among the participating NRENs.
15Performance monitoring
- The monitoring tools should be installed during
the initial test phase - basic SNMP monitoring will be performed on all
routers for all NRENs - flow analysis tools (if the routers support it)
flowscan/cflowd for detailed analysis - additional monitoring tools if needed
- online reports and graphs should be made
available for all NRENs
16Technical support and problem solving
- Each NREN should have at least one person that
can be contacted in case of an emergency. - The contact person should be able to solve most
of the problems that arise - basic communication tools e-mail, phone, fax, an
maybe IP phones - Implementing a trouble ticketing system (with web
interface and support for mail messages) - Mailing list for technical issues and problem
reporting - Activity duration until the end of the project
and beyond
17Problem - loss of connectivity
- Can be tackled with if there are redundant links,
and the routing policy should provision for this
situation - The link failure should be signaled to the
contracted carrier by any of the link ends - The links should maintain the 99 availability
rate
18Problem - DoS Attacks
- Very common problem in todays networks
- Can be equal to loss of connectivity if you are
unlucky - Can be detected using various tools (flow
analysis, network based sniffers, etc). - Can be signaled to the upstream NREN using BGP
communities to be automatically filtered
19Problem solving
- All other problems must be solved using basic
communication tools - e-mail, phone, fax
- mailing list(s) for support questions
- trouble ticketing system